IBOV 183,965.91 ▼ 0.99% IPSA 11,300.53 ▼ 1.30% IPC MEX 64,000.41 ▼ 0.43% MERVAL 2,939,964 ▼ 1.00% COLCAP 2,609.40 ▼ 0.12% BVL PERÚ 59,677.00 ▲ 0.43% USD/BRL5.19▲ 0.41% USD/MXN17.74▲ 0.07% USD/CLP961.42▼ 0.10% USD/COP3,351▲ 4.44% USD/PEN3.39▲ 0.50% USD/ARS1,520▲ 0.23% USD/UYU40.05▲ 2.84% USD/PYG5,894▲ 2.17% USD/BOB12.18▲ 14.34% USD/DOP59.35▲ 0.59% USD/CRC450.75▲ 4.23% USD/GTQ7.64▲ 3.19% USD/HNL26.85▲ 3.15% USD/NIO36.62▲ 0.31% USD/VES853.52▲ 0.02% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD 157.28 — 0.00% USD/TTD6.77▲ 2.69% EUR/BRL5.90▲ 1.15% BRENT 88.88 ▼ 0.03% WTI 83.11 ▼ 0.11% IRON ORE 161.91 — — COPPER 6.61 ▲ 0.03% GOLD 4,461 ▲ 1.78% SILVER 65.59 ▲ 1.26% SOY 1,184 ▲ 3.20% CORN 480.50 ▲ 10.02% WHEAT 655.00 ▲ 3.93% COFFEE 317.25 ▼ 5.51% SUGAR 16.43 ▼ 1.79% ORANGE JUICE 138.55 ▼ 0.47% COTTON 85.03 ▲ 2.33% COCOA 5,719 ▲ 3.18% BEEF 223.60 ▼ 3.93% CATTLE 339.10 ▼ 3.16% LITHIUM 75.20 ▲ 1.47% PETR4 41.64 ▼ 0.05% VALE3 72.97 ▲ 0.83% ITUB4 38.60 ▼ 1.03% BBDC4 16.85 ▲ 0.36% ABEV3 14.89 ▼ 0.80% BBAS3 19.37 ▲ 0.47% B3SA3 14.26 ▼ 0.21% WEGE3 47.59 ▲ 0.49% PRIO3 59.14 ▼ 0.19% SUZB3 41.33 ▲ 2.35% RENT3 34.68 ▼ 0.09% AZZA3 15.89 ▼ 2.63% CSAN3 3.22 ▼ 1.83% RAIZ4 0.25 — 0.00% PCAR3 2.75 ▼ 0.36% GMAT3 3.65 ▼ 1.08% PSSA3 48.13 ▼ 0.54% CVCB3 1.33 ▼ 2.92% POSI3 3.36 ▲ 2.44% SLCE3 13.34 ▲ 0.30% NATU3 8.14 ▼ 0.73% IBOV 183,965.91 ▼ 0.99% IPSA 11,300.53 ▼ 1.30% IPC MEX 64,000.41 ▼ 0.43% MERVAL 2,939,964 ▼ 1.00% COLCAP 2,609.40 ▼ 0.12% BVL PERÚ 59,677.00 ▲ 0.43% USD/BRL 5.16 ▲ 0.01% USD/MXN 17.06 ▼ 0.24% USD/CLP 913.98 ▲ 0.04% USD/COP 3,140 ▲ 0.03% USD/PEN 3.36 ▼ 0.66% USD/ARS 1,493 ▲ 0.10% USD/UYU 40.27 ▲ 1.24% USD/PYG 5,939 ▲ 1.68% USD/BOB 11.64 ▼ 0.76% USD/DOP 58.34 ▲ 1.25% USD/CRC 445.92 ▲ 0.89% USD/GTQ 7.62 ▲ 2.21% USD/HNL 26.79 ▲ 1.57% USD/NIO 36.62 ▲ 0.69% USD/VES 762.44 ▼ 0.13% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.28 — 0.00% USD/TTD 6.70 ▲ 0.61% EUR/BRL 5.95 ▲ 1.01% BRENT 88.88 ▼ 0.03% WTI 83.11 ▼ 0.11% IRON ORE 161.91 — — COPPER 6.61 ▲ 0.03% GOLD 4,461 ▲ 1.78% SILVER 65.59 ▲ 1.26% SOY 1,184 ▲ 3.20% CORN 480.50 ▲ 10.02% WHEAT 655.00 ▲ 3.93% COFFEE 317.25 ▼ 5.51% SUGAR 16.43 ▼ 1.79% ORANGE JUICE 138.55 ▼ 0.47% COTTON 85.03 ▲ 2.33% COCOA 5,719 ▲ 3.18% BEEF 223.60 ▼ 3.93% CATTLE 339.10 ▼ 3.16% LITHIUM 75.20 ▲ 1.47% PETR4 41.64 ▼ 0.05% VALE3 72.97 ▲ 0.83% ITUB4 38.60 ▼ 1.03% BBDC4 16.85 ▲ 0.36% ABEV3 14.89 ▼ 0.80% BBAS3 19.37 ▲ 0.47% B3SA3 14.26 ▼ 0.21% WEGE3 47.59 ▲ 0.49% PRIO3 59.14 ▼ 0.19% SUZB3 41.33 ▲ 2.35% RENT3 34.68 ▼ 0.09% AZZA3 15.89 ▼ 2.63% CSAN3 3.22 ▼ 1.83% RAIZ4 0.25 — 0.00% PCAR3 2.75 ▼ 0.36% GMAT3 3.65 ▼ 1.08% PSSA3 48.13 ▼ 0.54% CVCB3 1.33 ▼ 2.92% POSI3 3.36 ▲ 2.44% SLCE3 13.34 ▲ 0.30% NATU3 8.14 ▼ 0.73%
since 2009
Friday, September 25, 2026

