IBOV 185,147.15 ▼ 0.02% IPSA 11,315.26 ▼ 1.14% IPC MEX 64,727.54 ▼ 0.21% MERVAL 3,034,599 ▲ 1.11% COLCAP 2,565.50 ▲ 0.82% BVL PERÚ 59,789.81 — — USD/BRL5.13▲ 0.05% USD/MXN16.95▲ 0.25% USD/CLP928.88▼ 0.60% USD/COP3,131▲ 0.09% USD/PEN3.35▼ 0.17% USD/ARS1,511▲ 0.15% USD/UYU40.24— 0.00% USD/PYG5,947— 0.00% USD/BOB12.40— 0.00% USD/DOP58.99▲ 0.83% USD/CRC448.67— 0.00% USD/GTQ7.63— 0.00% USD/HNL26.84— 0.00% USD/NIO36.62▲ 0.69% USD/VES812.65▲ 0.78% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD 157.28 — 0.00% USD/TTD6.71— 0.00% EUR/BRL5.96▲ 0.17% BRENT 88.88 ▼ 0.03% WTI 83.11 ▼ 0.11% IRON ORE 161.91 — — COPPER 6.61 ▲ 0.03% GOLD 4,461 ▲ 1.78% SILVER 65.59 ▲ 1.26% SOY 1,184 ▲ 3.20% CORN 480.50 ▲ 10.02% WHEAT 655.00 ▲ 3.93% COFFEE 317.25 ▼ 5.51% SUGAR 16.43 ▼ 1.79% ORANGE JUICE 138.55 ▼ 0.47% COTTON 85.03 ▲ 2.33% COCOA 5,719 ▲ 3.18% BEEF 223.60 ▼ 3.93% CATTLE 339.10 ▼ 3.16% LITHIUM 75.20 ▲ 1.47% PETR4 41.64 ▼ 0.05% VALE3 72.97 ▲ 0.83% ITUB4 38.60 ▼ 1.03% BBDC4 16.85 ▲ 0.36% ABEV3 14.89 ▼ 0.80% BBAS3 19.37 ▲ 0.47% B3SA3 14.26 ▼ 0.21% WEGE3 47.59 ▲ 0.49% PRIO3 59.14 ▼ 0.19% SUZB3 41.33 ▲ 2.35% RENT3 34.68 ▼ 0.09% AZZA3 15.89 ▼ 2.63% CSAN3 3.22 ▼ 1.83% RAIZ4 0.25 — 0.00% PCAR3 2.75 ▼ 0.36% GMAT3 3.65 ▼ 1.08% PSSA3 48.13 ▼ 0.54% CVCB3 1.33 ▼ 2.92% POSI3 3.36 ▲ 2.44% SLCE3 13.34 ▲ 0.30% NATU3 8.14 ▼ 0.73% IBOV 185,147.15 ▼ 0.02% IPSA 11,315.26 ▼ 1.14% IPC MEX 64,727.54 ▼ 0.21% MERVAL 3,034,599 ▲ 1.11% COLCAP 2,565.50 ▲ 0.82% BVL PERÚ 59,789.81 — — USD/BRL 5.16 ▲ 0.01% USD/MXN 17.06 ▼ 0.24% USD/CLP 913.98 ▲ 0.04% USD/COP 3,140 ▲ 0.03% USD/PEN 3.36 ▼ 0.66% USD/ARS 1,493 ▲ 0.10% USD/UYU 40.27 ▲ 1.24% USD/PYG 5,939 ▲ 1.68% USD/BOB 11.64 ▼ 0.76% USD/DOP 58.34 ▲ 1.25% USD/CRC 445.92 ▲ 0.89% USD/GTQ 7.62 ▲ 2.21% USD/HNL 26.79 ▲ 1.57% USD/NIO 36.62 ▲ 0.69% USD/VES 762.44 ▼ 0.13% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.28 — 0.00% USD/TTD 6.70 ▲ 0.61% EUR/BRL 5.95 ▲ 1.01% BRENT 88.88 ▼ 0.03% WTI 83.11 ▼ 0.11% IRON ORE 161.91 — — COPPER 6.61 ▲ 0.03% GOLD 4,461 ▲ 1.78% SILVER 65.59 ▲ 1.26% SOY 1,184 ▲ 3.20% CORN 480.50 ▲ 10.02% WHEAT 655.00 ▲ 3.93% COFFEE 317.25 ▼ 5.51% SUGAR 16.43 ▼ 1.79% ORANGE JUICE 138.55 ▼ 0.47% COTTON 85.03 ▲ 2.33% COCOA 5,719 ▲ 3.18% BEEF 223.60 ▼ 3.93% CATTLE 339.10 ▼ 3.16% LITHIUM 75.20 ▲ 1.47% PETR4 41.64 ▼ 0.05% VALE3 72.97 ▲ 0.83% ITUB4 38.60 ▼ 1.03% BBDC4 16.85 ▲ 0.36% ABEV3 14.89 ▼ 0.80% BBAS3 19.37 ▲ 0.47% B3SA3 14.26 ▼ 0.21% WEGE3 47.59 ▲ 0.49% PRIO3 59.14 ▼ 0.19% SUZB3 41.33 ▲ 2.35% RENT3 34.68 ▼ 0.09% AZZA3 15.89 ▼ 2.63% CSAN3 3.22 ▼ 1.83% RAIZ4 0.25 — 0.00% PCAR3 2.75 ▼ 0.36% GMAT3 3.65 ▼ 1.08% PSSA3 48.13 ▼ 0.54% CVCB3 1.33 ▼ 2.92% POSI3 3.36 ▲ 2.44% SLCE3 13.34 ▲ 0.30% NATU3 8.14 ▼ 0.73%
since 2009
Tuesday, September 8, 2026

