IBOV 171,347.61 ▼ 0.52% IPC MEX 71,866.30 ▲ 0.66% MERVAL 2,848,945 — — USD/BRL5.58▲ 1.33% USD/MXN18.63▲ 0.55% USD/CLP983.76▲ 1.71% USD/COP3,300▲ 5.77% USD/PEN3.41▲ 0.02% USD/ARS1,545▼ 0.03% USD/UYU40.43▲ 3.52% USD/PYG6,196▲ 1.99% USD/BOB11.68▲ 0.19% USD/DOP60.46▲ 2.41% USD/CRC445.62▲ 1.24% USD/GTQ7.64▲ 2.97% USD/HNL26.89▲ 3.05% USD/NIO36.62▲ 2.53% USD/VES897.02▼ 0.13% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD157.69▲ 2.36% USD/TTD6.72▲ 2.10% EUR/BRL6.23▲ 1.67% BRENT 91.72 ▼ 0.92% WTI 86.20 ▼ 0.75% IRON ORE 161.91 — — COPPER 6.24 ▼ 1.33% GOLD 4,029 ▼ 2.08% SILVER 51.22 ▼ 2.57% SOY 1,227 ▲ 3.76% CORN 449.75 ▲ 2.39% WHEAT 592.25 ▲ 0.72% COFFEE 266.00 ▼ 2.78% SUGAR 18.15 ▼ 0.33% ORANGE JUICE 147.10 ▲ 6.32% COTTON 78.28 ▼ 0.63% COCOA 4,863 ▼ 2.82% BEEF 222.70 ▲ 3.01% CATTLE 326.63 ▼ 0.53% LITHIUM 59.85 ▼ 2.44% PETR4 45.05 ▼ 0.31% VALE3 64.91 ▼ 1.82% ITUB4 41.19 ▼ 1.27% BBDC4 14.31 ▼ 2.52% ABEV3 15.64 ▲ 0.19% BBAS3 16.84 ▼ 1.06% B3SA3 14.41 ▼ 2.96% WEGE3 50.68 ▼ 0.12% PRIO3 59.49 ▲ 0.17% SUZB3 54.72 ▲ 0.96% RENT3 29.72 ▼ 3.60% AZZA3 14.62 ▼ 3.31% CSAN3 2.67 ▼ 3.61% RAIZ4 24.40 ▼ 12.86% PCAR3 2.42 ▼ 0.41% GMAT3 3.81 ▼ 0.52% PSSA3 46.06 ▲ 0.90% CVCB3 0.86 ▼ 1.15% POSI3 2.97 ▼ 1.98% SLCE3 17.00 ▼ 1.73% NATU3 5.55 ▼ 2.80% BRKM5 2.96 ▼ 1.99% RANI3 8.36 ▼ 4.57% CSNA3 4.43 ▼ 1.34% IBOV 171,347.61 ▼ 0.52% IPC MEX 71,866.30 ▲ 0.66% MERVAL 2,848,945 — — USD/BRL 5.58 ▲ 1.37% USD/MXN 18.64 ▲ 0.56% USD/CLP 983.93 ▲ 1.73% USD/COP 3,300 ▲ 5.77% USD/PEN 3.41 ▲ 0.05% USD/ARS 1,545 ▼ 0.03% USD/UYU 40.43 ▲ 3.52% USD/PYG 6,196 ▲ 1.99% USD/BOB 11.68 ▲ 0.19% USD/DOP 60.46 ▲ 2.41% USD/CRC 445.62 ▲ 1.24% USD/GTQ 7.64 ▲ 2.97% USD/HNL 26.89 ▲ 3.05% USD/NIO 36.62 ▲ 2.53% USD/VES 897.02 ▼ 0.13% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.69 ▲ 2.36% USD/TTD 6.72 ▲ 2.10% EUR/BRL 6.23 ▲ 1.66% BRENT 91.72 ▼ 0.92% WTI 86.20 ▼ 0.75% IRON ORE 161.91 — — COPPER 6.24 ▼ 1.33% GOLD 4,029 ▼ 2.08% SILVER 51.22 ▼ 2.57% SOY 1,227 ▲ 3.76% CORN 449.75 ▲ 2.39% WHEAT 592.25 ▲ 0.72% COFFEE 266.00 ▼ 2.78% SUGAR 18.15 ▼ 0.33% ORANGE JUICE 147.10 ▲ 6.32% COTTON 78.28 ▼ 0.63% COCOA 4,863 ▼ 2.82% BEEF 222.70 ▲ 3.01% CATTLE 326.63 ▼ 0.53% LITHIUM 59.85 ▼ 2.44% PETR4 45.05 ▼ 0.31% VALE3 64.91 ▼ 1.82% ITUB4 41.19 ▼ 1.27% BBDC4 14.31 ▼ 2.52% ABEV3 15.64 ▲ 0.19% BBAS3 16.84 ▼ 1.06% B3SA3 14.41 ▼ 2.96% WEGE3 50.68 ▼ 0.12% PRIO3 59.49 ▲ 0.17% SUZB3 54.72 ▲ 0.96% RENT3 29.72 ▼ 3.60% AZZA3 14.62 ▼ 3.31% CSAN3 2.67 ▼ 3.61% RAIZ4 24.40 ▼ 12.86% PCAR3 2.42 ▼ 0.41% GMAT3 3.81 ▼ 0.52% PSSA3 46.06 ▲ 0.90% CVCB3 0.86 ▼ 1.15% POSI3 2.97 ▼ 1.98% SLCE3 17.00 ▼ 1.73% NATU3 5.55 ▼ 2.80% BRKM5 2.96 ▼ 1.99% RANI3 8.36 ▼ 4.57% CSNA3 4.43 ▼ 1.34%
since 2009
Tuesday, November 10, 2026

