IBOV 167,921.80 ▼ 0.75% IPC MEX 69,705.03 ▼ 0.12% MERVAL 92,079 ▼ 2.59% USD/BRL5.44▲ 1.17% USD/MXN18.79▼ 0.39% USD/CLP993.12▲ 0.49% USD/COP3,232▲ 2.08% USD/PEN3.47▲ 0.16% USD/ARS1,534▼ 0.29% USD/UYU40.19▲ 3.18% USD/PYG5,965▲ 5.35% USD/BOB12.07▲ 3.37% USD/DOP60.42▲ 0.50% USD/CRC451.45▲ 2.56% USD/GTQ7.64▲ 3.29% USD/HNL26.88▲ 0.49% USD/NIO36.62▲ 0.04% USD/VES887.03▼ 0.13% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD157.99▲ 2.89% USD/TTD6.71▲ 2.13% EUR/BRL6.08▲ 2.03% BRENT 109.58 ▼ 5.38% WTI 100.12 ▼ 1.61% IRON ORE 161.91 — — COPPER 6.65 ▲ 2.24% GOLD 4,073 ▲ 0.85% SILVER 54.49 ▲ 0.70% SOY 1,250 ▲ 0.70% CORN 450.25 ▼ 1.04% WHEAT 614.75 ▼ 0.20% COFFEE 294.35 ▼ 2.19% SUGAR 19.26 ▲ 0.84% ORANGE JUICE 143.20 ▲ 5.45% COTTON 77.90 ▼ 1.47% COCOA 5,581 ▲ 1.66% BEEF 230.73 ▲ 0.33% CATTLE 346.40 ▼ 1.00% LITHIUM 62.43 ▲ 1.89% PETR4 53.31 ▼ 1.06% VALE3 62.88 ▼ 2.33% ITUB4 41.42 ▼ 0.67% BBDC4 15.69 ▼ 1.63% ABEV3 15.40 ▲ 0.20% BBAS3 17.59 ▲ 0.69% B3SA3 15.27 ▲ 1.33% WEGE3 45.78 ▲ 2.81% PRIO3 69.21 ▼ 2.71% SUZB3 47.14 ▼ 0.55% RENT3 31.14 ▼ 1.67% AZZA3 16.72 ▲ 1.15% CSAN3 2.69 ▼ 2.89% RAIZ4 0.34 — 0.00% PCAR3 2.22 ▼ 3.48% GMAT3 3.74 ▲ 2.19% PSSA3 47.75 ▼ 0.89% CVCB3 0.98 — 0.00% POSI3 3.56 ▼ 0.84% SLCE3 16.97 ▼ 2.75% NATU3 5.68 ▼ 3.89% BRKM5 3.80 ▲ 19.50% RANI3 7.34 ▼ 0.54% CSNA3 4.76 ▼ 4.99% IBOV 167,921.80 ▼ 0.75% IPC MEX 69,705.03 ▼ 0.12% MERVAL 92,079 ▼ 2.59% USD/BRL 5.34 ▼ 1.32% USD/MXN 18.69 ▲ 0.62% USD/CLP 983.47 ▼ 0.57% USD/COP 3,149 ▲ 3.06% USD/PEN 3.45 ▲ 0.17% USD/ARS 1,537 ▼ 0.28% USD/UYU 40.21 ▲ 3.57% USD/PYG 5,803 ▲ 3.78% USD/BOB 11.97 ▲ 4.93% USD/DOP 60.54 ▲ 1.83% USD/CRC 451.24 ▲ 2.13% USD/GTQ 7.64 ▲ 3.23% USD/HNL 26.87 ▲ 3.37% USD/NIO 36.62 ▲ 2.81% USD/VES 885.08 ▼ 0.13% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.69 ▲ 2.63% USD/TTD 6.71 ▲ 2.07% EUR/BRL 5.95 ▲ 7.53% BRENT 109.58 ▼ 5.38% WTI 100.12 ▼ 1.61% IRON ORE 161.91 — — COPPER 6.65 ▲ 2.24% GOLD 4,073 ▲ 0.85% SILVER 54.49 ▲ 0.70% SOY 1,250 ▲ 0.70% CORN 450.25 ▼ 1.04% WHEAT 614.75 ▼ 0.20% COFFEE 294.35 ▼ 2.19% SUGAR 19.26 ▲ 0.84% ORANGE JUICE 143.20 ▲ 5.45% COTTON 77.90 ▼ 1.47% COCOA 5,581 ▲ 1.66% BEEF 230.73 ▲ 0.33% CATTLE 346.40 ▼ 1.00% LITHIUM 62.43 ▲ 1.89% PETR4 53.31 ▼ 1.06% VALE3 62.88 ▼ 2.33% ITUB4 41.42 ▼ 0.67% BBDC4 15.69 ▼ 1.63% ABEV3 15.40 ▲ 0.20% BBAS3 17.59 ▲ 0.69% B3SA3 15.27 ▲ 1.33% WEGE3 45.78 ▲ 2.81% PRIO3 69.21 ▼ 2.71% SUZB3 47.14 ▼ 0.55% RENT3 31.14 ▼ 1.67% AZZA3 16.72 ▲ 1.15% CSAN3 2.69 ▼ 2.89% RAIZ4 0.34 — 0.00% PCAR3 2.22 ▼ 3.48% GMAT3 3.74 ▲ 2.19% PSSA3 47.75 ▼ 0.89% CVCB3 0.98 — 0.00% POSI3 3.56 ▼ 0.84% SLCE3 16.97 ▼ 2.75% NATU3 5.68 ▼ 3.89% BRKM5 3.80 ▲ 19.50% RANI3 7.34 ▼ 0.54% CSNA3 4.76 ▼ 4.99%
since 2009
Saturday, October 31, 2026

