IBOV 185,229.17 ▼ 0.41% IPSA 11,381.18 ▲ 1.30% IPC MEX 63,375.93 ▼ 0.78% MERVAL 3,021,926 ▼ 1.29% COLCAP 2,548.22 ▲ 1.05% BVL PERÚ 60,023.65 ▼ 1.13% USD/BRL5.14▲ 0.26% USD/MXN17.22▼ 0.01% USD/CLP959.00▼ 0.31% USD/COP3,175▲ 1.37% USD/PEN3.37▼ 0.10% USD/ARS1,514▲ 0.26% USD/UYU40.16▲ 2.90% USD/PYG5,906▲ 2.95% USD/BOB9.95▼ 6.56% USD/DOP58.83▲ 0.22% USD/CRC444.45▲ 2.49% USD/GTQ7.63▲ 3.03% USD/HNL26.85▲ 0.38% USD/NIO36.62— 0.00% USD/VES846.42▼ 0.13% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD 157.28 — 0.00% USD/TTD6.75▲ 2.57% EUR/BRL5.91▲ 0.04% BRENT 88.88 ▼ 0.03% WTI 83.11 ▼ 0.11% IRON ORE 161.91 — — COPPER 6.61 ▲ 0.03% GOLD 4,461 ▲ 1.78% SILVER 65.59 ▲ 1.26% SOY 1,184 ▲ 3.20% CORN 480.50 ▲ 10.02% WHEAT 655.00 ▲ 3.93% COFFEE 317.25 ▼ 5.51% SUGAR 16.43 ▼ 1.79% ORANGE JUICE 138.55 ▼ 0.47% COTTON 85.03 ▲ 2.33% COCOA 5,719 ▲ 3.18% BEEF 223.60 ▼ 3.93% CATTLE 339.10 ▼ 3.16% LITHIUM 75.20 ▲ 1.47% PETR4 41.64 ▼ 0.05% VALE3 72.97 ▲ 0.83% ITUB4 38.60 ▼ 1.03% BBDC4 16.85 ▲ 0.36% ABEV3 14.89 ▼ 0.80% BBAS3 19.37 ▲ 0.47% B3SA3 14.26 ▼ 0.21% WEGE3 47.59 ▲ 0.49% PRIO3 59.14 ▼ 0.19% SUZB3 41.33 ▲ 2.35% RENT3 34.68 ▼ 0.09% AZZA3 15.89 ▼ 2.63% CSAN3 3.22 ▼ 1.83% RAIZ4 0.25 — 0.00% PCAR3 2.75 ▼ 0.36% GMAT3 3.65 ▼ 1.08% PSSA3 48.13 ▼ 0.54% CVCB3 1.33 ▼ 2.92% POSI3 3.36 ▲ 2.44% SLCE3 13.34 ▲ 0.30% NATU3 8.14 ▼ 0.73% IBOV 185,229.17 ▼ 0.41% IPSA 11,381.18 ▲ 1.30% IPC MEX 63,375.93 ▼ 0.78% MERVAL 3,021,926 ▼ 1.29% COLCAP 2,548.22 ▲ 1.05% BVL PERÚ 60,023.65 ▼ 1.13% USD/BRL 5.16 ▲ 0.01% USD/MXN 17.06 ▼ 0.24% USD/CLP 913.98 ▲ 0.04% USD/COP 3,140 ▲ 0.03% USD/PEN 3.36 ▼ 0.66% USD/ARS 1,493 ▲ 0.10% USD/UYU 40.27 ▲ 1.24% USD/PYG 5,939 ▲ 1.68% USD/BOB 11.64 ▼ 0.76% USD/DOP 58.34 ▲ 1.25% USD/CRC 445.92 ▲ 0.89% USD/GTQ 7.62 ▲ 2.21% USD/HNL 26.79 ▲ 1.57% USD/NIO 36.62 ▲ 0.69% USD/VES 762.44 ▼ 0.13% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.28 — 0.00% USD/TTD 6.70 ▲ 0.61% EUR/BRL 5.95 ▲ 1.01% BRENT 88.88 ▼ 0.03% WTI 83.11 ▼ 0.11% IRON ORE 161.91 — — COPPER 6.61 ▲ 0.03% GOLD 4,461 ▲ 1.78% SILVER 65.59 ▲ 1.26% SOY 1,184 ▲ 3.20% CORN 480.50 ▲ 10.02% WHEAT 655.00 ▲ 3.93% COFFEE 317.25 ▼ 5.51% SUGAR 16.43 ▼ 1.79% ORANGE JUICE 138.55 ▼ 0.47% COTTON 85.03 ▲ 2.33% COCOA 5,719 ▲ 3.18% BEEF 223.60 ▼ 3.93% CATTLE 339.10 ▼ 3.16% LITHIUM 75.20 ▲ 1.47% PETR4 41.64 ▼ 0.05% VALE3 72.97 ▲ 0.83% ITUB4 38.60 ▼ 1.03% BBDC4 16.85 ▲ 0.36% ABEV3 14.89 ▼ 0.80% BBAS3 19.37 ▲ 0.47% B3SA3 14.26 ▼ 0.21% WEGE3 47.59 ▲ 0.49% PRIO3 59.14 ▼ 0.19% SUZB3 41.33 ▲ 2.35% RENT3 34.68 ▼ 0.09% AZZA3 15.89 ▼ 2.63% CSAN3 3.22 ▼ 1.83% RAIZ4 0.25 — 0.00% PCAR3 2.75 ▼ 0.36% GMAT3 3.65 ▼ 1.08% PSSA3 48.13 ▼ 0.54% CVCB3 1.33 ▼ 2.92% POSI3 3.36 ▲ 2.44% SLCE3 13.34 ▲ 0.30% NATU3 8.14 ▼ 0.73%
since 2009
Sunday, September 20, 2026

Africa Africa Energy

Lesotho’s Polihali Dam Reaches 56.7% as Claimants Lose Court Round

By · September 20, 2026 · 5 min read

Africa Intelligence

One email, every weekday morning. African markets, politics and business — filed from our newsroom in Rio.

