IBOV 167,576.73 ▼ 0.15% IPSA 11,244.13 ▲ 0.02% IPC MEX 64,436.38 ▲ 0.68% MERVAL 2,870,339 ▼ 0.15% COLCAP 2,445.04 ▼ 0.36% BVL PERÚ 58,380.78 ▲ 0.78% USD/BRL5.19▲ 0.31% USD/MXN16.95▲ 0.04% USD/CLP921.20▼ 0.02% USD/COP3,065▼ 1.32% USD/PEN3.35▼ 0.47% USD/ARS1,497▼ 0.02% USD/UYU40.21▲ 0.95% USD/PYG5,992▲ 1.19% USD/BOB11.42▲ 0.14% USD/DOP58.82▲ 1.31% USD/CRC446.30▲ 2.09% USD/GTQ7.62▲ 2.24% USD/HNL26.81▲ 1.60% USD/NIO36.62▲ 0.69% USD/VES775.47▼ 0.13% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD 157.28 — 0.00% USD/TTD6.71▲ 0.93% EUR/BRL6.06▲ 0.51% BRENT 88.88 ▼ 0.03% WTI 83.11 ▼ 0.11% IRON ORE 161.91 — — COPPER 6.61 ▲ 0.03% GOLD 4,461 ▲ 1.78% SILVER 65.59 ▲ 1.26% SOY 1,184 ▲ 3.20% CORN 480.50 ▲ 10.02% WHEAT 655.00 ▲ 3.93% COFFEE 317.25 ▼ 5.51% SUGAR 16.43 ▼ 1.79% ORANGE JUICE 138.55 ▼ 0.47% COTTON 85.03 ▲ 2.33% COCOA 5,719 ▲ 3.18% BEEF 223.60 ▼ 3.93% CATTLE 339.10 ▼ 3.16% LITHIUM 75.20 ▲ 1.47% PETR4 41.64 ▼ 0.05% VALE3 72.97 ▲ 0.83% ITUB4 38.60 ▼ 1.03% BBDC4 16.85 ▲ 0.36% ABEV3 14.89 ▼ 0.80% BBAS3 19.37 ▲ 0.47% B3SA3 14.26 ▼ 0.21% WEGE3 47.59 ▲ 0.49% PRIO3 59.14 ▼ 0.19% SUZB3 41.33 ▲ 2.35% RENT3 34.68 ▼ 0.09% AZZA3 15.89 ▼ 2.63% CSAN3 3.22 ▼ 1.83% RAIZ4 0.25 — 0.00% PCAR3 2.75 ▼ 0.36% GMAT3 3.65 ▼ 1.08% PSSA3 48.13 ▼ 0.54% CVCB3 1.33 ▼ 2.92% POSI3 3.36 ▲ 2.44% SLCE3 13.34 ▲ 0.30% NATU3 8.14 ▼ 0.73% IBOV 167,576.73 ▼ 0.15% IPSA 11,244.13 ▲ 0.02% IPC MEX 64,436.38 ▲ 0.68% MERVAL 2,870,339 ▼ 0.15% COLCAP 2,445.04 ▼ 0.36% BVL PERÚ 58,380.78 ▲ 0.78% USD/BRL 5.16 ▲ 0.01% USD/MXN 17.06 ▼ 0.24% USD/CLP 913.98 ▲ 0.04% USD/COP 3,140 ▲ 0.03% USD/PEN 3.36 ▼ 0.66% USD/ARS 1,493 ▲ 0.10% USD/UYU 40.27 ▲ 1.24% USD/PYG 5,939 ▲ 1.68% USD/BOB 11.64 ▼ 0.76% USD/DOP 58.34 ▲ 1.25% USD/CRC 445.92 ▲ 0.89% USD/GTQ 7.62 ▲ 2.21% USD/HNL 26.79 ▲ 1.57% USD/NIO 36.62 ▲ 0.69% USD/VES 762.44 ▼ 0.13% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.28 — 0.00% USD/TTD 6.70 ▲ 0.61% EUR/BRL 5.95 ▲ 1.01% BRENT 88.88 ▼ 0.03% WTI 83.11 ▼ 0.11% IRON ORE 161.91 — — COPPER 6.61 ▲ 0.03% GOLD 4,461 ▲ 1.78% SILVER 65.59 ▲ 1.26% SOY 1,184 ▲ 3.20% CORN 480.50 ▲ 10.02% WHEAT 655.00 ▲ 3.93% COFFEE 317.25 ▼ 5.51% SUGAR 16.43 ▼ 1.79% ORANGE JUICE 138.55 ▼ 0.47% COTTON 85.03 ▲ 2.33% COCOA 5,719 ▲ 3.18% BEEF 223.60 ▼ 3.93% CATTLE 339.10 ▼ 3.16% LITHIUM 75.20 ▲ 1.47% PETR4 41.64 ▼ 0.05% VALE3 72.97 ▲ 0.83% ITUB4 38.60 ▼ 1.03% BBDC4 16.85 ▲ 0.36% ABEV3 14.89 ▼ 0.80% BBAS3 19.37 ▲ 0.47% B3SA3 14.26 ▼ 0.21% WEGE3 47.59 ▲ 0.49% PRIO3 59.14 ▼ 0.19% SUZB3 41.33 ▲ 2.35% RENT3 34.68 ▼ 0.09% AZZA3 15.89 ▼ 2.63% CSAN3 3.22 ▼ 1.83% RAIZ4 0.25 — 0.00% PCAR3 2.75 ▼ 0.36% GMAT3 3.65 ▼ 1.08% PSSA3 48.13 ▼ 0.54% CVCB3 1.33 ▼ 2.92% POSI3 3.36 ▲ 2.44% SLCE3 13.34 ▲ 0.30% NATU3 8.14 ▼ 0.73%
since 2009
Thursday, August 20, 2026

