IBOV 164,089.81 ▼ 0.43% COLCAP 2,452.46 — — IPC MEX 69,932.54 ▲ 0.83% MERVAL 2,848,945 — — USD/BRL5.89▼ 0.63% USD/MXN19.41▲ 1.23% USD/CLP1,033▲ 1.62% USD/COP3,602▲ 8.85% USD/PEN3.48▲ 0.69% USD/ARS1,592▲ 0.76% USD/UYU40.72▲ 3.56% USD/PYG6,399▲ 4.83% USD/BOB11.72▲ 3.82% USD/DOP59.74▲ 2.38% USD/CRC440.90▲ 1.97% USD/GTQ7.64▲ 3.48% USD/HNL26.89▲ 3.50% USD/NIO36.62▲ 2.97% USD/VES917.52▼ 0.13% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD157.09▲ 2.61% USD/TTD6.72▲ 2.42% EUR/BRL6.48▼ 0.73% BRENT 88.50 ▼ 0.97% WTI 81.69 ▲ 1.90% IRON ORE 161.91 — — COPPER 5.48 ▼ 2.54% GOLD 3,555 ▼ 2.64% SILVER 40.71 ▼ 5.65% SOY 1,232 ▲ 0.28% CORN 450.25 ▲ 3.68% WHEAT 588.75 ▲ 2.04% COFFEE 260.40 ▼ 5.08% SUGAR 17.70 ▲ 0.51% ORANGE JUICE 131.20 ▼ 2.31% COTTON 82.34 ▲ 6.20% COCOA 5,444 ▲ 4.97% BEEF 229.93 ▲ 2.39% CATTLE 332.95 ▼ 0.41% LITHIUM 53.69 ▼ 1.85% PETR4 40.55 ▼ 1.82% VALE3 55.19 ▼ 5.51% ITUB4 39.74 ▲ 0.03% BBDC4 13.62 ▼ 0.66% ABEV3 16.10 ▲ 1.00% BBAS3 14.18 ▼ 0.14% B3SA3 14.18 ▲ 0.14% WEGE3 50.20 ▲ 0.58% PRIO3 59.60 ▲ 2.37% SUZB3 56.14 ▲ 1.72% RENT3 28.51 ▼ 0.80% AZZA3 14.18 ▼ 2.74% CSAN3 3.23 ▲ 2.87% RAIZ4 13.90 ▼ 7.33% PCAR3 3.27 ▼ 9.17% GMAT3 4.10 ▼ 0.24% PSSA3 41.93 ▼ 2.28% CVCB3 0.69 ▼ 4.17% POSI3 3.14 ▼ 7.10% SLCE3 16.81 ▼ 0.77% NATU3 4.26 ▼ 6.37% BRKM5 2.50 ▼ 14.09% RANI3 7.83 ▲ 0.26% IBOV 164,089.81 ▼ 0.43% COLCAP 2,452.46 — — IPC MEX 69,932.54 ▲ 0.83% MERVAL 2,848,945 — — USD/BRL 5.91 ▼ 0.43% USD/MXN 19.41 ▲ 1.23% USD/CLP 1,033 ▲ 1.62% USD/COP 3,602 ▲ 8.85% USD/PEN 3.48 ▲ 0.69% USD/ARS 1,592 ▲ 0.76% USD/UYU 40.72 ▲ 3.56% USD/PYG 6,399 ▲ 4.83% USD/BOB 11.72 ▲ 3.82% USD/DOP 59.74 ▲ 2.38% USD/CRC 440.90 ▲ 1.97% USD/GTQ 7.64 ▲ 3.48% USD/HNL 26.89 ▲ 3.50% USD/NIO 36.62 ▲ 2.97% USD/VES 917.52 ▼ 0.13% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.09 ▲ 2.61% USD/TTD 6.72 ▲ 2.42% EUR/BRL 6.47 ▼ 0.75% BRENT 88.50 ▼ 0.97% WTI 81.69 ▲ 1.90% IRON ORE 161.91 — — COPPER 5.48 ▼ 2.54% GOLD 3,555 ▼ 2.64% SILVER 40.71 ▼ 5.65% SOY 1,232 ▲ 0.28% CORN 450.25 ▲ 3.68% WHEAT 588.75 ▲ 2.04% COFFEE 260.40 ▼ 5.08% SUGAR 17.70 ▲ 0.51% ORANGE JUICE 131.20 ▼ 2.31% COTTON 82.34 ▲ 6.20% COCOA 5,444 ▲ 4.97% BEEF 229.93 ▲ 2.39% CATTLE 332.95 ▼ 0.41% LITHIUM 53.69 ▼ 1.85% PETR4 40.55 ▼ 1.82% VALE3 55.19 ▼ 5.51% ITUB4 39.74 ▲ 0.03% BBDC4 13.62 ▼ 0.66% ABEV3 16.10 ▲ 1.00% BBAS3 14.18 ▼ 0.14% B3SA3 14.18 ▲ 0.14% WEGE3 50.20 ▲ 0.58% PRIO3 59.60 ▲ 2.37% SUZB3 56.14 ▲ 1.72% RENT3 28.51 ▼ 0.80% AZZA3 14.18 ▼ 2.74% CSAN3 3.23 ▲ 2.87% RAIZ4 13.90 ▼ 7.33% PCAR3 3.27 ▼ 9.17% GMAT3 4.10 ▼ 0.24% PSSA3 41.93 ▼ 2.28% CVCB3 0.69 ▼ 4.17% POSI3 3.14 ▼ 7.10% SLCE3 16.81 ▼ 0.77% NATU3 4.26 ▼ 6.37% BRKM5 2.50 ▼ 14.09% RANI3 7.83 ▲ 0.26%
since 2009
Tuesday, November 24, 2026

