IBOV 187,206.89 ▼ 0.56% IPSA 11,220.60 ▼ 0.16% IPC MEX 63,924.77 ▼ 0.28% MERVAL 3,098,898 ▼ 1.87% COLCAP 2,589.69 ▼ 1.41% BVL PERÚ 59,373.28 ▼ 0.32% USD/BRL5.13▲ 0.40% USD/MXN16.96▼ 0.14% USD/CLP941.13— 0.00% USD/COP3,078— 0.00% USD/PEN3.35▲ 0.03% USD/ARS1,509▼ 0.28% USD/UYU40.26▲ 3.12% USD/PYG5,903▲ 3.23% USD/BOB11.98▼ 2.70% USD/DOP58.96▲ 0.79% USD/CRC447.55▲ 1.57% USD/GTQ7.63▲ 2.98% USD/HNL26.85▲ 0.57% USD/NIO36.62— 0.00% USD/VES830.41▼ 0.13% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD 157.28 — 0.00% USD/TTD6.74▲ 2.35% EUR/BRL5.95▲ 0.25% BRENT 88.88 ▼ 0.03% WTI 83.11 ▼ 0.11% IRON ORE 161.91 — — COPPER 6.61 ▲ 0.03% GOLD 4,461 ▲ 1.78% SILVER 65.59 ▲ 1.26% SOY 1,184 ▲ 3.20% CORN 480.50 ▲ 10.02% WHEAT 655.00 ▲ 3.93% COFFEE 317.25 ▼ 5.51% SUGAR 16.43 ▼ 1.79% ORANGE JUICE 138.55 ▼ 0.47% COTTON 85.03 ▲ 2.33% COCOA 5,719 ▲ 3.18% BEEF 223.60 ▼ 3.93% CATTLE 339.10 ▼ 3.16% LITHIUM 75.20 ▲ 1.47% PETR4 41.64 ▼ 0.05% VALE3 72.97 ▲ 0.83% ITUB4 38.60 ▼ 1.03% BBDC4 16.85 ▲ 0.36% ABEV3 14.89 ▼ 0.80% BBAS3 19.37 ▲ 0.47% B3SA3 14.26 ▼ 0.21% WEGE3 47.59 ▲ 0.49% PRIO3 59.14 ▼ 0.19% SUZB3 41.33 ▲ 2.35% RENT3 34.68 ▼ 0.09% AZZA3 15.89 ▼ 2.63% CSAN3 3.22 ▼ 1.83% RAIZ4 0.25 — 0.00% PCAR3 2.75 ▼ 0.36% GMAT3 3.65 ▼ 1.08% PSSA3 48.13 ▼ 0.54% CVCB3 1.33 ▼ 2.92% POSI3 3.36 ▲ 2.44% SLCE3 13.34 ▲ 0.30% NATU3 8.14 ▼ 0.73% IBOV 187,206.89 ▼ 0.56% IPSA 11,220.60 ▼ 0.16% IPC MEX 63,924.77 ▼ 0.28% MERVAL 3,098,898 ▼ 1.87% COLCAP 2,589.69 ▼ 1.41% BVL PERÚ 59,373.28 ▼ 0.32% USD/BRL 5.16 ▲ 0.01% USD/MXN 17.06 ▼ 0.24% USD/CLP 913.98 ▲ 0.04% USD/COP 3,140 ▲ 0.03% USD/PEN 3.36 ▼ 0.66% USD/ARS 1,493 ▲ 0.10% USD/UYU 40.27 ▲ 1.24% USD/PYG 5,939 ▲ 1.68% USD/BOB 11.64 ▼ 0.76% USD/DOP 58.34 ▲ 1.25% USD/CRC 445.92 ▲ 0.89% USD/GTQ 7.62 ▲ 2.21% USD/HNL 26.79 ▲ 1.57% USD/NIO 36.62 ▲ 0.69% USD/VES 762.44 ▼ 0.13% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.28 — 0.00% USD/TTD 6.70 ▲ 0.61% EUR/BRL 5.95 ▲ 1.01% BRENT 88.88 ▼ 0.03% WTI 83.11 ▼ 0.11% IRON ORE 161.91 — — COPPER 6.61 ▲ 0.03% GOLD 4,461 ▲ 1.78% SILVER 65.59 ▲ 1.26% SOY 1,184 ▲ 3.20% CORN 480.50 ▲ 10.02% WHEAT 655.00 ▲ 3.93% COFFEE 317.25 ▼ 5.51% SUGAR 16.43 ▼ 1.79% ORANGE JUICE 138.55 ▼ 0.47% COTTON 85.03 ▲ 2.33% COCOA 5,719 ▲ 3.18% BEEF 223.60 ▼ 3.93% CATTLE 339.10 ▼ 3.16% LITHIUM 75.20 ▲ 1.47% PETR4 41.64 ▼ 0.05% VALE3 72.97 ▲ 0.83% ITUB4 38.60 ▼ 1.03% BBDC4 16.85 ▲ 0.36% ABEV3 14.89 ▼ 0.80% BBAS3 19.37 ▲ 0.47% B3SA3 14.26 ▼ 0.21% WEGE3 47.59 ▲ 0.49% PRIO3 59.14 ▼ 0.19% SUZB3 41.33 ▲ 2.35% RENT3 34.68 ▼ 0.09% AZZA3 15.89 ▼ 2.63% CSAN3 3.22 ▼ 1.83% RAIZ4 0.25 — 0.00% PCAR3 2.75 ▼ 0.36% GMAT3 3.65 ▼ 1.08% PSSA3 48.13 ▼ 0.54% CVCB3 1.33 ▼ 2.92% POSI3 3.36 ▲ 2.44% SLCE3 13.34 ▲ 0.30% NATU3 8.14 ▼ 0.73%
since 2009
Sunday, September 13, 2026

Colombia Starts Clearing 553 Stalled Infrastructure Permits

By · September 13, 2026 · 4 min read

The LatAm Brief

One email, every weekday morning. What moved in Latin American markets, politics and expat life.