Energy Latin America

Suriname’s GranMorgu Oil Stays on Schedule

By · October 31, 2026 · 6 min read
The Paramaribo waterfront seen from the Suriname River, with historic wooden buildings
File photo, 2021. The Paramaribo waterfront on the Suriname River. (Photo: Rafaeljantz, CC BY-SA 4.0, via Wikimedia Commons)

SURINAME · ENERGY

Key Facts

  • The country Suriname is a small Dutch-speaking South American country next to Guyana that has pumped oil only onshore so far.
  • Why it matters GranMorgu is its first offshore oil project, run by TotalEnergies with US company APA Corporation as a partner, so its timetable drives the budget, oil-linked bond payouts and US supplier work.
  • Why now Fresh progress updates from the operator, the state oil company and a minister came between 21 September and 30 October 2026, with drilling due to begin in December or January.
  • What happened GranMorgu is roughly halfway through its execution phase and first oil is still planned for 2028. Production drilling starts in December or early January 2027, depending on the account.
  • The numbers The fields hold more than 750 million barrels of recoverable oil, the production ship is designed for 220,000 barrels a day, and about 800 people work on the project directly.
  • What it means for you US investors in Suriname’s oil-linked debt, US oilfield suppliers and Houston-based APA are exposed to the 2028 start date, so any slip would matter more than today’s schedule.
  • Still open The exact first-drilling date, the month of first oil and the final cost are not confirmed.

In Plain English

GranMorgu is the name of TotalEnergies’ offshore oil project in Suriname, and it is Suriname’s first offshore oil development. First oil means the day crude is first produced and sent to market.

An FPSO, short for floating production, storage and offloading vessel, is a ship that processes oil from underwater wells and stores it before export. Staatsolie is Suriname’s state-owned oil company and a partner in the project.

TotalEnergies’ GranMorgu offshore oil project in Suriname is on schedule for first oil in 2028, the company’s Suriname general manager, Artur Nunes da Silva, said in an interview with Radio ABC published on 27 October 2026. He described the work as roughly halfway through, with drilling due to start in early January 2027 with two rigs, the Suriname Herald reported on 30 October.

TotalEnergies operates the project with Suriname’s state oil company Staatsolie and US company APA Corporation as partners, and the updates follow earlier subsea construction news. For US readers the stakes include a Houston-based partner, US oilfield contractors and the oil-linked payout on Suriname’s restructured bonds.

What the Operator Says Is on Track

Da Silva said the project has moved from preparation, studies, engineering and contract talks into actual execution. “Now it’s the money time,” he said, according to Radio ABC.

TotalEnergies’ own release of 19 September 2026 said GranMorgu has progressed according to schedule since the final investment decision in October 2024, with the drilling campaign and offshore installation scheduled to begin in early 2027. A TotalEnergies Suriname update of 7 October 2026 said the project has reached 50% of execution and remains on track for first oil in 2028.

The floating production ship is still being finished at three yards in China, where its tests are also being run, and is planned to leave for Suriname in early 2028. After arrival it will be installed and connected to the subsea pipes, the Suriname Herald wrote.

Two port cranes lifting container spreaders at the harbor of Paramaribo, Suriname
File photo, 2009. Cranes at the harbor of Paramaribo, Suriname. (Photo: Mark Ahsmann, CC BY-SA 3.0, via Wikimedia Commons)

Drilling and the Subsea Work

Da Silva said drilling begins in early January 2027 with two rigs, according to the Suriname Herald’s account of his interview, while Radio ABC’s summary says only that the first drilling steps come in January 2027. Part of the equipment for drilling and installation is already at logistics bases in Suriname, and TotalEnergies says the first major subsea production equipment has reached its Kuldipsingh Port Facility.