Latin America Mexico

Telxius Opens Cancún Gateway Ahead of Its Unfinished Cable

By · September 8, 2026 · 5 min read

Daily Brief

The morning intel from across Latin America. Free.

By subscribing you agree to our privacy policy. We never share your email.

MEXICO · INFRASTRUCTURE

Key Facts

  • What’s finished: Telxius’s new Cancún Landing Gateway and Edge Data Center is complete and ready for customers.
  • What’s not: The Tikal submarine cable it was built to serve is not due until the first half of 2027.
  • The route: Tikal will run from Puerto Barrios, Guatemala, via Cancún, to Boca Raton, Florida, in the United States.
  • The builders: Telxius built the Cancún branch alone; the wider Tikal trunk is a joint project with América Móvil.
  • The capacity: Telxius puts the main trunk’s initial capacity at about 380 Tbps.
  • The bigger picture: Telefónica and Pontegadea, Telxius’s owners, are seeking buyers for its whole submarine cable business.

Telxius has finished a new cable landing station and data centre in Cancún, Mexico. The submarine cable it was built to serve is not due until 2027.

Computer rendering of Telxius's Landing Gateway and Edge Data Center building in Cancun, Mexico
Company rendering of the Cancún Landing Gateway & Edge Data Center. The building is finished; the undersea cable it was built to serve is not. (Image: Telxius)
One-stop reference
Company Intelligence
Every listed company in Latin America — financials, ownership and structure for 1,450+ companies across 26 exchanges, in one place.
Browse the directory →
RT
Ask Rio Times
17 years of Latin America reporting, on demand.
Open the full Ask Rio Times →

Cancún’s new facility is complete. Telxius calls it a Landing Gateway and Edge Data Center, and says it is ready to take on customers now.

The cable it was built for is a different story. Tikal, the submarine system due to land there, is not expected until the first half of 2027.

Boca Raton sits on Florida’s coast, making it a US landing point for the new cable. The Caribbean has relatively few redundant cable routes, so extra ones give operators more options if one is damaged.

That gap says something about how this kind of infrastructure gets built. The landing house goes up first, well before the ship that will use it arrives.

What a Landing Gateway Does

A submarine cable comes ashore at a landing station, where it is spliced into terrestrial networks. Cancún’s version adds something newer: computing capacity built into the same site.

That is the edge data centre part. Processing can happen close to where the cable lands, rather than being sent further inland first.

Telxius describes the facility as carrier-neutral, meaning it belongs to no single network operator. Any carrier can interconnect there on equal terms.

It also cites Tier III standards with N+1/2N redundancy for power and cooling. In practice, that means maintenance and repairs can happen without shutting the site down.

Telxius calls the whole facility AI-ready, a marketing phrase with no fixed technical meaning. Tier III and N+1/2N, by contrast, are defined engineering standards.

