IBOV 164,643.46 ▼ 1.95% IPC MEX 69,779.20 ▼ 0.01% MERVAL 2,848,945 — — USD/BRL5.50▲ 1.18% USD/MXN18.78▲ 1.07% USD/CLP982.16▲ 0.45% USD/COP3,249▲ 6.57% USD/PEN3.46▼ 0.10% USD/ARS1,549▲ 0.24% USD/UYU40.19▲ 3.30% USD/PYG5,936▲ 4.80% USD/BOB12.05▲ 2.55% USD/DOP60.03▲ 2.27% USD/CRC449.50▲ 2.16% USD/GTQ7.64▲ 3.23% USD/HNL26.88▲ 3.34% USD/NIO36.62▲ 2.87% USD/VES888.88▼ 0.13% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD157.59▲ 2.48% USD/TTD6.69▲ 1.98% EUR/BRL6.16▲ 1.52% BRENT 109.58 ▼ 5.38% WTI 100.12 ▼ 1.61% IRON ORE 161.91 — — COPPER 6.65 ▲ 2.24% GOLD 4,073 ▲ 0.85% SILVER 54.49 ▲ 0.70% SOY 1,250 ▲ 0.70% CORN 450.25 ▼ 1.04% WHEAT 614.75 ▼ 0.20% COFFEE 294.35 ▼ 2.19% SUGAR 19.26 ▲ 0.84% ORANGE JUICE 143.20 ▲ 5.45% COTTON 77.90 ▼ 1.47% COCOA 5,581 ▲ 1.66% BEEF 230.73 ▲ 0.33% CATTLE 346.40 ▼ 1.00% LITHIUM 62.43 ▲ 1.89% PETR4 53.31 ▼ 1.06% VALE3 62.88 ▼ 2.33% ITUB4 41.42 ▼ 0.67% BBDC4 15.69 ▼ 1.63% ABEV3 15.40 ▲ 0.20% BBAS3 17.59 ▲ 0.69% B3SA3 15.27 ▲ 1.33% WEGE3 45.78 ▲ 2.81% PRIO3 69.21 ▼ 2.71% SUZB3 47.14 ▼ 0.55% RENT3 31.14 ▼ 1.67% AZZA3 16.72 ▲ 1.15% CSAN3 2.69 ▼ 2.89% RAIZ4 0.34 — 0.00% PCAR3 2.22 ▼ 3.48% GMAT3 3.74 ▲ 2.19% PSSA3 47.75 ▼ 0.89% CVCB3 0.98 — 0.00% POSI3 3.56 ▼ 0.84% SLCE3 16.97 ▼ 2.75% NATU3 5.68 ▼ 3.89% BRKM5 3.80 ▲ 19.50% RANI3 7.34 ▼ 0.54% CSNA3 4.76 ▼ 4.99% IBOV 164,643.46 ▼ 1.95% IPC MEX 69,779.20 ▼ 0.01% MERVAL 2,848,945 — — USD/BRL 5.34 ▼ 1.32% USD/MXN 18.69 ▲ 0.62% USD/CLP 983.47 ▼ 0.57% USD/COP 3,149 ▲ 3.06% USD/PEN 3.45 ▲ 0.17% USD/ARS 1,537 ▼ 0.28% USD/UYU 40.21 ▲ 3.57% USD/PYG 5,803 ▲ 3.78% USD/BOB 11.97 ▲ 4.93% USD/DOP 60.54 ▲ 1.83% USD/CRC 451.24 ▲ 2.13% USD/GTQ 7.64 ▲ 3.23% USD/HNL 26.87 ▲ 3.37% USD/NIO 36.62 ▲ 2.81% USD/VES 885.08 ▼ 0.13% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.69 ▲ 2.63% USD/TTD 6.71 ▲ 2.07% EUR/BRL 5.95 ▲ 7.53% BRENT 109.58 ▼ 5.38% WTI 100.12 ▼ 1.61% IRON ORE 161.91 — — COPPER 6.65 ▲ 2.24% GOLD 4,073 ▲ 0.85% SILVER 54.49 ▲ 0.70% SOY 1,250 ▲ 0.70% CORN 450.25 ▼ 1.04% WHEAT 614.75 ▼ 0.20% COFFEE 294.35 ▼ 2.19% SUGAR 19.26 ▲ 0.84% ORANGE JUICE 143.20 ▲ 5.45% COTTON 77.90 ▼ 1.47% COCOA 5,581 ▲ 1.66% BEEF 230.73 ▲ 0.33% CATTLE 346.40 ▼ 1.00% LITHIUM 62.43 ▲ 1.89% PETR4 53.31 ▼ 1.06% VALE3 62.88 ▼ 2.33% ITUB4 41.42 ▼ 0.67% BBDC4 15.69 ▼ 1.63% ABEV3 15.40 ▲ 0.20% BBAS3 17.59 ▲ 0.69% B3SA3 15.27 ▲ 1.33% WEGE3 45.78 ▲ 2.81% PRIO3 69.21 ▼ 2.71% SUZB3 47.14 ▼ 0.55% RENT3 31.14 ▼ 1.67% AZZA3 16.72 ▲ 1.15% CSAN3 2.69 ▼ 2.89% RAIZ4 0.34 — 0.00% PCAR3 2.22 ▼ 3.48% GMAT3 3.74 ▲ 2.19% PSSA3 47.75 ▼ 0.89% CVCB3 0.98 — 0.00% POSI3 3.56 ▼ 0.84% SLCE3 16.97 ▼ 2.75% NATU3 5.68 ▼ 3.89% BRKM5 3.80 ▲ 19.50% RANI3 7.34 ▼ 0.54% CSNA3 4.76 ▼ 4.99%
since 2009
Tuesday, November 3, 2026

