IBOV 169,295.41 ▼ 1.83% IPC MEX 71,204.98 ▼ 0.84% MERVAL 2,848,945 — — USD/BRL5.78▲ 2.04% USD/MXN18.51▲ 0.02% USD/CLP998.03▲ 0.32% USD/COP3,311▲ 0.25% USD/PEN3.41▲ 0.06% USD/ARS1,550▲ 0.37% USD/UYU40.61▲ 0.05% USD/PYG6,186▼ 0.16% USD/BOB 11.59 — 0.00% USD/DOP60.36▼ 0.38% USD/CRC442.56▼ 0.04% USD/GTQ7.64▼ 0.05% USD/HNL26.90▼ 0.05% USD/NIO 36.62 — 0.00% USD/VES913.46▲ 0.06% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD157.69— 0.00% USD/TTD6.72▼ 0.44% EUR/BRL6.36▲ 1.77% BRENT 92.08 ▼ 3.92% WTI 85.30 ▼ 3.68% IRON ORE 161.91 — — COPPER 5.99 ▼ 1.41% GOLD 3,856 ▼ 0.78% SILVER 46.94 ▼ 4.26% SOY 1,227 ▼ 1.31% CORN 448.50 ▲ 0.67% WHEAT 601.75 ▲ 1.43% COFFEE 274.40 ▼ 1.53% SUGAR 18.10 ▼ 1.68% ORANGE JUICE 135.75 ▼ 0.40% COTTON 81.31 ▲ 3.21% COCOA 5,200 ▲ 1.58% BEEF 224.38 ▲ 1.69% CATTLE 333.25 ▼ 1.70% LITHIUM 56.84 ▼ 3.27% PETR4 44.02 ▼ 2.83% VALE3 60.70 ▼ 4.41% ITUB4 41.30 ▼ 2.29% BBDC4 14.23 ▼ 2.00% ABEV3 15.87 ▲ 0.51% BBAS3 14.95 ▼ 0.99% B3SA3 14.81 ▼ 0.54% WEGE3 50.40 ▼ 1.77% PRIO3 62.63 ▼ 1.06% SUZB3 55.50 ▲ 1.33% RENT3 29.31 ▼ 2.53% AZZA3 16.14 ▲ 1.45% CSAN3 3.09 ▼ 0.32% RAIZ4 20.00 — 0.00% PCAR3 2.60 ▲ 1.56% GMAT3 4.13 ▼ 2.82% PSSA3 45.54 ▼ 1.87% CVCB3 0.79 ▼ 4.82% POSI3 3.10 ▼ 1.59% SLCE3 17.85 ▼ 2.35% NATU3 4.90 ▼ 4.48% BRKM5 2.84 ▼ 5.96% RANI3 8.19 ▲ 0.12% CSNA3 3.68 ▼ 1.08% IBOV 169,295.41 ▼ 1.83% IPC MEX 71,204.98 ▼ 0.84% MERVAL 2,848,945 — — USD/BRL 5.78 ▲ 2.04% USD/MXN 18.52 ▲ 0.03% USD/CLP 998.03 ▲ 0.32% USD/COP 3,311 ▲ 0.25% USD/PEN 3.41 ▲ 0.06% USD/ARS 1,550 ▲ 0.37% USD/UYU 40.61 ▲ 0.05% USD/PYG 6,186 ▼ 0.16% USD/BOB 11.59 — 0.00% USD/DOP 60.36 ▼ 0.38% USD/CRC 442.56 ▼ 0.04% USD/GTQ 7.64 ▼ 0.05% USD/HNL 26.90 ▼ 0.05% USD/NIO 36.62 — 0.00% USD/VES 913.46 ▲ 0.06% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.69 ▲ 2.75% USD/TTD 6.72 ▲ 2.12% EUR/BRL 6.36 ▲ 1.77% BRENT 92.08 ▼ 3.92% WTI 85.30 ▼ 3.68% IRON ORE 161.91 — — COPPER 5.99 ▼ 1.41% GOLD 3,856 ▼ 0.78% SILVER 46.94 ▼ 4.26% SOY 1,227 ▼ 1.31% CORN 448.50 ▲ 0.67% WHEAT 601.75 ▲ 1.43% COFFEE 274.40 ▼ 1.53% SUGAR 18.10 ▼ 1.68% ORANGE JUICE 135.75 ▼ 0.40% COTTON 81.31 ▲ 3.21% COCOA 5,200 ▲ 1.58% BEEF 224.38 ▲ 1.69% CATTLE 333.25 ▼ 1.70% LITHIUM 56.84 ▼ 3.27% PETR4 44.02 ▼ 2.83% VALE3 60.70 ▼ 4.41% ITUB4 41.30 ▼ 2.29% BBDC4 14.23 ▼ 2.00% ABEV3 15.87 ▲ 0.51% BBAS3 14.95 ▼ 0.99% B3SA3 14.81 ▼ 0.54% WEGE3 50.40 ▼ 1.77% PRIO3 62.63 ▼ 1.06% SUZB3 55.50 ▲ 1.33% RENT3 29.31 ▼ 2.53% AZZA3 16.14 ▲ 1.45% CSAN3 3.09 ▼ 0.32% RAIZ4 20.00 — 0.00% PCAR3 2.60 ▲ 1.56% GMAT3 4.13 ▼ 2.82% PSSA3 45.54 ▼ 1.87% CVCB3 0.79 ▼ 4.82% POSI3 3.10 ▼ 1.59% SLCE3 17.85 ▼ 2.35% NATU3 4.90 ▼ 4.48% BRKM5 2.84 ▼ 5.96% RANI3 8.19 ▲ 0.12% CSNA3 3.68 ▼ 1.08%
since 2009
Monday, November 16, 2026