Oil, Gas and Environment Minister Patrick Brunings gave a different start, telling reporters before a Council of Ministers meeting that production drilling begins in December and that about 43% of the project is done. His account, published on 22 October, also said drill ships are expected soon in Surinamese waters.

What the Project Is

APA says GranMorgu will produce from the Krabdagu and Sapakara oil discoveries, where appraisal drilling confirmed gross estimated recoverable resources of more than 750 million barrels. The oil will flow through subsea wells to a floating production ship about 150 kilometers off the coast, with a capacity of 220,000 barrels a day.

TotalEnergies and APA took the final investment decision in October 2024, and APA lists first oil as expected in 2028. President Jennifer Geerlings-Simons said on 30 September that the government expects first oil from Block 58 around the middle of 2028 and called 2027 the preparation year.

Jobs and Local Suppliers

Da Silva said about 800 people now work directly on the project, more than first expected, because more Surinamese met the job requirements and more work could be done locally. More than 150 foreign employees are posted through TotalEnergies, with more at other companies.

Brunings said nearly 70% of the staff at the US contractor Halliburton in Suriname are Surinamese. Geerlings-Simons said a local content law is due to go to the National Assembly in 2027, before first oil.

Partner Staatsolie Backs the Timetable

Staatsolie said on 21 September 2026 that construction of the production ship, fabrication of key offshore components and preparations for drilling the production wells were progressing according to schedule. TotalEnergies chairman Patrick Pouyanné had visited Suriname on 19 September and toured the port where much of the logistics takes place.

Staatsolie Managing Director Annand Jagesar thanked TotalEnergies for enabling the project to progress “according to schedule and within budget”. Staatsolie also said a new exploration campaign is planned in Block 58 in 2027, and that more than 100 Surinamese companies already supply the project.

What It Means for You

US investors following Suriname’s oil-linked bond payout and US oilfield suppliers have the most direct exposure to a 2028 start date. A confirmed drilling start in December or January would be the next hard marker, because production cannot begin before wells are drilled and connected.

Visitors to Suriname can expect more oil-industry activity around Paramaribo, since Staatsolie says a large share of the project logistics runs through the port. The updates also show that the government and the operator are giving the same headline message of an on-time project.

What Is Not Known

The exact date of first drilling is not settled, because a minister gave December while the operator’s manager gave early January 2027. Only the year 2028 is confirmed by the operator, and the president has pointed to the middle of the year without naming a month.

TotalEnergies’ Suriname site puts total investment at around US$10.5 billion, but the share already spent was not stated in the updates reviewed. It is also unclear whether the minister’s 43% completion figure and the operator’s 50% execution figure measure the same thing.

Frequently Asked Questions

When will Suriname’s GranMorgu oil project start production?

First oil is planned for 2028, according to TotalEnergies’ Suriname manager and partner Staatsolie. President Jennifer Geerlings-Simons has pointed to around the middle of 2028.

Who owns the GranMorgu project?

TotalEnergies operates the project, with APA Corporation and Suriname’s state oil company Staatsolie as partners. Staatsolie describes its own interest as 20%.

How much oil will GranMorgu produce?

APA says the fields hold more than 750 million barrels of gross estimated recoverable oil. The floating production ship is designed for 220,000 barrels a day.

When does GranMorgu drilling begin?

TotalEnergies’ Suriname manager said drilling steps begin in January 2027, and TotalEnergies’ own release puts the drilling campaign in early 2027. Minister Patrick Brunings said production drilling begins in December.

How many jobs has GranMorgu created?

About 800 people work directly on the project, according to TotalEnergies’ Suriname manager. Staatsolie says more than 100 Surinamese companies supply goods and services.

Sources: Staatsolie, news release on the TotalEnergies CEO visit and GranMorgu progress, 21 September 2026; TotalEnergies Suriname, press release, 19 September 2026; TotalEnergies Suriname, GranMorgu milestone update, 7 October 2026; TotalEnergies Suriname, GranMorgu project page, opened 31 October 2026; APA Corporation, Suriname portfolio page, opened 31 October 2026; Radio ABC, GranMorgu-project levert nu al 800 directe banen op, 27 October 2026; Suriname Herald, 30 October 2026; Suriname Herald, 22 October 2026; Radio ABC, 30 September 2026.

This article was produced by The Rio Times’ automated newsroom system. How we use AI · Report an error · Editorial responsibility: Matthias Camenzind, Editor-in-Chief

RT
Ask Rio Times
17 years of Latin America reporting, on demand.
Open the full Ask Rio Times →
The Rio Times · Power Map
See who really holds power in Latin America
Click to open the Power Map →

Brazil runoff date: Sunday, October 25, poll closing times and when results start · Brazil runoff polls: Flávio 51%, Lula 49% · Kalshi and Polymarket odds

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.