How much gas Argentina’s Néstor Kirchner Gas Pipeline will be able to transport as of June 20

The Argentine government is set to inaugurate the Néstor Kirchner gas pipeline on June 20, marking a significant step towards energy self-sufficiency.
The pipeline will enable the transportation of non-conventional gas from Vaca Muerta to the province of Buenos Aires.
According to the Chief of Cabinet, Agustín Rossi, the pipeline was 63.9% complete by the end of May 2023.
However, it is expected to be 80-85% complete by the inauguration date, which would allow Enarsa to authorize the ‘Apto Para Funcionar’ (APF).
Oscar Sardi, CEO of Transportadora Gas del Sur (TGS), anticipates the pipeline will take about a month to become fully operational.
By May 2023, the Néstor Kirchner gas pipeline had received investments of US$318 billion, and an estimated US$361 billion will be needed for its completion.
The pipeline is projected to enhance the current gas transportation capacity by 11 million m3/day, leading to an annual foreign currency saving of US$2.249 billion.
The government predicts the project will be 100% complete by November 2023.
By July, the pipeline is expected to add 10 million m3/d to the transport capacity, followed by an additional 19 million m3/d by autumn 2024 and another 18 million m3/d by winter 2024.
This would result in a total capacity increase of 58 million m3/d, resulting in a foreign currency saving of US$7.461 billion.
More: Argentina news in English, every day from The Rio Times.
This article was produced by The Rio Times’ automated AI newsroom. Editorial responsibility: Matthias Camenzind, Publisher and Editor-in-Chief. The Rio Times also runs Ask Rio Times, which answers from 100,000+ of our own articles, the daily Latin America Power Map, and prediction-market odds on elections and markets.. How we use AI · Report an error