Mining Peru

Buenaventura Invests US$36.2 Million to Extend Uchucchacua Mine Life

Peru's Buenaventura plans to keep its silver mine running to June 2029, pending environmental approval.

By · · 6 min read
An underground loader working in a mine tunnel, illustrating Buenaventura's Uchucchacua investment
Uchucchacua produces silver, lead and zinc in the Lima region.

Peru · Mining

Key Facts

  • —What happened Peru’s Buenaventura revived a US$36.22 million plan to extend its Uchucchacua silver, lead and zinc mine in the Lima region.
  • —How big a jump Output climbed from 21% to 45% of permitted levels in two years, with 30 extra months on the line.
  • —The real story A US$12.31 million plant upgrade and US$11.42 million tailings dam investment let Buenaventura recover reserves within its mining limit.
  • —The catch The timeline depends on Peru’s Senace approval, with no decision date set; a delay could push it back.
  • —Who it touches Shareholders tracking Peruvian mining and metals should watch Uchucchacua, a traditional silver producer (US$…).
  • —What comes next If Senace approves, the mine would keep running until June 2029; otherwise, the current schedule applies.

Peru’s Buenaventura plans to keep its silver mine running to June 2029, pending environmental approval.

Free daily brief — no card needed
Get every Mining story in one morning email
We build you a personalized brief around the topics you follow — free for 7 days. Love it? Your first month after that is US$1.

Peru’s Compañía de Minas Buenaventura has revived a US$36.22 million investment plan at its Uchucchacua silver, lead and zinc mine in the Lima region. The goal is to extend the mine’s life by 30 months, to June 2029, if the environmental agency Senace approves the request.

RT
Ask Rio Times
17 years of Latin America reporting, on demand.
Open the full Ask Rio Times →

Why the mine needs more time

Uchucchacua has been mining well below its permitted levels for three straight years. Buenaventura blames equipment availability and limited access to the ore body.

In 2023, the mine produced just 21% of the approved amount. That figure rose to 38% in 2024 and to 45% in 2025.

For 2026, the company plans to extract 730,000 tonnes of mineral. The permit allows 960,000 tonnes for the year.

The LatAm Brief

One email, every weekday morning. What moved in Latin American markets, politics and expat life.

