IBOV 188,268.59 ▲ 1.42% IPSA 11,238.63 ▼ 1.16% IPC MEX 64,106.82 ▼ 1.09% MERVAL 3,157,852 ▲ 1.53% COLCAP 2,626.71 ▲ 1.65% BVL PERÚ 60,702.89 ▼ 2.19% USD/BRL5.10▼ 0.16% USD/MXN16.95▼ 0.20% USD/CLP940.47▲ 1.38% USD/COP3,100▼ 0.32% USD/PEN3.36▲ 0.12% USD/ARS1,513▼ 0.08% USD/UYU40.24▲ 3.05% USD/PYG5,868▲ 2.26% USD/BOB12.36▲ 1.91% USD/DOP58.67▲ 0.29% USD/CRC447.58▲ 1.69% USD/GTQ7.63▲ 3.04% USD/HNL26.85▲ 0.57% USD/NIO36.62▲ 0.34% USD/VES830.41▲ 0.45% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD 157.28 — 0.00% USD/TTD6.73▲ 2.40% EUR/BRL5.91▼ 0.31% BRENT 88.88 ▼ 0.03% WTI 83.11 ▼ 0.11% IRON ORE 161.91 — — COPPER 6.61 ▲ 0.03% GOLD 4,461 ▲ 1.78% SILVER 65.59 ▲ 1.26% SOY 1,184 ▲ 3.20% CORN 480.50 ▲ 10.02% WHEAT 655.00 ▲ 3.93% COFFEE 317.25 ▼ 5.51% SUGAR 16.43 ▼ 1.79% ORANGE JUICE 138.55 ▼ 0.47% COTTON 85.03 ▲ 2.33% COCOA 5,719 ▲ 3.18% BEEF 223.60 ▼ 3.93% CATTLE 339.10 ▼ 3.16% LITHIUM 75.20 ▲ 1.47% PETR4 41.64 ▼ 0.05% VALE3 72.97 ▲ 0.83% ITUB4 38.60 ▼ 1.03% BBDC4 16.85 ▲ 0.36% ABEV3 14.89 ▼ 0.80% BBAS3 19.37 ▲ 0.47% B3SA3 14.26 ▼ 0.21% WEGE3 47.59 ▲ 0.49% PRIO3 59.14 ▼ 0.19% SUZB3 41.33 ▲ 2.35% RENT3 34.68 ▼ 0.09% AZZA3 15.89 ▼ 2.63% CSAN3 3.22 ▼ 1.83% RAIZ4 0.25 — 0.00% PCAR3 2.75 ▼ 0.36% GMAT3 3.65 ▼ 1.08% PSSA3 48.13 ▼ 0.54% CVCB3 1.33 ▼ 2.92% POSI3 3.36 ▲ 2.44% SLCE3 13.34 ▲ 0.30% NATU3 8.14 ▼ 0.73% IBOV 188,268.59 ▲ 1.42% IPSA 11,238.63 ▼ 1.16% IPC MEX 64,106.82 ▼ 1.09% MERVAL 3,157,852 ▲ 1.53% COLCAP 2,626.71 ▲ 1.65% BVL PERÚ 60,702.89 ▼ 2.19% USD/BRL 5.16 ▲ 0.01% USD/MXN 17.06 ▼ 0.24% USD/CLP 913.98 ▲ 0.04% USD/COP 3,140 ▲ 0.03% USD/PEN 3.36 ▼ 0.66% USD/ARS 1,493 ▲ 0.10% USD/UYU 40.27 ▲ 1.24% USD/PYG 5,939 ▲ 1.68% USD/BOB 11.64 ▼ 0.76% USD/DOP 58.34 ▲ 1.25% USD/CRC 445.92 ▲ 0.89% USD/GTQ 7.62 ▲ 2.21% USD/HNL 26.79 ▲ 1.57% USD/NIO 36.62 ▲ 0.69% USD/VES 762.44 ▼ 0.13% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.28 — 0.00% USD/TTD 6.70 ▲ 0.61% EUR/BRL 5.95 ▲ 1.01% BRENT 88.88 ▼ 0.03% WTI 83.11 ▼ 0.11% IRON ORE 161.91 — — COPPER 6.61 ▲ 0.03% GOLD 4,461 ▲ 1.78% SILVER 65.59 ▲ 1.26% SOY 1,184 ▲ 3.20% CORN 480.50 ▲ 10.02% WHEAT 655.00 ▲ 3.93% COFFEE 317.25 ▼ 5.51% SUGAR 16.43 ▼ 1.79% ORANGE JUICE 138.55 ▼ 0.47% COTTON 85.03 ▲ 2.33% COCOA 5,719 ▲ 3.18% BEEF 223.60 ▼ 3.93% CATTLE 339.10 ▼ 3.16% LITHIUM 75.20 ▲ 1.47% PETR4 41.64 ▼ 0.05% VALE3 72.97 ▲ 0.83% ITUB4 38.60 ▼ 1.03% BBDC4 16.85 ▲ 0.36% ABEV3 14.89 ▼ 0.80% BBAS3 19.37 ▲ 0.47% B3SA3 14.26 ▼ 0.21% WEGE3 47.59 ▲ 0.49% PRIO3 59.14 ▼ 0.19% SUZB3 41.33 ▲ 2.35% RENT3 34.68 ▼ 0.09% AZZA3 15.89 ▼ 2.63% CSAN3 3.22 ▼ 1.83% RAIZ4 0.25 — 0.00% PCAR3 2.75 ▼ 0.36% GMAT3 3.65 ▼ 1.08% PSSA3 48.13 ▼ 0.54% CVCB3 1.33 ▼ 2.92% POSI3 3.36 ▲ 2.44% SLCE3 13.34 ▲ 0.30% NATU3 8.14 ▼ 0.73%
since 2009
Friday, September 11, 2026