Mexico Business

Mexico City Is Rebuilding Buenavista for Trains That Do Not Run Yet

By · August 20, 2026 · 6 min read

Daily Brief

The morning intel from across Latin America. Free.

By subscribing you agree to our privacy policy. We never share your email.

Mexico · Infrastructure

Key Facts

  • What Rehabilitated platforms, new rails and ballast, new yards and sheds, and a new platform for the Mexico City–Querétaro train.
  • Where The Buenavista terminal, Mexico City.
  • When it is ready The expansion is projected for June 2027. The Querétaro platform is estimated to be in operation by September 2027.
  • The target More than 180,000 users a day.
  • Who builds the railway The Defence Ministry, through the Felipe Ángeles engineering group, for the Querétaro line.
  • Cost No published figure for the Buenavista works. The Mexico City–Querétaro project as a whole is estimated at around 144 billion pesos.

Platforms, rails, yards and a new bay — for services that begin after the building work ends.

The Buenavista terminal expansion is under way in Mexico City, and the important detail is the tense. Nothing about it is finished. The works are projected for June 2027, and the platform for the Querétaro service is estimated to be operating from September 2027.

Commuters in a Mexico City metro concourse, illustrating the Buenavista terminal expansion
Mexico City. Buenavista already handles metro, Metrobus and suburban rail passengers. (Photo internet reproduction)
One-stop reference
Company Intelligence
Every listed company in Latin America — financials, ownership and structure for 1,450+ companies across 26 exchanges, in one place.
Browse the directory →
RT
Ask Rio Times
Latin American markets, currencies and companies.
Open the full Ask Rio Times →

What the Buenavista terminal expansion involves

Platform rehabilitation, laying rails and ballast on the junction with the line to the Felipe Ángeles airport, construction of new yards and sheds, and a new platform dedicated to the Mexico City–Querétaro train.