Tikal, the Cable It Was Built For

Tikal will run from Puerto Barrios, Guatemala, with a landing at Cancún, to Boca Raton, Florida. It is due for service in the first half of 2027.

That date has already slipped. When the Cancún extension was first announced in October 2023, Telxius targeted mid-2026.

Telxius puts the main trunk’s initial capacity at about 380 Tbps, up from an initial 190 Tbps estimate. For comparison, ARCOS-1, the older cable that already serves Puerto Barrios, was designed for about 8.4 Tbps.

CELIA, another Caribbean cable Telxius is building toward Boca Raton, is rated above 170 Tbps. ARCOS-1’s US landing is North Miami Beach, not Boca Raton, so it does not share Tikal’s exact route.

Telxius’s release calls Tikal the highest-capacity cable on that specific route, which no other cable appears to share. That comparison could not be independently confirmed either way, so this piece states only the capacity Telxius has published.

The wider Tikal system began in January 2023 as a joint project between Telxius and América Móvil. Telxius later took on the Cancún branch alone — a partnership this particular release never mentions.

The cable itself is being supplied by Alcatel Submarine Networks, which has also built CELIA and several of Telxius’s other recent systems.

Workers stand beside a submarine cable being laid in a trench on a beach
A submarine cable is laid ashore at a separate site. Tikal, the cable Cancún’s new facility awaits, is not due until 2027.

Why Route Diversity Matters

Submarine cables carry more than 99% of international data, including the traffic behind everyday streaming and cloud services. Globally there are around 500 of them, and the industry logs more than 200 cable faults a year.

The Caribbean is more exposed than most regions. Hurricanes, seismic activity and heavy shipping traffic all threaten the same narrow corridors that cables must pass through.

An international submarine-cable resilience summit in Porto, Portugal, in February 2026 was organised by Portugal’s regulator with the ITU and ICPC. The Caribbean Telecommunications Union, reacting afterwards, called geographic redundancy “foundational to economic continuity, digital public services and national security” for Caribbean states.

Guatemala’s Caribbean coast is not new to this. ARCOS-1, a cable in service since 2001, already links Puerto Barrios to the US and more than a dozen other countries.

That is a reminder of how few, and how old, some of the region’s existing routes still are.

Where It Fits in Telxius’s Network

Cancún does not stand alone. Telxius already runs SAm-1, connecting the US with Central and South America, and PCCS, its Pacific Caribbean route.

It also operates a landing gateway in Punta Cana, Dominican Republic, and recently expanded its network in Santo Domingo. CELIA, a separate cable also due in 2027, will add landing points in Puerto Rico, Aruba, Antigua and Martinique.

From Cancún, Telxius also offers an alternative terrestrial route to Santiago de Querétaro, in central Mexico. That gives customers a second path inland if the coastal route is disrupted.

Who Owns Telxius

Telxius is majority-owned by Telefónica, the Spanish telecoms group, which holds 70%. The remaining 30% belongs to Pontegadea, the investment vehicle of Zara founder Amancio Ortega.

The two bought out a 40% stake previously held by KKR in 2022. Telxius describes its network as spanning more than 100,000 kilometres (62,000 miles) of subsea and terrestrial fibre.

In July 2026, Telefónica and Pontegadea said they were seeking buyers for the whole of that submarine cable business. Market estimates put its value at around €1.2 billion, with financial advisers already contacting potential buyers.

It is not clear whether Cancún and Tikal would be included if a sale goes ahead. A new owner is, in principle, a live possibility for the network this facility joins.

What the Announcement Leaves Out

Telxius’s announcement leaves several ordinary questions unanswered. It gives no investment figure, no floor space or power rating for the data centre, and no staffing numbers.

Nor does it name an opening date for the facility beyond the date of the release itself. Those gaps are not filled in here with estimates.

Sources: Telxius press release, 3 September 2026; Telxius project pages for Tikal and CELIA; Submarine Networks; Data Center Dynamics; Converge Digest; Caribbean Telecommunications Union; Wikipedia (ARCOS-1, Telxius).

This article was produced by The Rio Times’ automated newsroom system. How we use AI · Report an error

Read More from The Rio Times

The Rio Times · Power Map
See who really holds power in Latin America
Click to open the Power Map

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.