Colombia Latin America

Cali Mayor Sees 4-Year Rebuild After Quake

By · · 5 min read
White two-storey corner building with arched windows and balconies, taped off, with rubble bags on the pavement
A damaged corner building in Cali's historic centre, photographed in mid-August 2026 after the earthquake. Photo: Tefita228 / Wikimedia Commons (CC BY 4.0)

COLOMBIA · DISASTER RECOVERY

Key Facts

  • What Mayor Alejandro Eder of Cali, in south-western Colombia, expects four years of rebuilding.
  • Cost The mayor puts the city’s recovery bill at about 10 trillion Colombian pesos (COP), or about US$3.06 billion.
  • Toll More than 150 people died in Cali in the 10 August earthquake.
  • Buildings 85 Cali buildings have been identified for demolition, according to city figures reported on 9 and 10 November.
  • Power Index Colombia ranks 6th of 14 in The Rio Times Latin America Power Index, with 51.1 points (November 2026 edition).

Three months after the earthquake, the mayor of Cali says the city is only at the start of a long road. He compares the rebuilding to a four-year marathon, and it is not yet clear how much the national government will contribute.

Free daily brief — no card needed
Get every Colombia story in one morning email
We build you a personalized brief around the topics you follow — free for 7 days. Love it? Your first month after that is US$1.

Alejandro Eder, the mayor of Cali, said on Tuesday 10 November 2026 that rebuilding after the city’s earthquake will take about four years. He spoke in a radio interview three months after the quake struck on Monday 10 August.

Cali is a city of south-western Colombia, in the Valle del Cauca department (state). Expats, travellers and anyone with ties to the city will feel how fast the recovery moves.

What the Mayor Said About the Timeline

“In three months, one does not recover or rebuild after an earthquake,” Eder said in the interview. He compared the process to a marathon lasting four years, of which the first three months have passed.

The four-year estimate is not new, because he gave a timeline of about four years on Tuesday 29 September 2026. He did so after meeting the national government’s economic team at the Casa de Nariño, Colombia’s presidential palace.

Visitors walk across a paved pedestrian esplanade with white railings and arched metal frames, with green trees and apartment towers behind under a cloudy sky
A pedestrian esplanade on the Bulevar del Río beside the Cali River, with visitors strolling under trees and tower blocks behind (undated file photo). Photo: Cathetovar / Wikimedia Commons (CC BY-SA 4.0)
RT
Ask Rio Times
17 years of Latin America reporting, on demand.
Open the full Ask Rio Times →

How Many People and Buildings Were Lost

The earthquake struck on Monday 10 August 2026, with a reported magnitude of 7.4. Its epicentre was at San José del Palmar, a town in Chocó, a Pacific-coast department (state).