Africa Africa & the Great Powers

Congo Approves a US$1.26 Billion Railway for the Lobito Corridor

By · August 4, 2026 · 6 min read
Lobito Corridor railway - copper processing plant in Congo's copper belt
A copper processing plant in the Congolese copper belt, the traffic the Lobito Corridor railway is meant to carry.

DR CONGO · MINING & LOGISTICS

Key Facts

The price tag: a draft collaboration convention valued at US$1.258 billion, adopted by the Council of Ministers, according to Zoom Eco’s 3 August 2026 account of the minutes.

Free daily brief — no card needed
Get every Africa story in one morning email
We build you a personalized brief around the topics you follow — free for 7 days. Love it? Your first month after that is US$1.

The line: Dilolo–Sakania, 1,004.5 km running from the Angolan border at Dilolo, across Congo’s copper belt, to the Zambian border at Sakania.

The target: rehabilitation should lift capacity progressively to 13.7 million tonnes a year, per the same report.

The contractor: Mota-Engil Africa — Portuguese, but 31% owned by China’s state-owned CCCC, per the group’s 27 April 2026 filing to Euronext Lisbon.

Who tabled it: Deputy Prime Minister and Transport Minister Jean-Pierre Bemba.

The wider route: the track is the Congolese leg of the Lobito Corridor, the Atlantic export path backed by Washington and Brussels.

The Lobito Corridor railway has moved from communiqué to cabinet approval. Congo’s Council of Ministers has adopted a draft US$1.258 billion collaboration convention with Mota-Engil Africa covering the financing, rehabilitation, operation and eventual transfer of the 1,004.5 km Dilolo–Sakania line, according to Zoom Eco’s 3 August 2026 report on the minutes.

What the Lobito Corridor railway deal actually covers

The convention is broader than a construction contract. It bundles financing, rehabilitation, modernisation, operation, maintenance and the eventual transfer of the line back to the state, Zoom Eco reported, citing the Council of Ministers minutes.

That structure matters more than the headline number. A concession that includes operation and maintenance puts a private operator, not a ministry, in charge of whether trains actually run on time.

Deputy Prime Minister and Transport Minister Jean-Pierre Bemba presented the file. The counterparty is Mota-Engil Africa, the African arm of a Portuguese group that has been building on the continent since 1946, when its founder opened a construction business in Angola.

One caveat belongs in the open. Zoom Eco places the relevant Council of Ministers sitting on Friday 31 July 2026, while earlier Congolese reporting dated approval of the underlying public-private partnership to the 94th Council of Ministers on 10 July 2026, when the file was tabled by the Minister of State for Planning standing in for Bemba.

Those are two stages of the same file rather than a contradiction. What has not happened yet is a signature.

Why 13.7 million tonnes is the number to watch

Congo’s problem has never been ore in the ground. It has been getting the ore to a ship.

Copper and cobalt from Katanga have historically travelled thousands of kilometres south and east, mostly by road, to ports in South Africa, Tanzania and Mozambique. Trucking is slow, expensive and exposed to every border queue on the way.

A rehabilitated line running progressively to 13.7 million tonnes a year changes that arithmetic. It shortens the journey to the Atlantic and moves a large share of volume off the road network.

For anyone modelling Congolese copper, the freight cost per tonne is the variable that moves. Rail capacity is the lever behind it.

The Atlantic route versus the eastern route

The Lobito Corridor is the reason this contract carries geopolitical weight. It runs west, from the Congolese copper belt through Angola to the Atlantic port of Lobito.