The stated objective is to handle more than 180,000 users a day. Buenavista today is the terminus of the Tren Suburbano to Cuautitlán and a metro and Metrobús interchange; the expansion is meant to turn it into the head of a genuine intercity network.

Timing, again: the expansion is projected ready for June 2027, and the Querétaro platform for September 2027. The Mexico City–Querétaro service itself has a start target of 2027.

No investment figure has been published specifically for the Buenavista works. The Querétaro railway project as a whole carries an estimate of around 144 billion pesos, roughly US$7.6 billion at about 18.9 pesos to the dollar.

Why Mexico is building passenger rail again

Because it stopped. Mexico effectively abandoned intercity passenger rail in the late 1990s when the freight network was concessioned, leaving a country of Mexico’s size and density almost entirely dependent on buses and aviation between cities.

The current programme reverses that, and it is being executed by the armed forces rather than by a civil transport agency — the Querétaro line is the responsibility of the Defence Ministry through its Felipe Ángeles engineering group, which also built and operates the airport of the same name.

Whatever one makes of that institutional choice, it explains the delivery model: military engineering units, fixed timetables announced well in advance, and comparatively little published procurement detail.

What it means for getting around, eventually

Mexico City to Querétaro is roughly 220 kilometres and currently a three-hour drive that can become far worse. A rail service on that corridor would be the single most consequential change to intercity travel in central Mexico in a generation.

The Pachuca service covers a shorter but heavily commuted corridor into Hidalgo. Together they would make Buenavista a genuine hub rather than a suburban terminus with a metro connection.

For anyone planning travel now, though, the practical answer is unchanged: buses and driving. Nothing described here is available to a passenger before 2027, and infrastructure timetables of this kind are routinely optimistic.

What Buenavista is today

It sits just north of the historic centre, on the site of the old Buenavista railway station, and it is already one of the busiest interchanges in the city — the terminus of the Tren Suburbano to Cuautitlán, a Metro Line B stop, a Metrobús node and a shopping centre.

That existing load is why the works are complicated. The expansion is being carried out around a functioning terminal rather than on a clear site, which is the usual reason urban rail projects slip.

The junction with the line to the Felipe Ángeles airport is a separate strand of the same programme, connecting the terminal north to the airport built on the former Santa Lucía air base.

For a traveller today, none of this changes anything. The Suburbano runs as it always has, and Querétaro and Pachuca remain bus journeys.

Why this matters if you watch Latin American infrastructure

Rebuilding intercity passenger rail from a standing start is something almost no country in the region has attempted at this scale. Argentina has been restoring long-distance services incrementally; Brazil has been tendering and re-tendering a São Paulo–Rio line for years without turning earth.

Mexico is the test case for whether it can be done quickly, and Buenavista is where the answer will be visible — because a terminal is the part of a railway that a passenger actually experiences.

The number to watch is not the 144 billion pesos. It is whether June 2027 holds.

Frequently Asked Questions

When will the Buenavista expansion be finished?

The expansion works are projected for June 2027, with the platform for the Mexico City–Querétaro train estimated to be in operation by September 2027. Nothing described in the project is available to passengers before then.

What is being built?

Rehabilitated platforms, new rails and ballast on the junction with the line to the Felipe Ángeles airport, new yards and sheds, and a new platform for the Querétaro service. The stated capacity target is more than 180,000 users a day.

How much does it cost, and who is building it?

No figure has been published for the Buenavista works specifically. The Mexico City–Querétaro railway project as a whole is estimated at around 144 billion pesos, roughly US$7.6 billion, and is the responsibility of the Defence Ministry through its Felipe Ángeles engineering group.

Sources: Carta de México — Buenavista terminal expanded in CDMX for trains to Querétaro and Hidalgo

This article was produced by The Rio Times’ automated newsroom system. How we use AI · Report an error

Read More from The Rio Times

The Rio Times · Power Map
See who really holds power in Latin America
Click to open the Power Map

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.