IBOV 166,012.61 ▲ 0.74% COLCAP 2,452.46 — — IPC MEX 69,355.62 ▲ 1.06% MERVAL 2,848,945 — — USD/BRL5.82▼ 1.85% USD/MXN19.30▲ 0.64% USD/CLP1,022▲ 0.57% USD/COP3,555▲ 7.43% USD/PEN3.47▲ 0.39% USD/ARS1,589▲ 0.57% USD/UYU40.72▲ 3.56% USD/PYG6,399▲ 4.83% USD/BOB11.72▲ 3.82% USD/DOP59.57▲ 2.09% USD/CRC440.90▲ 1.97% USD/GTQ7.64▲ 3.48% USD/HNL26.89▲ 3.50% USD/NIO36.62▲ 2.97% USD/VES917.52▼ 0.13% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD157.09▲ 2.61% USD/TTD6.72▲ 2.42% EUR/BRL6.39▼ 2.09% BRENT 87.49 ▼ 2.10% WTI 80.77 ▲ 0.75% IRON ORE 161.91 — — COPPER 5.51 ▼ 2.10% GOLD 3,616 ▼ 0.96% SILVER 41.89 ▼ 2.91% SOY 1,233 ▲ 0.31% CORN 448.00 ▲ 3.17% WHEAT 591.75 ▲ 2.56% COFFEE 264.25 ▼ 3.68% SUGAR 17.67 ▲ 0.34% ORANGE JUICE 134.30 — 0.00% COTTON 81.11 ▲ 4.62% COCOA 5,399 ▲ 4.11% BEEF 224.60 ▲ 0.72% CATTLE 334.25 ▼ 0.35% LITHIUM 54.70 ▲ 5.23% PETR4 42.06 ▲ 1.84% VALE3 56.62 ▼ 3.06% ITUB4 40.49 ▲ 1.91% BBDC4 14.01 ▲ 2.19% ABEV3 16.03 ▲ 0.56% BBAS3 14.39 ▲ 1.34% B3SA3 14.45 ▲ 2.05% WEGE3 49.61 ▼ 0.60% PRIO3 59.40 ▲ 2.03% SUZB3 55.06 ▼ 0.24% RENT3 29.34 ▲ 2.09% AZZA3 14.87 ▲ 1.99% CSAN3 3.32 ▲ 5.73% RAIZ4 13.90 ▼ 7.33% PCAR3 3.70 ▲ 2.78% GMAT3 4.26 ▲ 3.65% PSSA3 43.49 ▲ 1.35% CVCB3 0.74 ▲ 2.78% POSI3 3.35 ▼ 0.89% SLCE3 17.12 ▲ 1.06% NATU3 4.71 ▲ 3.52% BRKM5 2.81 ▼ 3.44% RANI3 7.90 ▲ 1.15% IBOV 166,012.61 ▲ 0.74% COLCAP 2,452.46 — — IPC MEX 69,355.62 ▲ 1.06% MERVAL 2,848,945 — — USD/BRL 5.83 ▼ 1.64% USD/MXN 19.31 ▲ 0.68% USD/CLP 1,023 ▲ 0.69% USD/COP 3,565 ▲ 7.71% USD/PEN 3.46 ▲ 0.19% USD/ARS 1,589 ▲ 0.54% USD/UYU 40.61 ▲ 3.28% USD/PYG 6,212 ▲ 1.77% USD/BOB 11.72 ▲ 3.82% USD/DOP 59.74 ▲ 2.38% USD/CRC 441.73 ▲ 2.16% USD/GTQ 7.64 ▲ 3.48% USD/HNL 26.89 ▲ 3.51% USD/NIO 36.62 ▲ 2.97% USD/VES 913.46 ▼ 0.57% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.09 ▲ 2.61% USD/TTD 6.70 ▲ 2.17% EUR/BRL 6.40 ▼ 1.83% BRENT 87.49 ▼ 2.10% WTI 80.77 ▲ 0.75% IRON ORE 161.91 — — COPPER 5.51 ▼ 2.10% GOLD 3,616 ▼ 0.96% SILVER 41.89 ▼ 2.91% SOY 1,233 ▲ 0.31% CORN 448.00 ▲ 3.17% WHEAT 591.75 ▲ 2.56% COFFEE 264.25 ▼ 3.68% SUGAR 17.67 ▲ 0.34% ORANGE JUICE 134.30 — 0.00% COTTON 81.11 ▲ 4.62% COCOA 5,399 ▲ 4.11% BEEF 224.60 ▲ 0.72% CATTLE 334.25 ▼ 0.35% LITHIUM 54.70 ▲ 5.23% PETR4 42.06 ▲ 1.84% VALE3 56.62 ▼ 3.06% ITUB4 40.49 ▲ 1.91% BBDC4 14.01 ▲ 2.19% ABEV3 16.03 ▲ 0.56% BBAS3 14.39 ▲ 1.34% B3SA3 14.45 ▲ 2.05% WEGE3 49.61 ▼ 0.60% PRIO3 59.40 ▲ 2.03% SUZB3 55.06 ▼ 0.24% RENT3 29.34 ▲ 2.09% AZZA3 14.87 ▲ 1.99% CSAN3 3.32 ▲ 5.73% RAIZ4 13.90 ▼ 7.33% PCAR3 3.70 ▲ 2.78% GMAT3 4.26 ▲ 3.65% PSSA3 43.49 ▲ 1.35% CVCB3 0.74 ▲ 2.78% POSI3 3.35 ▼ 0.89% SLCE3 17.12 ▲ 1.06% NATU3 4.71 ▲ 3.52% BRKM5 2.81 ▼ 3.44% RANI3 7.90 ▲ 1.15%
since 2009
Tuesday, November 24, 2026