Business Colombia

Colombia Regional Airports: Only 6 of 14 Projects Underway

By · July 26, 2026 · 5 min read

The LatAm Brief

One email, every weekday morning. What moved in Latin American markets, politics and expat life.

Yesterday’s subject line: “Venezuela pumps the most oil in seven years”

Free. We send a confirmation link first — nothing arrives until you click it. Unsubscribe with one click in any edition. If you stop opening us for 30 days we stop sending by ourselves, as we assume the interest is no longer there. See our privacy policy. We never share your email.

Infrastructure · Colombia

Key Facts

The count. Just six of 14 regional airport projects hold live contracts, according to the Colombian Chamber of Infrastructure (CCI).

The progress. Physical advance on those projects does not exceed 3%.

The cause. The CCI says the main obstacle is no longer financing but the slow pace of processes between the ANI and the aviation regulator Aerocivil.

The asks. It urged the incoming government to fast-track four major airport works already backed by private initiatives.

The projects. Those include expansions at Bogotá’s El Dorado and Cali’s Alfonso Bonilla Aragón, the Cartagena airport and a new runway in Antioquia.

Only six of Colombia’s 14 planned regional airport projects have signed contracts, and even those show almost no progress, the country’s infrastructure lobby warns, blaming bureaucratic delays rather than a lack of money.

Airport in Colombia
Colombia’s regional airport upgrades have stalled at the contracting stage. (Photo: Wikimedia Commons)
One-stop reference
Company Intelligence
Every listed company in Latin America — financials, ownership and structure for 1,450+ companies across 26 exchanges, in one place.
Browse the directory →
RT
Ask Rio Times
Latin American markets, currencies and companies.
Open the full Ask Rio Times →

Contracts Signed, Shovels Idle

Colombia set out to modernize 14 regional airports, but only six have reached the contract stage. Even those barely register on the ground, with progress under 3%.

The result is a pipeline stuck between announcement and construction. For travelers and airlines, it means aging terminals and constrained capacity persist.

To understand why this matters, it helps to picture Colombia’s geography. The Andes split into three towering ranges inside the country, making overland travel between cities a matter of many hours on winding roads.