Yesterday’s subject line: “Nigeria just won a US$3.4 billion arbitration in Paris”

Free. We send a confirmation link first — nothing arrives until you click it. Unsubscribe with one click in any edition. If you stop opening us for 30 days we stop sending by ourselves, as we assume the interest is no longer there. See our privacy policy. We never share your email.

LESOTHO · INFRASTRUCTURE

Key Facts

  • What happened. Lesotho Highlands Water Project Phase 2 reached 56.7% completion, with Polihali Dam at 53% and the 38 km transfer tunnel at 58%. South Africa’s water minister Pemmy Majodina declared herself satisfied with progress after a September visit.
  • How big. Phase 2 is expected to create around 6,000 jobs over five years and will increase the water Lesotho exports to South Africa’s Gauteng region, the economic heart of the neighbour that surrounds it.
  • The catch. More than 3,000 individuals and 889 businesses demanding compensation for lost land and livelihoods failed before Lesotho’s Constitutional Court. The court declined to hear their case and sent them back to the ordinary High Court track.
  • Who it hits. Highland communities around the dam sites in Mokhotlong district, construction workers, and every South African household downstream that will drink Lesotho’s water.
  • What comes next. The claimants can pursue compensation through the High Court under existing legislation. Construction continues toward completion, and communities are pressing for a larger share of the project’s benefits.
Maseru and the Lesotho highlands
Lesotho. Phase two of the highlands water project passed 56.7% completion.
One-stop reference
Company Intelligence
Every listed company in Latin America — financials, ownership and structure for 1,450+ companies across 26 exchanges, in one place.
Browse the directory →
RT
Ask Rio Times
17 years of Latin America reporting, on demand.
Open the full Ask Rio Times →

The Lesotho Highlands Water Project is more than half built and will send water and jobs downhill for decades. The people who lived where the water will be are still fighting for compensation.

The second phase of the Lesotho Highlands Water Project, one of Africa’s largest infrastructure schemes, has passed the halfway mark. The project reports 56.7% completion, with the Polihali Dam at 53% and the 38-kilometre transfer tunnel at 58%. In the same month, thousands of people displaced by the project lost a round in court.

A dam that is also a national economy

The Lesotho Highlands Water Project is the country’s single biggest asset. It moves water from the Maluti mountains through dams and tunnels into South Africa’s Gauteng province, and Lesotho earns royalties from every cubic metre. Phase 1 built the Katse and Mohale dams in the 1990s and 2000s. Phase 2 adds the Polihali Dam and a 38-kilometre transfer tunnel, with a hydropower component that will also supply Lesotho’s own grid.

Progress has been steady. The Polihali dam wall was about 50% complete by early July, with the rockfill and the upstream concrete curb rising past 2,020 metres above sea level, according to Engineering News. South Africa’s water and sanitation minister, Pemmy Majodina, visited in September and said she was satisfied with the construction pace and with the resettlement programme for affected communities. The project is expected to sustain around 6,000 jobs over five years — significant employment in a small mountain economy.

The other side of the ledger

The water that flows south leaves flooded valleys behind. More than 3,000 individuals and 889 businesses have been seeking fuller compensation for land and livelihoods lost to the Katse, Mohale and Polihali dams. They are organised in the Mokhotlong Business Forum Development Trust, the Community Resources Development Trust and a group of community members. They asked Lesotho’s High Court, sitting as the Constitutional Court, to take their case directly.

In a judgment delivered in May and released in writing this month, the full Bench declined. The court held that the claimants have adequate remedies under existing legislation and must pursue them through the ordinary High Court route. It is a procedural defeat, not a final one — but it means years of additional litigation for communities that have already waited decades, as Moneyweb reports. Local media in Lesotho report growing pressure from highland communities for a greater share of the project’s benefits.

What this means for expats and investors

For engineers, contractors and development professionals, Phase 2 remains one of the few megaprojects in the region that is genuinely on schedule, and its procurement and employment will run for years. For anyone assessing Lesotho’s stability, the compensation dispute is the variable to watch: the project is the country’s fiscal backbone, and the communities hosting it are its most organised critics.

What Is Not Known

The final cost and completion date of Phase 2 have slipped before and are not firmly public. The eventual compensation package for displaced communities is unresolved. The timeline for the hydropower component, and how much of the project’s revenue will reach the highland districts beyond wages, are likewise open questions.

Frequently Asked Questions

What is the Lesotho Highlands Water Project?

A binational scheme that dams and tunnels water from Lesotho’s mountains to South Africa’s Gauteng region in exchange for royalties. Phase 2 adds the Polihali Dam and a 38-kilometre transfer tunnel, plus hydropower for Lesotho.

How far along is the Polihali Dam?

The project reports Phase 2 at 56.7% completion, with the Polihali Dam at 53% and the transfer tunnel at 58%. The dam wall passed the halfway mark in mid-2026.

What did the court decide about compensation?

Lesotho’s Constitutional Court declined to hear the case of more than 3,000 individuals and 889 businesses directly, ruling they must pursue compensation through the ordinary High Court under existing laws. The claims themselves remain open.

The Big Picture

Africa: The New Scramble — why the world’s powers are competing for the continent

This article was produced by The Rio Times’ automated newsroom system. How we use AI · Report an error

Read More from The Rio Times

The Rio Times · Power Map
See who really holds power in Latin America
Click to open the Power Map

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.