Washington and Brussels have both promoted the corridor as an alternative to the eastward routes, where Chinese-owned mining groups and Chinese-financed logistics dominate. The Dilolo–Sakania section is the Congolese piece of that map.

The choice of contractor complicates that framing rather than settling it. Mota-Engil is Portuguese and Porto-based, but China Communications Construction Company, the Chinese state-owned builder, holds 31.00% of it and has a vice-chairman on its board, according to the company’s own filing to Euronext Lisbon on 27 April 2026.

A corridor promoted as the Western alternative would therefore be built and run by a European contractor that is itself close to one-third Chinese state-owned. That is not a scandal, but it is the kind of detail that gets lost in the political framing.

Nor does the corridor remove China from the upstream picture. Chinese groups still own much of the production the railway would carry, a reminder that a corridor changes who moves the metal, not necessarily who owns it.

The money Kinshasa does not have spare

The convention lands against a stretched budget. Under the Budget Ministry’s commitment plan, the state intends to commit CDF 13,538.6 billion — about US$5.97 billion — between 1 July and 30 September 2026, Zoom Eco reported on 4 August 2026.

Defence takes the single largest quarterly envelope at CDF 2,343.3 billion, or roughly US$1.03 billion. Interior and security receive CDF 815.4 billion, about US$359 million.

Put plainly, Congo expects to commit roughly four-fifths as much to its army in a single quarter as the entire railway is said to cost. That is the fiscal context in which a concession structure becomes attractive.

A concession shifts the upfront capital to the operator and repays it through traffic over time. It is also why the traffic forecast, rather than the construction schedule, is the assumption that deserves scrutiny.

What to watch next on the Lobito Corridor railway

Three things will show whether this is real. The first is the financing package.

The US International Development Finance Corporation signed a letter of interest with Mota-Engil’s African engineering arm on 5 December 2025 covering up to US$1 billion. That is an expression of interest subject to full review, not a committed loan.

The second is the tariff. A corridor only wins volume if the door-to-port cost beats the trucking alternative that miners use today.

The third is the Angolan side, where Mota-Engil already holds 50% of Lobito Atlantic Railway, the consortium running the roughly 1,300 km from the port of Lobito to the Congolese border under a 30-year concession. The same operator on both sides of the frontier should ease coordination.

It also concentrates pricing power over Congolese exports in one company, a question Kinshasa has not answered in public. Until these land, the safest reading is that Kinshasa has approved the intention rather than signed the outcome.

Frequently Asked Questions

How much is the Congo Lobito Corridor railway deal worth?

The collaboration convention is valued at US$1.258 billion. Zoom Eco reported the figure on 3 August 2026, citing the Council of Ministers minutes.

Which railway line does the deal cover?

It covers the Dilolo–Sakania line, 1,004.5 km running from Dilolo on the Angolan border, across Congo’s copper belt, to Sakania on the Zambian border. The line is the Congolese leg of the Lobito Corridor.

Who will build and operate the line?

Mota-Engil Africa, the African arm of the Portuguese construction group, under a concession that includes operation, maintenance and eventual transfer to the state. Deputy Prime Minister and Transport Minister Jean-Pierre Bemba presented the file.

How much freight would the rebuilt line carry?

Rehabilitation is expected to lift capacity progressively to 13.7 million tonnes a year. That is the figure attributed to the Council of Ministers file.

Why does the Lobito Corridor matter geopolitically?

It sends Congolese copper and cobalt west to the Atlantic instead of east, and Washington and Brussels have promoted it as an alternative to Chinese-served export routes. Chinese groups nonetheless still own much of the production the corridor would carry.

Connected Coverage

This story is part of our running series on the contest for African resources, Africa: The New Scramble, and sits alongside our wider reporting from Central Africa.

Sources: Council of ministers minutes (via Zoom Eco, 3 August 2026); Congo Budget Ministry.

This article was produced by The Rio Times’ automated newsroom system. How we use AI · Report an error · Editorial responsibility: Matthias Camenzind, Editor-in-Chief

RT
Ask Rio Times
Latin American markets, currencies and companies.
Open the full Ask Rio Times →

Africa Intelligence

One email, every weekday morning. African markets, politics and business — filed from our newsroom in Rio.

Yesterday’s subject line: “Congo's toll tops 5,000 as a US travel rule begins”

Free. We send a confirmation link first — nothing arrives until you click it. Unsubscribe with one click in any edition. If you stop opening us for 30 days we stop sending by ourselves, as we assume the interest is no longer there. See our privacy policy. We never share your email.

Brazil runoff date: Sunday, October 25, poll closing times and when results start · Brazil runoff polls: Flávio 51%, Lula 49% · Kalshi and Polymarket odds

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.