In that context, regional airports are not a luxury—they are the practical link that connects producers in the coffee belt, business travelers in Medellín, and tourists headed to the Caribbean coaSt When terminal upgrades stall, the economic isolation of whole departments deepens quietly but steadily.

A Bureaucratic Bottleneck, Not a Money One

The Chamber of Infrastructure is blunt about the cause. The problem, it says, is not funding but the slow coordination between the ANI concessions agency and the Aerocivil aviation authority.

Permits, technical sign-offs and inter-agency steps drag on. Private capital is available; the approvals to deploy it are not moving.

For a foreign reader unfamiliar with Colombia’s institutional setup, the ANI—the National Infrastructure Agency—is the state body that structures and oversees public-private partnerships for transport projects. Aerocivil, meanwhile, is the civil aviation authority responsible for airspace safety, airport licensing and technical regulations.

Both must sign off at multiple stages before a shovel hits the ground. When their processes move at different speeds, even a fully financed project can sit frozen.

The CCI’s message is that the bottleneck is procedural, not fiscal, which shifts the pressure from the finance ministry to the technical desks inside these two agencies.

The Big Four in Waiting

The CCI singled out four major works it wants expedited, all with private initiatives already filed. They are the expansion of Bogotá’s El Dorado, the enlargement of Cali’s Alfonso Bonilla Aragón, the Cartagena airport, and a new runway for Antioquia.

Together they represent the backbone of Colombia’s air-connectivity upgrade. Their delay ripples across tourism, trade and regional development.

El Dorado is the country’s main international gateway and a hub for connections across the Americas. Cali’s airport serves the fertile Cauca Valley, a powerhouse for agribusiness and manufacturing.

Cartagena’s terminal is the entry point for one of Latin America’s most visited colonial cities. Antioquia’s proposed new runway would ease pressure on Medellín’s constrained airfield and open a fresh corridor for cargo and passengers.

Each project has a private backer ready to move, which makes the standstill less about finding money and more about clearing the administrative path.

Why It Matters

Air links are decisive for a mountainous country where road travel is slow and costly. Every stalled terminal caps growth in secondary cities.

For investors and expats, the episode is a familiar Colombian story: capital ready, process lagging. Unblocking the ANI-Aerocivil pipeline is now the key to progress.

The broader significance goes beyond construction timelines. Reliable regional aviation shapes where companies choose to locate distribution centers, where international retirees decide to settle, and whether a small coffee grower can reach a buyer in Bogotá within a day.

When the state cannot convert signed contracts into visible works, the credibility of the entire concessions model comes under quiet scrutiny. What to watch next is whether the incoming administration treats the CCI’s call as a quick-win opportunity or lets the inter-agency friction continue.

Another open question is whether the eight projects still without contracts will get the political attention they need, or whether the focus narrows to the four headline airports at the expense of smaller cities that also depend on a functioning airstrip.

Frequently Asked Questions

How many of Colombia’s regional airport projects have contracts?

Only six of 14 planned regional airport projects hold live contracts, and their physical progress does not exceed 3%, according to the Colombian Chamber of Infrastructure.

Why are the projects delayed?

The Chamber of Infrastructure says the obstacle is bureaucratic, specifically slow coordination between the ANI and the Aerocivil aviation regulator, rather than a lack of financing.

Which major airport works are pending?

Priority works include expansions at Bogotá’s El Dorado and Cali’s Alfonso Bonilla Aragón, the Cartagena airport, and a new runway in Antioquia.

Sources

Connected Coverage

Bimbo Struggles to Sell Its Nutrella Bread Brand as Brazil’s CADE Rejects Buyers

BermudAir Orders 10 Airbus A220s in Fleet Expansion Push

Sources: Colombian Chamber of Infrastructure (CCI).

This article was produced by The Rio Times’ automated newsroom system. How we use AI · Report an error

Read More from The Rio Times

The Rio Times · Power Map
See who really holds power in Latin America
Click to open the Power Map

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.