Africa Africa & the Great Powers

Tanzania Misses Its Own Deadline on a US$42 Billion LNG Deal

By · August 6, 2026 · 7 min read

Africa Intelligence

One email, every weekday morning. African markets, politics and business — filed from our newsroom in Rio.

Yesterday’s subject line: “Three Ethiopian airports are in Tigrayan hands”

Free. We send a confirmation link first — nothing arrives until you click it. Unsubscribe with one click in any edition. If you stop opening us for 30 days we stop sending by ourselves, as we assume the interest is no longer there. See our privacy policy. We never share your email.

Tanzania · ENERGY

Key Facts

—Deadline missed: Tanzania said in January it would sign the host government agreement for its US$42 billion liquefied natural gas project before June 2026. That target has passed with no signing announced.

—Why the document matters: The agreement is the legal framework the project needs before the companies can commit capital. Until it is signed there can be no final investment decision and no construction.

—Project value: US$42 billion, up from the US$30 billion quoted when the preliminary agreement was signed in Dodoma in June 2022.

—Consortium members: Shell and Equinor lead the group, with ExxonMobil, Pavilion Energy, Medco Energi and the state-owned Tanzania Petroleum Development Corporation (TPDC).

—Gas reserves and timing: The project targets more than 47 trillion cubic feet of offshore gas. Even on the government’s own schedule, first production is not expected until about 2034.

—Near-term drilling: TPDC began drilling the first of three wells at Mnazi Bay on 6 February 2026, a programme costing about 235 billion Tanzanian shillings (roughly US$89 million).

Tanzania said in January that it would sign the legal framework for its US$42 billion liquefied natural gas project before June. Two months past that deadline the document remains unsigned, and the country’s largest single investment is still waiting on a signature.

Ships at the Port of Dar es Salaam, Tanzania
The Port of Dar es Salaam. Tanzania’s gas ambitions rest on export infrastructure that has yet to be built
One-stop reference
Company Intelligence
Every listed company in Latin America — financials, ownership and structure for 1,450+ companies across 26 exchanges, in one place.
Browse the directory →
RT
Ask Rio Times
Latin American markets, currencies and companies.
Open the full Ask Rio Times →

A deadline set in London, and missed

Speaking to reporters in London in January 2026, Kitila Mkumbo, Tanzania’s Minister of State in the President’s Office for Planning and Investment, was unambiguous. “The deal is done and we expect this to be signed before June,” he said, adding that the project was expected to create more than 100,000 jobs. Commercial negotiations, he said, were complete; what remained was legal review by the Attorney General’s office.

June came and went. The Rio Times reported in June that Tanzania expected to sign the agreement that month, on the strength of the minister’s own timetable. As of early August 2026 no signing has been announced by the government, by TPDC or by the companies involved. For a project first agreed in outline more than a decade ago, it is another entry in a long list of missed dates.

For an investor reading from outside Tanzania, the distinction that matters is between a deal being agreed and a deal being signable. The host government agreement is the contract that fixes tax, legal and regulatory terms for the life of the project. Until it exists, Shell, Equinor and their partners cannot take a final investment decision, cannot order equipment and cannot begin construction. Everything else is preparation.

What is still being argued over

The sticking points are the same ones that have slowed the project for years. The government wants a domestic market obligation, reserving a share of the extracted gas for use inside Tanzania rather than sending all of it to export markets. It also wants guaranteed participation for Tanzanian companies in the supply chain. Both are ordinary demands from a resource-holding state, and both cut into project economics.

The counterweight is scale. This is the largest single investment Tanzania has ever attempted, at a value the government now puts at US$42 billion. When President Samia Suluhu Hassan witnessed the signing of the preliminary agreement at State House in Dodoma in June 2022, the figure quoted was US$30 billion. The gap reflects both revised engineering estimates and the passage of time.