Chile Latin America

Dominga Mine Rejection Stands in Chile as Andes Iron Drops Supreme Court Appeals

Andes Iron withdrew its Supreme Court appeals, so the rejection of Chile's Dominga mine stands. The US$3bn project now hinges on Kast's ministers.

By · · 5 min read
Beach and fishing boats at Isla Damas in the Humboldt Penguin National Reserve, Coquimbo Region, Chile
Isla Damas in the Humboldt Penguin National Reserve, the protected marine area near the planned Dominga mine and port in La Higuera, Coquimbo Region. (Photo: Camila Fernanda Reyes Vera, CC BY-SA 4.0 via Wikimedia Commons)
RT
Ask Rio Times
17 years of Latin America reporting, on demand.
Open the full Ask Rio Times →

MINING · CHILE

Key Facts

  • The country Chile, where the planned Dominga iron and copper mine and port in La Higuera, Coquimbo Region, has been disputed for more than a decade.
  • What happened On 28 September 2026 Andes Iron withdrew its Supreme Court appeals. A 20 February 2026 appeals-court ruling that left the project’s rejection firm therefore stands (El Desconcierto, La Tercera).
  • Who is involved Andes Iron, linked to the Délano Méndez and Garcés families; Los Choros fishers and environmental groups opposing Dominga; and pro-Dominga groups seeking to annul the rejection.
  • What it means for you A project Andes Iron values at more than US$3 billion (La Tercera, CNN Chile) stays blocked. Any revival now runs through ministers in President José Antonio Kast’s cabinet.
  • Still open The Environmental Evaluation Service has admitted requests to invalidate the January 2025 rejection. No date for a decision has been announced.

The rejection of the Dominga mine in Chile stands after Andes Iron dropped its Supreme Court appeals on 28 September. El Desconcierto and BioBioChile reported the move.

Free daily brief — no card needed
Get every Chile story in one morning email
We build you a personalized brief around the topics you follow — free for 7 days. Love it? Your first month after that is US$1.

The company now wants President José Antonio Kast’s ministers to reopen the file. The iron and copper project with its own port in La Higuera, Coquimbo Region, has been contested for more than a decade.

Andes Iron puts the investment at more than US$3 billion, La Tercera reported.

What Andes Iron Withdrew

The company filed a brief abandoning its cassation and complaint appeals against a 20 February ruling by the Antofagasta Court of Appeals. That ruling had left firm a January 2025 rejection by a committee of ministers.

The judges had already decided the case and only the drafting of the ruling remained, said lawyer Antonia Berríos. She represents the association of fishers and shellfish divers of Los Choros, a fishing village nearby.