Yesterday’s subject line: “'The false peace is over' - Colombia”

Free. We send a confirmation link first — nothing arrives until you click it. Unsubscribe with one click in any edition. If you stop opening us for 30 days we stop sending by ourselves, as we assume the interest is no longer there. See our privacy policy. We never share your email.

COLOMBIA · INFRASTRUCTURE

Key Facts

  • The plan Colombia’s infrastructure agency is clearing a backlog of 553 stalled permit applications.
  • The start Monday 14 September 2026.
  • What the permits are Authorisations to use, occupy and intervene in road and rail infrastructure on concessioned corridors.
  • The priority Essential public services first: water, sewerage, gas and electricity.
  • The backlog Some files have been stalled for more than two years.
  • The claim ANI says resolution benefits more than 15 million people across 11 departments.

These are not planning applications. They are the permissions a utility needs to lay a pipe across a motorway, and 553 of them have been sitting still.

A Colombian highway
Colombia Starts Clearing 553 Stalled Infrastructure Permits
One-stop reference
Company Intelligence
Every listed company in Latin America — financials, ownership and structure for 1,450+ companies across 26 exchanges, in one place.
Browse the directory →
RT
Ask Rio Times
Latin American markets, currencies and companies.
Open the full Ask Rio Times →

Colombia’s Agencia Nacional de Infraestructura begins a clearance programme on Monday aimed at resolving 553 permit applications that have accumulated on concessioned road and rail corridors, some stalled for more than two years.

What the Permits Actually Are

The backlog consists of permisos de uso, ocupación e intervención, authorisations for a third party to use, occupy or intervene in road and rail infrastructure that sits under a national concession.

In practice these are the permissions a utility needs to cross a concessioned highway with a water main, a gas pipe or an electricity line, or to work within the right of way alongside it.

Describing them as generic administrative procedures understates what the delay costs. A water connection that cannot cross a motorway is a neighbourhood without water, and the permit is the only thing standing between the two.

The Plan

ANI announced the plan de choque on 11 September and begins executing it on Monday 14 September. Priority goes to files involving essential public services: water, sewerage, gas and electricity.

The agency, headed by Ricardo Ayerbe, says it will monitor progress weekly against performance indicators. No completion date has been announced.

ANI puts the benefit at more than 15 million people across 11 departments, which is the agency’s own figure and describes the population served by the utilities waiting on the permits rather than people directly affected.

A Colombian road corridor
Concessionaires hold operational control of corridors for decades.

Why the Backlog Formed

Concession contracts in Colombia give the private concessionaire operational control of a corridor for two to three decades, and any third-party intervention has to be reconciled with that contract as well as with technical and safety requirements.

That produces a permit process with several parties and no single owner of the timetable, which is the structural reason files stall rather than a failure attributable to any one of them.

Files stuck for more than two years indicate the process has no effective deadline, and a clearance programme addresses the stock without changing that.

What Would Make It Durable

A backlog cleared without a procedural change reaccumulates. The measure of whether this works is not how many of the 553 are resolved but how long the next application takes.

Weekly indicators are a reasonable start, because the absence of any measured service standard is what allowed the backlog to form. Whether they survive past the clearance is the question.

Bogotá
Clearing permits is among the cheapest infrastructure measures available.

The Wider Context

Colombia’s infrastructure programme has been slowed through 2026 by fiscal constraints, with the 2027 budget pointing to the country’s largest recorded deficit.

Clearing permits is among the cheapest things a government can do for infrastructure delivery, because the investment is being made by someone else and the state is only removing an obstacle to it. That is presumably part of the appeal.

The 11 departments ANI names are not identified in the announcement, and neither is the split between road and rail files. Both would say something about where the bottleneck actually sits.

Rail is the smaller share of Colombia’s concessioned network by a wide margin, so the backlog is almost certainly concentrated on the road corridors that carry the country’s freight between the Andean interior and the Caribbean ports.

Frequently Asked Questions

What is ANI clearing?

553 stalled applications for permits to use, occupy or intervene in concessioned road and rail infrastructure.

When does it start?

Monday 14 September 2026.

What gets priority?

Files involving essential public services: water, sewerage, gas and electricity.

How long have they been stalled?

Some for more than two years.

Who benefits?

ANI says more than 15 million people across 11 departments.

Sources: La República, El Tiempo, Infobae Colombia, El Heraldo.

This article was drafted with automated assistance and reviewed before publication. How we use AI · Report an error

Read More from The Rio Times

The Rio Times · Power Map
See who really holds power in Latin America
Click to open the Power Map

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.