MALAWI · INFRASTRUCTURE
Key Facts
- The country Malawi is a landlocked African country that relies on public money and donors to build roads.
- Why it matters A US$350 million US road grant ended in 2025; road awards worth US$480 million are now planned.
- What happened In January 2026 Malawi’s graft watchdog arrested irrigation officials and contractors over alleged US$21 million in improper payments.
- What it means for you Road deals now carry formal complaint windows; investors should watch audits, court cases and who leads the watchdog.
- Still open Who will lead the watchdog, whether the irrigation suspects go to trial, and whether road awards face challenges.
In Plain English
The Anti-Corruption Bureau (ACB) is Malawi’s state watchdog that investigates graft and arrests suspects. The Roads Authority buys and manages the national road network, and the National Audit Office is the state auditor of public money.
The Greenbelt Authority is a state agency, set up by law in 2017, that promotes large-scale irrigation farming. The Millennium Challenge Corporation (MCC) is a US government aid agency, and the kwacha (K) is Malawi’s currency.
Malawi’s Anti-Corruption Bureau (ACB), the state watchdog that investigates graft and arrests suspects, is chasing alleged theft from public works while an acting chief runs it. One 2026 case involves K36.78 billion (US$21 million) of alleged improper payments at the state irrigation agency.
For US readers the stakes are practical: a US aid agency ended a US$350 million Malawi road and land grant in December 2025. Malawi’s Roads Authority has since announced plans to award road contracts worth K832.9 billion (US$480 million at the Reserve Bank of Malawi’s middle rate of K1,734 per US$ on 30 October 2026).
An earlier report on the Chiweta-Karonga road awards covered one contract, and Malawi explained covers the wider economy. New here are the irrigation case, the audit-office hiring case and the end of the US grant.
What Happened
On 8 October 2026 the Roads Authority said it intends to award K587.12 billion (US$339 million) for the 105 km Chiweta-Karonga road, split between the builders Unik Construction Engineering Ltd and China Civil Engineering Construction Corporation. Losing bidders had until Thursday 22 October to complain under the Public Procurement and Disposal of Public Assets Act of 2025.
In May the agency announced intended awards of K245.78 billion (US$142 million) on the M10 and M1 roads. On 22 October it invited consultants to bid for Chiweta-Karonga design and supervision, with the cost to come from public funds.
The Watchdog at Work
On 9 October 2026 the ACB ordered Admarc, the state agricultural marketing corporation, to stop awarding a K2.97 billion (US$1.7 million) tarpaulin contract while the bureau looks into the deal. On 21 October it ordered the National Audit Office to cancel a hiring round for two audit posts.
The bureau cited exam papers shared in advance and a senior audit official suspected of taking a bribe. Gabriel Chembezi, its acting director general, issued the statement.
The Irrigation Case
The ACB says it began with a complaint on 10 November 2025 about advance payments to contractors at the Greenbelt Authority, the state irrigation agency. It puts the payments for four irrigation schemes at K36.78 billion (US$21 million).
The bureau alleges that the money went out without performance bonds and against fake work certificates, and that some funded political campaigns. It began arresting agency officials and private contractors in January 2026.
By 23 January the ACB said all 11 suspects had been formally charged and granted bail. Every claim here is an allegation, and the suspects are presumed innocent.

Why It Matters
Transparency International, the anti-corruption group, scored Malawi 34 out of 100 in its 2025 Corruption Perceptions Index, released on 10 February 2026, and ranked it 109th of 182 countries. The score matches 2024, and sits above the 32 average for sub-Saharan Africa but below the global average of 42.
The index measures perceived corruption among officials and does not prove that any single contract was tainted. It is the backdrop for every new road contract.
The Millennium Challenge Corporation’s board voted in August 2025 to terminate the US$350 million Malawi Transport and Land Compact, meant to upgrade more than 300 km of roads. Its program page gives no reason and shows only US$1.85 million spent of the US$244.95 million road project by 30 June 2025.
The World Bank approved a US$65 million credit on 4 September 2025 to rebuild about 90 km of the M1 in the Lower Shire valley, with the Roads Authority as an implementing agency. The credit runs to the end of 2030.
What It Means for You
US investors, lenders and contractors should know that large road contracts now pass a standstill period in which losing bidders may complain. The Admarc halt shows that the ACB can stop a purchase before the contract is signed.
Travelers to the far north should not expect a rebuilt Chiweta-Karonga road soon, as the project is still at the contract-notice stage. The State Department’s Malawi advisory page shows Level 2, exercise increased caution, citing crime and civil unrest.
What Is Not Known
It is not known whether any bidder challenged the 8 October road awards before the 22 October deadline, or whether the contracts have been signed. The notices give no start date and no source for the K587.12 billion.
It is not known when the ACB will get a permanent head. It is also unclear how many of the 11 irrigation suspects will stand trial, or whether a court will accept the K36.78 billion figure.
Frequently Asked Questions
What is Malawi’s Anti-Corruption Bureau?
It is the state watchdog that investigates corruption and arrests suspects. As of 21 October 2026 it was led by an acting director general, Gabriel Chembezi.
How corrupt is Malawi in the latest global index?
Transparency International scored Malawi 34 out of 100 in its 2025 index and ranked it 109th of 182 countries. Zero means highly corrupt and 100 means very clean.
Did the United States end its road grant to Malawi?
Yes. The Millennium Challenge Corporation’s board voted in August 2025 to end its US$350 million Malawi Transport and Land Compact, and the program is listed as terminated on 19 December 2025.
How much will Malawi spend on new roads?
The Roads Authority announced intended awards of K832.9 billion (US$480 million) in May and October 2026. These are intended awards, and the notices do not say where the money comes from.
Sources: Roads Authority, notification of intention to award, Chiweta-Karonga, 8 October 2026; Roads Authority, notification of intention to award, M10 and M1, 27 May 2026; Roads Authority, request for proposals for Chiweta-Karonga design and supervision, 22 October 2026; Transparency International, Malawi, Corruption Perceptions Index 2025 and CPI 2025 results workbook; Millennium Challenge Corporation, Malawi Transport and Land Compact and signing release, 28 September 2022; World Bank, project P500625; Reserve Bank of Malawi, exchange rates, 30 October 2026; Public Procurement and Disposal of Assets Authority; US Department of State, Malawi travel advisory.