The LatAm Brief

One email, every weekday morning. What moved in Latin American markets, politics and expat life.

Yesterday’s subject line: “Exxon takes a first step back to Venezuela”

Free. We send a confirmation link first — nothing arrives until you click it. Unsubscribe with one click in any edition. If you stop opening us for 30 days we stop sending by ourselves, as we assume the interest is no longer there. See our privacy policy. We never share your email.

More than 150 people died in Cali, according to the city’s count in September. Our earlier report tracked the national toll and damage in the first weeks.

City figures reported on 9 and 10 November put the number of buildings in Cali identified for demolition at 85. Earlier counts were lower, and the final number could change.

What the Rebuilding Will Cost

Eder puts the city’s recovery bill at about COP 10 trillion (about US$3.06 billion). That conversion uses the official market rate, known as the TRM (Tasa Representativa del Mercado), of COP 3,269.88 per US$ for 10 November 2026.

In Colombian usage the sum is written as “10 billones”, which means 10 trillion in English. On 30 October he put a wider request to the national government at COP 24 trillion (about US$7.3 billion), of which COP 10 trillion is for recovery.

In September a proposal reached Cali’s city council, the elected local legislature, to let Eder change up to 20% of the 2026 city budget until 30 November 2026. We could not confirm that it passed.

Who Pays and Who Leads the Recovery

The national government of President Abelardo de la Espriella has a reconstruction fund, the Fondo Milagro (Miracle Fund), headed by Jaime Andrés Uribe Tamayo. The full national contribution to Cali’s rebuilding is not clear.

The fund’s budget and the total national contribution are not known to us. Our report on rent aid and our one-month report show how the national response began.

What It Means for You

Residents and visitors should expect rebuilding to shape the city for years. Travellers should check with the city before booking.

Two events remain on the calendar: a Colombia v Chile football friendly in Cali on Friday 13 November 2026, a benefit match for quake victims, and the Feria de Cali salsa festival, traditionally held in late December. Readers who follow Colombia can use our Colombia coverage for updates.

What Is Not Known

No official total cost exists yet, and we do not know how much the national government in Bogotá will pay. The final number of demolitions is also open.

It is also unclear whether the council has approved the budget powers, which would end on 30 November. The official death toll for Cali is not settled either, because published counts differ.

Frequently Asked Questions

How long will rebuilding Cali take?

Mayor Alejandro Eder says about four years. He compared the effort to a marathon of four years, of which three months have passed.

How much will the rebuilding cost?

Eder puts the cost at about COP 10 trillion (about US$3.06 billion at the official exchange rate, the TRM, of COP 3,269.88 per US$ on 10 November 2026). No official total for all costs has been published.

How many people died in Cali?

More than 150 people died in Cali. Published counts differ slightly, so the official toll is not settled.

When did the earthquake strike?

It struck on Monday 10 August 2026, with a reported magnitude of 7.4. The epicentre was at San José del Palmar in Chocó.

Sources: Mayor of Cali Alejandro Eder, public statements, 10 November 2026; Alcaldía de Cali, the city government, cali.gov.co; Concejo de Cali, the city council; Superintendencia Financiera de Colombia, the financial regulator, official exchange rate (TRM) for 10 November 2026 via datos.gov.co.

This article was produced by The Rio Times’ automated AI newsroom. Editorial responsibility: Matthias Camenzind, Publisher and Editor-in-Chief. The Rio Times also runs Ask Rio Times, which answers from 100,000+ of our own articles, the daily Latin America Power Map, and prediction-market odds on elections and markets.. How we use AI · Report an error

Living in or visiting Cali? See our Cali city guide with rents, safety and upcoming concerts.

The Rio Times · Power Map
See who really holds power in Latin America
Click to open the Power Map →

Brazil runoff date: Sunday, October 25, poll closing times and when results start · Brazil runoff polls: Flávio 51%, Lula 49% · Kalshi and Polymarket odds

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.