Argentina Latin America

Rio Tinto Plans US$2.7 Billion Lithium Project in Salta

By · · 3 min read

Satellite view of lithium brine evaporation ponds on a salt flat in Argentina
Rio Tinto Plans US$2.7 Billion Lithium Project in Salta Photo: Coordenação-Geral de Observação da Terra/INPE, CC BY-SA 2.0, Wikimedia Commons.
RT
Ask Rio Times
Latin American markets, currencies and companies.
Open the full Ask Rio Times →

BUSINESS · ARGENTINA

Key Facts

  • —The country Argentina, in the lithium-rich Puna highlands of Salta province in the far north-west.
  • —What happened On 2 October 2026 in Paris, Governor Gustavo Sáenz said Rio Tinto confirmed US$2.7 billion for its Rincón lithium project, El Tribuno and Aries reported.
  • —The numbers 50,000 tonnes a year of battery-grade lithium carbonate from two 25,000-tonne lines, the first due in 2028. About 600 permanent jobs in operation, per the same reports.
  • —What it means for you Argentina’s lithium output is set to keep rising, adding export dollars. Suppliers and workers in Salta stand to gain most during the 2027 construction peak.
  • —Still open Rio Tinto had not published its own update on 2 October. Its March figures differ (US$2.5 billion, about 60,000 tonnes), and 2028 lithium prices are uncertain.

The Rio Tinto lithium project at Rincón, in Argentina’s Salta province, is to cost US$2.7 billion and produce 50,000 tonnes a year. Governor Gustavo Sáenz gave the figures on Friday 2 October after meeting company executives in Paris.

Free daily brief — no card needed
Get every Argentina story in one morning email
We build you a personalized brief around the topics you follow — free for 7 days. Love it? Your first month after that is US$1.

The project is not new, but the meeting set out a clearer timetable and a job count. The first of two production lines is due to start in 2028, El Tribuno and the Salta outlet Aries reported.

What was confirmed in Paris

Sáenz met Jérôme Pécresse, who runs Rio Tinto’s aluminium and lithium business, and business development manager Joey Kairala. The talks took place during Argentina Week, a promotion event in the French capital.

According to both reports, Rincón will make battery-grade lithium carbonate in two lines of 25,000 tonnes each. That chemical is the form of lithium most widely sold to battery makers.

Rio Times chart: jobs at Rio Tinto's Rincón lithium project in Salta by phase
Jobs at Rincón by phase: 255 direct and 2,400 indirect in construction now, more than 4,000 indirect at the April–July 2027 peak, about 600 direct in operation. Source: El Tribuno and Aries, 2 Oct 2026.

The jobs figures are the main new detail. Construction currently employs 255 people directly and about 2,400 indirectly, the reports said.

Indirect employment is expected to pass 4,000 between April and July 2027. Once running, the plant should employ around 600 people directly.

How the Rio Tinto lithium plan got here

Rio Tinto agreed to buy Rincón in 2021. In May 2025 it became the first mining project approved under the RIGI, the national incentive scheme for large investments, Cadena 3 reported at the time.

Salta’s mining authority then issued the environmental impact declaration in August 2025, after a public hearing and consultation with Indigenous communities. In March 2026, Reporte Minero said Rincón shipped its first 200 tonnes of lithium carbonate to Shanghai.

Sáenz framed the plan as a test of whether mining reaches local people. “We want each investment to translate into employment, growth of local suppliers, infrastructure and new opportunities,” he said, as quoted by Aries.

Why it matters, and the risks

Salta already hosts several large lithium developments, including Ganfeng’s projects. President Javier Milei took provincial governors to Argentina Week to court investors.

Lithium prices were low when the permit was granted in 2025, LM Neuquén Más Energía noted. A plant starting in 2028 will sell into whatever market exists then.

The stated figures also vary. In March, Rio Tinto put the cost at US$2.5 billion and said it plans to build for about 60,000 tonnes a year.

Salta’s 2025 environmental permit covers 50,000 tonnes, matching Friday’s figure. The US$2.7 billion is the sum approved under the RIGI in 2025.

What Is Not Yet Known

Rio Tinto had not issued its own statement on the Paris meeting by Friday afternoon. The figures so far come from the provincial side, as reported by El Tribuno and Aries.

In March, Rio Tinto secured US$1.175 billion in loans from four lenders, including the International Finance Corporation, the World Bank’s private-sector arm. Whether the new timetable changes that funding plan has not been disclosed.

It is also unclear how many of the 600 permanent jobs will go to Salta residents. Earlier Argentine coverage set out the wider context in Milei Takes Governors to Paris to Trade Deals for an End to Primaries and Argentina Lithium: China’s Ganfeng Locks In a Three-Project Salta Megadevelopment.

Sources: El Tribuno (2 Oct 2026); Aries (2 Oct 2026); Cadena 3 (20 May 2025); LM Neuquén Más Energía (28 Aug 2025); Reporte Minero (10 Mar 2026); Rio Tinto (11 Mar 2026).

This article was produced by The Rio Times’ automated AI newsroom. Editorial responsibility: Matthias Camenzind, Publisher and Editor-in-Chief. The Rio Times also runs Ask Rio Times, which answers from 100,000+ of our own articles, the daily Latin America Power Map, and prediction-market odds on elections and markets.. How we use AI · Report an error

LatAm Markets: Live Signals → — real-time movers, turnover leaders and FX across Latin America.

The LatAm Brief

One email, every weekday morning. What moved in Latin American markets, politics and expat life.

Yesterday’s subject line: “Lula weighs a record 40 ministries”

Brazil runoff date: Sunday, October 25, poll closing times and when results start · Brazil runoff polls: Flávio 51%, Lula 49% · Kalshi and Polymarket odds

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.