IBOV 168,498.45 ▲ 1.39% IPC MEX 71,393.57 ▲ 0.43% MERVAL 2,848,945 — — USD/BRL5.51▼ 0.01% USD/MXN18.61▲ 0.01% USD/CLP 975.74 — 0.00% USD/COP3,240▲ 0.03% USD/PEN3.44▼ 0.01% USD/ARS 1,545 — 0.00% USD/UYU40.31▲ 3.23% USD/PYG6,358▲ 6.40% USD/BOB11.81▲ 0.77% USD/DOP60.59▲ 4.05% USD/CRC448.27▲ 2.01% USD/GTQ7.64▲ 3.17% USD/HNL26.88▲ 3.19% USD/NIO 36.62 — 0.00% USD/VES895.29▼ 0.13% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD157.99▲ 2.78% USD/TTD6.72▲ 2.44% EUR/BRL6.13▲ 0.07% BRENT 98.32 ▲ 0.03% WTI 90.83 ▲ 0.34% IRON ORE 161.91 — — COPPER 6.24 ▼ 0.18% GOLD 4,075 ▼ 0.94% SILVER 51.94 ▼ 0.56% SOY 1,194 ▲ 1.08% CORN 441.50 ▲ 0.34% WHEAT 591.25 ▼ 1.34% COFFEE 280.15 ▲ 1.08% SUGAR 18.25 ▼ 1.67% ORANGE JUICE 130.55 ▲ 1.63% COTTON 78.54 ▼ 0.22% COCOA 5,119 ▼ 1.20% BEEF 214.05 ▼ 0.16% CATTLE 318.38 ▼ 2.05% LITHIUM 60.91 ▲ 1.21% PETR4 45.36 — 0.00% VALE3 64.04 — 0.00% ITUB4 40.53 — 0.00% BBDC4 14.20 — 0.00% ABEV3 15.48 — 0.00% BBAS3 17.13 — 0.00% B3SA3 14.39 — 0.00% WEGE3 48.19 — 0.00% PRIO3 60.48 — 0.00% SUZB3 53.40 ▲ 2.12% RENT3 30.29 — 0.00% AZZA3 14.76 ▲ 4.98% CSAN3 2.77 — 0.00% RAIZ4 28.00 ▲ 2.56% PCAR3 2.40 ▲ 0.42% GMAT3 3.80 — 0.00% PSSA3 44.35 ▲ 1.46% CVCB3 0.84 ▲ 2.44% POSI3 3.09 ▼ 0.64% SLCE3 16.61 ▲ 1.59% NATU3 5.17 — 0.00% BRKM5 3.20 — 0.00% RANI3 8.53 ▲ 0.83% CSNA3 4.41 — 0.00% IBOV 168,498.45 ▲ 1.39% IPC MEX 71,393.57 ▲ 0.43% MERVAL 2,848,945 — — USD/BRL 5.51 ▼ 0.01% USD/MXN 18.61 ▲ 0.01% USD/CLP 975.74 — 0.00% USD/COP 3,240 ▲ 0.03% USD/PEN 3.44 ▼ 0.01% USD/ARS 1,545 — 0.00% USD/UYU 40.31 ▲ 3.23% USD/PYG 6,358 ▲ 6.40% USD/BOB 11.81 ▲ 0.77% USD/DOP 60.59 ▲ 4.05% USD/CRC 448.27 ▲ 2.01% USD/GTQ 7.64 ▲ 3.17% USD/HNL 26.88 ▲ 3.19% USD/NIO 36.62 — 0.00% USD/VES 895.29 ▼ 0.13% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.99 ▲ 2.78% USD/TTD 6.72 ▲ 2.44% EUR/BRL 6.13 ▲ 0.07% BRENT 98.32 ▲ 0.03% WTI 90.83 ▲ 0.34% IRON ORE 161.91 — — COPPER 6.24 ▼ 0.18% GOLD 4,075 ▼ 0.94% SILVER 51.94 ▼ 0.56% SOY 1,194 ▲ 1.08% CORN 441.50 ▲ 0.34% WHEAT 591.25 ▼ 1.34% COFFEE 280.15 ▲ 1.08% SUGAR 18.25 ▼ 1.67% ORANGE JUICE 130.55 ▲ 1.63% COTTON 78.54 ▼ 0.22% COCOA 5,119 ▼ 1.20% BEEF 214.05 ▼ 0.16% CATTLE 318.38 ▼ 2.05% LITHIUM 60.91 ▲ 1.21% PETR4 45.36 — 0.00% VALE3 64.04 — 0.00% ITUB4 40.53 — 0.00% BBDC4 14.20 — 0.00% ABEV3 15.48 — 0.00% BBAS3 17.13 — 0.00% B3SA3 14.39 — 0.00% WEGE3 48.19 — 0.00% PRIO3 60.48 — 0.00% SUZB3 53.40 ▲ 2.12% RENT3 30.29 — 0.00% AZZA3 14.76 ▲ 4.98% CSAN3 2.77 — 0.00% RAIZ4 28.00 ▲ 2.56% PCAR3 2.40 ▲ 0.42% GMAT3 3.80 — 0.00% PSSA3 44.35 ▲ 1.46% CVCB3 0.84 ▲ 2.44% POSI3 3.09 ▼ 0.64% SLCE3 16.61 ▲ 1.59% NATU3 5.17 — 0.00% BRKM5 3.20 — 0.00% RANI3 8.53 ▲ 0.83% CSNA3 4.41 — 0.00%
since 2009
Sunday, November 8, 2026

Argentina Energy

Argentina Starts LNG Export Pipeline

By · · 4 min read
View from a hillside of the town of Añelo in Neuquén province, the service hub of the Vaca Muerta shale oil basin
File photo, 2014. The Neuquén town of Añelo, a service hub of the Vaca Muerta shale area.

