IBOV 187,206.89 ▼ 0.56% IPSA 11,220.10 ▼ 0.16% IPC MEX 63,924.77 ▼ 0.28% MERVAL 3,098,898 ▼ 1.87% COLCAP 2,589.69 ▼ 1.41% BVL PERÚ 59,373.28 ▼ 0.32% USD/BRL5.13— 0.00% USD/MXN16.96▼ 0.01% USD/CLP941.13— 0.00% USD/COP3,077▼ 0.78% USD/PEN3.35▼ 0.01% USD/ARS1,509— 0.00% USD/UYU40.26▲ 3.12% USD/PYG5,903▲ 3.35% USD/BOB11.98▼ 2.70% USD/DOP58.96▲ 0.56% USD/CRC447.55▲ 1.64% USD/GTQ7.63▲ 2.97% USD/HNL26.85▲ 3.13% USD/NIO36.62▲ 2.58% USD/VES830.41▼ 1.28% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD 157.28 — 0.00% USD/TTD6.74▲ 2.35% EUR/BRL5.95▲ 0.25% BRENT 88.88 ▼ 0.03% WTI 83.11 ▼ 0.11% IRON ORE 161.91 — — COPPER 6.61 ▲ 0.03% GOLD 4,461 ▲ 1.78% SILVER 65.59 ▲ 1.26% SOY 1,184 ▲ 3.20% CORN 480.50 ▲ 10.02% WHEAT 655.00 ▲ 3.93% COFFEE 317.25 ▼ 5.51% SUGAR 16.43 ▼ 1.79% ORANGE JUICE 138.55 ▼ 0.47% COTTON 85.03 ▲ 2.33% COCOA 5,719 ▲ 3.18% BEEF 223.60 ▼ 3.93% CATTLE 339.10 ▼ 3.16% LITHIUM 75.20 ▲ 1.47% PETR4 41.64 ▼ 0.05% VALE3 72.97 ▲ 0.83% ITUB4 38.60 ▼ 1.03% BBDC4 16.85 ▲ 0.36% ABEV3 14.89 ▼ 0.80% BBAS3 19.37 ▲ 0.47% B3SA3 14.26 ▼ 0.21% WEGE3 47.59 ▲ 0.49% PRIO3 59.14 ▼ 0.19% SUZB3 41.33 ▲ 2.35% RENT3 34.68 ▼ 0.09% AZZA3 15.89 ▼ 2.63% CSAN3 3.22 ▼ 1.83% RAIZ4 0.25 — 0.00% PCAR3 2.75 ▼ 0.36% GMAT3 3.65 ▼ 1.08% PSSA3 48.13 ▼ 0.54% CVCB3 1.33 ▼ 2.92% POSI3 3.36 ▲ 2.44% SLCE3 13.34 ▲ 0.30% NATU3 8.14 ▼ 0.73% IBOV 187,206.89 ▼ 0.56% IPSA 11,220.10 ▼ 0.16% IPC MEX 63,924.77 ▼ 0.28% MERVAL 3,098,898 ▼ 1.87% COLCAP 2,589.69 ▼ 1.41% BVL PERÚ 59,373.28 ▼ 0.32% USD/BRL 5.16 ▲ 0.01% USD/MXN 17.06 ▼ 0.24% USD/CLP 913.98 ▲ 0.04% USD/COP 3,140 ▲ 0.03% USD/PEN 3.36 ▼ 0.66% USD/ARS 1,493 ▲ 0.10% USD/UYU 40.27 ▲ 1.24% USD/PYG 5,939 ▲ 1.68% USD/BOB 11.64 ▼ 0.76% USD/DOP 58.34 ▲ 1.25% USD/CRC 445.92 ▲ 0.89% USD/GTQ 7.62 ▲ 2.21% USD/HNL 26.79 ▲ 1.57% USD/NIO 36.62 ▲ 0.69% USD/VES 762.44 ▼ 0.13% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.28 — 0.00% USD/TTD 6.70 ▲ 0.61% EUR/BRL 5.95 ▲ 1.01% BRENT 88.88 ▼ 0.03% WTI 83.11 ▼ 0.11% IRON ORE 161.91 — — COPPER 6.61 ▲ 0.03% GOLD 4,461 ▲ 1.78% SILVER 65.59 ▲ 1.26% SOY 1,184 ▲ 3.20% CORN 480.50 ▲ 10.02% WHEAT 655.00 ▲ 3.93% COFFEE 317.25 ▼ 5.51% SUGAR 16.43 ▼ 1.79% ORANGE JUICE 138.55 ▼ 0.47% COTTON 85.03 ▲ 2.33% COCOA 5,719 ▲ 3.18% BEEF 223.60 ▼ 3.93% CATTLE 339.10 ▼ 3.16% LITHIUM 75.20 ▲ 1.47% PETR4 41.64 ▼ 0.05% VALE3 72.97 ▲ 0.83% ITUB4 38.60 ▼ 1.03% BBDC4 16.85 ▲ 0.36% ABEV3 14.89 ▼ 0.80% BBAS3 19.37 ▲ 0.47% B3SA3 14.26 ▼ 0.21% WEGE3 47.59 ▲ 0.49% PRIO3 59.14 ▼ 0.19% SUZB3 41.33 ▲ 2.35% RENT3 34.68 ▼ 0.09% AZZA3 15.89 ▼ 2.63% CSAN3 3.22 ▼ 1.83% RAIZ4 0.25 — 0.00% PCAR3 2.75 ▼ 0.36% GMAT3 3.65 ▼ 1.08% PSSA3 48.13 ▼ 0.54% CVCB3 1.33 ▼ 2.92% POSI3 3.36 ▲ 2.44% SLCE3 13.34 ▲ 0.30% NATU3 8.14 ▼ 0.73%
since 2009
Saturday, September 12, 2026

Business & Economy Costa Rica

Costa Rica Ordered to Fix Roundabouts Built Too Small for Its Own Trucks

By · September 12, 2026 · 5 min read

The LatAm Brief

One email, every weekday morning. What moved in Latin American markets, politics and expat life.