“The effect of this action by the company is that no ruling will be issued,” Berríos told El Desconcierto and Cooperativa. The Antofagasta decision therefore stands.

Why the Company Says It Stepped Back

In a statement, Andes Iron said the court case had frozen invalidation requests filed by pro-Dominga social organisations. It withdrew “so as not to obstruct their progress,” the statement said, as quoted by Cooperativa and La Tercera.

The company argues that the 2025 rejection “openly contravened” an earlier ruling of the First Environmental Court, a specialised tribunal. It called the rejection an administrative act carried out in contempt of that court.

Andes Iron told Cooperativa the move is a change of strategy, not the end of the project. It will seek a new decision from a committee of ministers, this time drawn from Kast’s cabinet.

The Environmental Evaluation Service (SEA), which runs Chile’s permit reviews, has admitted the invalidation requests. El Desconcierto and Diario El Día reported this.

More Than a Decade of Permits and Courts

A regional environmental commission in Coquimbo approved Dominga in August 2021, and the company says that permit remains valid. In January 2023 a committee of ministers under President Gabriel Boric rejected the project.

A second committee vote rejected it again in January 2025. Andes Iron then tried to enforce the environmental court’s ruling through a compliance procedure, which the Antofagasta court blocked in February 2026.

On 10 August 2026 the company declared the start of construction, general manager Pedro Ducci said. Opponents called it a pressure tactic, since Dominga lacked a final environmental permit.

A report by CONAF, the national forestry agency, found protected native vegetation had been cut without an approved plan, El Desconcierto reported. Andes Iron rejected the accusation and said the work was rehabilitation of wells covered by its permit.

Why the Pressure Moves to Kast

Opponents say no court remedies remain against the Antofagasta ruling. They argue the invalidation route could open a political exit under the Kast government.

Carolina Bahamondes of MODEMA, a local environmental group, asked if it is valid “to override ethics and the judiciary” for a rejected project. Nancy Duman of the Alianza Humboldt coalition said Dominga has ended its evaluation in rejection three times.

Supporters see a stalled investment in a region short of jobs. On 28 September, the day of the withdrawal, Kast unveiled an emergency jobs plan and has also pushed faster environmental approvals.

The stabilising factor is that any new decision must follow a formal procedure that can be challenged. The risk for the government is that a quick approval could draw fresh lawsuits from fishers.

What Is Not Yet Known

It is not known when the SEA or a committee of ministers will rule on the invalidation requests. Kast’s government has not said whether it will defend or revisit the 2025 rejection.

The status of the preparatory works declared in August also remains disputed. Andes Iron plans larger works from the first quarter of 2027, La Tercera reported.

Frequently Asked Questions

Is the Dominga mine approved or rejected?

It is rejected. The January 2025 rejection by a committee of ministers stands. The Antofagasta Court of Appeals upheld it, and Andes Iron dropped its Supreme Court appeals.

Why did Andes Iron withdraw its appeals?

The company said the court case had frozen invalidation requests against the 2025 rejection. It wants those requests to move forward through the administrative route.

What role does Kast’s government play?

If the invalidation requests advance, the file could return to a committee of ministers from Kast’s cabinet. Opponents say an approval by that route would sidestep the courts.

What did Andes Iron do?

It withdrew its Supreme Court appeals on 28 September 2026, so the rejection of the Dominga mine and port project stands.

Sources: El Desconcierto; Cooperativa; La Tercera; BioBioChile; CNN Chile; Diario El Día (all 28–29 September 2026); Andes Iron public statement of 28 September 2026 as quoted by Cooperativa and La Tercera.

This article was produced by The Rio Times’ automated AI newsroom. Editorial responsibility: Matthias Camenzind, Publisher and Editor-in-Chief. The Rio Times also runs Ask Rio Times, which answers from 100,000+ of our own articles, the daily Latin America Power Map, and prediction-market odds on elections and markets.. How we use AI · Report an error

The Rio Times · Power Map
See who really holds power in Latin America
Click to open the Power Map →

Brazil runoff date: Sunday, October 25, poll closing times and when results start · Brazil runoff polls: Flávio 51%, Lula 49% · Kalshi and Polymarket odds

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.