Argentina is laying the steel that will carry its shale gas to the sea, so that tankers can ship it to the world. On Sunday, 8 November 2026, the San Matías pipeline was under construction, with pipe moving along the route and first excavations done.

The project is meant to turn Vaca Muerta, a major shale formation in Patagonia, into an export business for liquefied natural gas (LNG), gas chilled into a liquid for ships. It matters to US readers because YPF, Argentina’s state-controlled oil company listed on the New York Stock Exchange, is a partner in the export venture.

Key Facts

Free daily brief — no card needed
Get every Argentina story in one morning email
We build you a personalized brief around the topics you follow — free for 7 days. Love it? Your first month after that is US$1.

—What. Construction of the 472 km San Matías gas pipeline has started in Argentina. Cost: about US$1.3 billion.

—Where. It links the Vaca Muerta shale gas field in Neuquén province to the Atlantic coast of Río Negro.

—Capacity. Up to 27 million cubic metres of gas a day, for two floating LNG plants.

—When. Completion is planned for around mid-2028; the project holds approval under Argentina’s RIGI investment regime.

—Power Index. Argentina ranks 4th of 14 in The Rio Times Latin America Power Index, with 60.2 points (November 2026 edition).

A US$1.3 billion pipeline of 472 km is rising across Patagonia, and it will decide how fast Argentina can sell gas abroad. The line is due to finish around mid-2028.

What Happened

San Matías Pipeline, the company building the line, has begun moving 36-inch steel pipes by truck from the port of San Antonio Este to staging areas along the route. The Río Negro provincial government said on 5 October 2026 that the first excavations had also started.

The line will run 472 km from Vaca Muerta to the Gulf of San Matías, in Río Negro. It is designed to carry up to 27 million cubic metres of gas a day, according to the provincial government.

Argentina’s Economy Ministry approved the project in June 2026 under RIGI, a regime that gives large investments tax and currency benefits. On 28 August 2026 the provincial government said San Matías Pipeline had closed a US$900 million international bank loan, about 70% of the cost.

Neuquén city, Argentina
The city of Neuquén, capital of the Argentine province where the Vaca Muerta gas field lies. photo. The city of Neuquén, capital of Neuquén Province, Argentina, undated. Photo: miroab, CC BY-SA 2.0, Wikimedia Commons.

Who Is Behind It

Southern Energy, an Argentine export consortium, will use the gas for two floating liquefaction ships anchored in the gulf. Its partners are Pan American Energy (a large Argentine oil company), YPF, Pampa Energía (an Argentine power and gas producer), Harbour Energy (a British oil company) and Golar LNG, a floating-LNG specialist.

The two ships have a combined capacity of close to 6 million tonnes of LNG a year. The provincial government expects the whole project to exceed US$15 billion of investment over 20 years.

Regional lenders such as Bladex have already backed the venture, as our report on the Bladex loan to Southern Energy shows. Bladex is a Latin American trade bank.

Why It Matters

Argentina has the gas but lacks the export infrastructure to sell it beyond South America. A dedicated line gives that gas a route to the coast, as our earlier report on the Vaca Muerta oil and pipeline loan showed.

For the United States, new LNG supply from the Southern Hemisphere adds competition for buyers in Europe and Asia. It also gives US investors in YPF a clearer view of the timeline, which we followed in YPF’s LNG contracts.

What Happens Next

The pipeline is due to be finished around mid-2028, according to the Río Negro government. The two floating plants and the line will have to move in step before any cargo can sail.

Further pipe shipments will arrive at San Antonio Este through the coming months. The project will also need contracts as buyers sign for cargoes.

What Is Not Known

The exact date of the first LNG cargo has not been confirmed by the companies in the documents we could check. The cost of the full project may also change as construction advances.

We could not confirm independently when pipe welding began or which contractor leads it. We have left both out until the company or the province publishes them.

What It Means for You

If you follow energy stocks, watch YPF and its partners for updates on financing and delivery dates. A line this size takes years, so short-term price moves are more likely to come from announcements than from gas actually flowing.

Travellers in Patagonia may see more pipe trucks on the roads of Río Negro. A local cooperative, RioQuen, has put nine trucks on the pipe haul.

Frequently Asked Questions

Which pipeline has started construction in Argentina?

It is the San Matías pipeline, 472 km long, from Vaca Muerta to the Gulf of San Matías. It will carry gas for two floating LNG plants.

How much does the San Matías pipeline cost?

The estimated cost is about US$1.3 billion. About US$900 million comes from an international bank loan, according to the Río Negro government.

When will the gas pipeline be finished?

Completion is expected around mid-2028, according to the Río Negro government. Dates can slip on large projects like this one.

Sources

Government of Río Negro province, pipeline and excavation statement (5 October 2026) and financing statement (28 August 2026); Argentina Economy Ministry RIGI approval (June 2026). Read on 8 November 2026.

RT
Ask Rio Times
17 years of Latin America reporting, on demand.
Open the full Ask Rio Times →

This article was produced by The Rio Times’ automated AI newsroom. Editorial responsibility: Matthias Camenzind, Publisher and Editor-in-Chief. How we use AI · Report an error

The Rio Times · Power Map
See who really holds power in Latin America
Click to open the Power Map →

Brazil runoff date: Sunday, October 25, poll closing times and when results start · Brazil runoff polls: Flávio 51%, Lula 49% · Kalshi and Polymarket odds

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.