Yesterday’s subject line: “'The false peace is over' - Colombia”

Free. We send a confirmation link first — nothing arrives until you click it. Unsubscribe with one click in any edition. If you stop opening us for 30 days we stop sending by ourselves, as we assume the interest is no longer there. See our privacy policy. We never share your email.

COSTA RICA · INFRASTRUCTURE

Key Facts

  • The order The Contraloría General de la República has ordered CONAVI to correct safety defects on Route 32.
  • The defect Seven roundabouts were designed for a 16.8-metre articulated vehicle. The corridor carries 22.4-metre cargo units.
  • The gap 5.6 metres, which is why heavy vehicles cross into opposing lanes and pedestrian space.
  • The evidence Drone footage confirmed the violations.
  • The deadlines Corrective measures adopted by 30 October 2026, full implementation by 30 March 2027.
  • The cost US$1.4 million more on four roundabouts, on top of about US$6.8 million already spent against an original US$5.4 million budget.

Costa Rica built seven roundabouts on its main Caribbean freight corridor for trucks 5.6 metres shorter than the ones that use it.

A road in Costa Rica
Costa Rica Ordered to Fix Roundabouts Built Too Small for Its Own Trucks
One-stop reference
Company Intelligence
Every listed company in Latin America — financials, ownership and structure for 1,450+ companies across 26 exchanges, in one place.
Browse the directory →
RT
Ask Rio Times
Latin American markets, currencies and companies.
Open the full Ask Rio Times →

Costa Rica’s comptroller general has ordered the national roads council to correct design defects on Route 32, after finding that roundabouts on the country’s principal Caribbean freight corridor cannot accommodate the vehicles that use it.

What Is Wrong

Seven roundabouts on Route 32 were designed around a WB-15 articulated vehicle, 16.8 metres long. The corridor serves the Caribbean ports and carries WB-20 cargo units of 22.4 metres.

The difference is 5.6 metres, and the consequence is that heavy vehicles negotiating the roundabouts cross into opposing lanes, into pedestrian and cycle space, and onto green areas.

The Contraloría confirmed the violations with drone footage rather than relying on reported incidents, which is why the finding is difficult to contest.

Port and freight infrastructure
Route 32 serves the Caribbean ports at Limon and Moin.

What It Costs

Correcting four of the problematic roundabouts will require an additional US$1.4 million.

That comes on top of roughly US$6.8 million already spent against an original budget of US$5.4 million. The Contraloría describes the result as direct patrimonial damage to the public treasury.

CONAVI’s board must adopt corrective measures by 30 October 2026, with full implementation required by 30 March 2027.

Costa Rican road infrastructure
The comptroller describes direct patrimonial damage to the public treasury.

Why Route 32 Matters

Route 32 connects San José and the central valley to Limón and Moín on the Caribbean coast, which is where the great majority of Costa Rican container traffic moves.

It is a single corridor carrying a national export function, and it has a long history of landslides, closures and delayed expansion work. Every disruption on it reaches the ports within hours.

A design error that forces the country’s largest trucks to leave their lane at seven points on that corridor is therefore a freight problem as much as a safety one.

The comptroller’s finding does not allege corruption. It describes a specification that did not match the traffic, approved and built anyway, and a bill the public is paying twice.

How a Specification Error Survives to Construction

Roundabout geometry is set by a design vehicle, a standard template that determines turning radii and lane widths. Choosing the wrong template produces a structure that works on paper and fails in traffic.

The WB-15 and WB-20 designations are standard classifications, and the difference between them is exactly the kind of decision that is made once early in a design and then propagated through every drawing that follows.

What the comptroller is describing is therefore a single early error that nobody caught in review, on a corridor whose traffic composition was known to everyone involved.

The corrective bill of US$1.4 million on four roundabouts, against US$6.8 million already spent, is the price of that omission.

The Corridor’s Longer Record

Route 32 has been under expansion for the better part of a decade, on a project financed with Chinese credit and repeatedly delayed by landslides, design disputes and contractor problems.

The road crosses the Braulio Carrillo national park, where the terrain is steep, saturated and prone to slides, and closures there cut the central valley off from the Caribbean ports for hours or days at a time.

Costa Rica has no practical alternative route for container traffic to Limón and Moín. That is what turns every engineering problem on this corridor into a national logistics problem, and it is why a comptroller’s order about roundabout geometry is worth reporting at all.

Frequently Asked Questions

What did the Contraloría order?

That CONAVI correct safety defects on Route 32, with measures adopted by 30 October 2026 and implemented by 30 March 2027.

What is the defect?

Seven roundabouts designed for 16.8-metre articulated vehicles on a corridor carrying 22.4-metre cargo units.

What does it cost to fix?

An additional US$1.4 million on four roundabouts, against roughly US$6.8 million already spent on an original US$5.4 million budget.

How was it established?

Drone footage confirmed heavy vehicles crossing into opposing lanes and pedestrian space.

Why does Route 32 matter?

It is the main corridor between San José and the Caribbean ports at Limón and Moín, carrying most Costa Rican container traffic.

Sources: Contraloria General de la Republica, Delfino, La Nacion Costa Rica.

This article was drafted with automated assistance and reviewed before publication. How we use AI · Report an error

Read More from The Rio Times

The Rio Times · Power Map
See who really holds power in Latin America
Click to open the Power Map

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.