At that 2022 ceremony, the president told negotiators to “continue to safeguard the interests of the country in the next stages,” while acknowledging that “it is give-or-take, so both sides should embrace fluidity.” Four years later, the fluidity has not produced a signature.

The resource, and how long it takes to reach a buyer

The project targets more than 47 trillion cubic feet of natural gas in deep water off the southern coast, to be piped ashore and liquefied at a plant at Likong’o, in Lindi region, for export by sea. Shell and Equinor operate the offshore blocks; ExxonMobil, Pavilion Energy, Medco Energi and TPDC hold the remaining interests.

The timeline is the part most often lost in the headline number. When the minister spoke in January he put first production about eight years out, which points to around 2034, and that count already assumes a signature that has not happened. An investor buying into the Tanzanian growth story on the strength of this project is buying a payoff in the next decade, not this one.

Construction itself is expected to run four to six years and to employ around 10,000 people, with roughly 500 permanent jobs once the plant is operating, figures given by the then energy minister, January Makamba, at the 2022 signing.

Smaller projects are moving while the big one waits

A liquefied natural gas carrier under way at sea
An LNG carrier at sea. Tanzania’s project would liquefy gas at Likong’o, in Lindi region, and ship it to buyers in Asia and Europe

While the export megaproject waits, TPDC has pushed ahead with cheaper work on fields that already produce. At Mnazi Bay in Mtwara region, drilling on the first of three wells began on 6 February 2026. Two of the wells, MB-5 and MS-2, are intended to lift output from the existing field; the third, Kasa-1, is an attempt to open a new one.

TPDC Director General Mussa Mohamed Makame, briefing reporters in Dodoma, put the cost of the three-well programme at about 235 billion Tanzanian shillings, roughly US$89 million at current rates. The remaining two wells are expected to be completed by October 2026.

TPDC is separately advancing the Ntorya project in the Ruvuma basin, which includes a 34.2-kilometre pipeline to the Madimba gas processing plant at an estimated cost of about 122.7 billion shillings, or roughly US$46 million. These are modest sums beside the LNG scheme, but they deliver gas within a year or two rather than within a decade, and they are entirely within the state’s own control.

Why outside powers are watching

The consortium itself maps the competition. Shell and Equinor are European; ExxonMobil is American; Pavilion Energy and Medco Energi bring Singaporean and Indonesian capital and a route into Asian demand. Europe wants non-Russian gas, Asia remains the largest LNG import market, and Washington has an interest in an American major holding a stake in one of the continent’s largest energy assets.

China’s presence is in the infrastructure rather than the reserves. The Mtwara to Dar es Salaam gas pipeline, commissioned in 2015, was built with a US$1.2 billion loan from China’s Export-Import Bank. That pipeline carries the gas that Tanzania already uses at home.

The regional context matters too. Mozambique’s LNG build-out has been repeatedly disrupted by conflict in Cabo Delgado, and Uganda is pushing its own oil export route. Tanzania’s pitch is stability. The longer the signature is delayed, the weaker that pitch becomes. The contest is tracked in our pillar Africa: The New Scramble.

What to watch next

The single event that changes the picture is the signing itself. Watch for an announcement from the Ministry of Energy, from TPDC, or in the quarterly disclosures of Shell and Equinor, both of which would have to flag a commitment of this size to their own shareholders.

After that comes the harder test: a final investment decision, which is a separate step and can follow the agreement by years. Environmental approval and the associated legal amendments also remain outstanding.

In the meantime, the honest read is that Tanzania’s near-term gas story is the small onshore programme at Mnazi Bay and Ntorya, not the export terminal. The US$42 billion figure is real, but so is the fact that nobody has yet signed for it.

Frequently Asked Questions

Has Tanzania signed the LNG agreement?

No. The government said in January 2026 that it expected to sign before June, but as of early August 2026 no signing has been announced by the government, TPDC or the companies involved.

How much is the Tanzania LNG project worth?

The government now puts the project at US$42 billion. The figure quoted when the preliminary agreement was signed in June 2022 was US$30 billion.

Which companies are involved, and when would gas actually flow?

Shell and Equinor lead the consortium, with ExxonMobil, Pavilion Energy, Medco Energi and Tanzania’s TPDC. The government put first production about eight years out when it spoke in January 2026, which points to around 2034, a date that already assumes a signature that has not happened.

Connected Coverage

Tanzania’s gas ambitions are part of the wider contest for resources and influence across the continent, tracked in our pillar Africa: The New Scramble.

Sources

This article was produced by The Rio Times’ automated newsroom system. How we use AI · Report an error

LatAm Markets: Live Signals → — real-time movers, turnover leaders and FX across Latin America.

Read More from The Rio Times

The Rio Times · Power Map
See who really holds power in Latin America
Click to open the Power Map →

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.