Yesterday’s subject line: “Petrobras plans US$122 billion of investment”

The slower pace means Buenaventura needs extra time to recover all its approved reserves. The investment plan is designed to make that happen without exceeding the maximum mining rate.

What the US$36.2 million buys

The biggest single item is US$12.31 million to modify the concentrator plant. That is the facility that separates silver, lead and zinc from the crushed rock.

Another US$11.42 million will go to raising tailings dam No. 3. A tailings dam is the structure that holds the waste left after the valuable metal is taken out—so enlarging it means more room for the leftover rock.

The rest covers access roads, power systems, ventilation, drilling platforms, and water recirculation. The plan also adds the Alto Huantajalla quarry as a new source of material.

The concentrator’s capacity stays at 6,000 tonnes per day. Buenaventura says it will not exceed the maximum mining rate under its permit.

How the schedule extends

Buenaventura wants to add 30 months to the mine’s operating schedule. If approved, Uchucchacua would keep running until June 2029.

Senace, Peru’s environmental permitting agency, has started evaluating the request. This is the same agency that approves major mining project changes, so its sign-off is the gatekeeper for the timeline.

No resolution date has been announced—the outcome depends on Senace’s technical and environmental review, which can take time.

The extension would let Buenaventura extract its approved reserves without speeding up production beyond current limits. That means a steadier, more predictable operation.

Why Latin American investors should care

Uchucchacua is one of Peru’s traditional silver producers, and this investment shows the company’s commitment to the asset. For anyone living in Peru or tracking the region’s mining sector, this is a clear sign that the silver, lead and zinc trade still has legs.

The lower production levels reflect real operational constraints, not a change in strategy. So this plan is about catching up on lost time, not abandoning the mine.

For shareholders, the US$36.2 million outlay is relatively small compared to the value of the remaining reserves. The key risk is regulatory timing: an approval delay could push the schedule back, so watch Senace’s moves.

Buenaventura’s shares trade on the Lima exchange and as an ADR in New York. This project update matters for anyone tracking Peruvian mining stocks or the broader metals market in Latin America.

The bigger picture for Buenaventura

Buenaventura is one of Peru’s largest precious metals producers, and this move fits into a broader pattern of keeping mature mines alive with targeted investment. The Uchucchacua plan is modest in size but strategically important for maintaining output.

The decision to stay below permit levels suggests a cautious approach to safety and ore recovery. That should support a smoother approval process, but nothing is guaranteed—Senace has the final word.

If the extension is granted, Uchucchacua would operate into mid-2029, giving Buenaventura more time to draw down its approved reserves. That could also smooth out its production profile across the company’s other assets.

For now, the roadmap is clear: spend US$36.22 million, keep the plant at 6,000 tonnes per day, and wait for Senace’s verdict. The clock is ticking but not loudly—no decision date has been set.

Frequently Asked Questions

What is Senace?

Senace is Peru’s environmental permitting agency. It reviews requests for mining project changes like the one Buenaventura filed for Uchucchacua.

Why is the mine running below its permit?

Buenaventura says equipment availability and access to the ore body have limited production. In 2023 it mined 21% of the approved amount, in 2024 38% and in 2025 45%.

When would the mine close?

If Senace approves the extension, Uchucchacua would operate until June 2029. Without approval, the current schedule applies.

What is a tailings dam?

A tailings dam is a structure that holds the waste material left after valuable metals are extracted from ore. Buenaventura will spend US$11.42 million to enlarge dam No. 3 at Uchucchacua.

Sources: bnamericas.com; gestion.pe; mineriaenlinea.com; mineriayproyectos.com; sahmcapital.com

This article was produced by The Rio Times’ automated AI newsroom. Editorial responsibility: Matthias Camenzind, Publisher and Editor-in-Chief. The Rio Times also runs Ask Rio Times, which answers from 100,000+ of our own articles, the daily Latin America Power Map, and prediction-market odds on elections and markets.. How we use AI · Report an error

The Rio Times · Power Map
See who really holds power in Latin America
Click to open the Power Map →

Brazil runoff date: Sunday, October 25, poll closing times and when results start · Brazil runoff polls: Flávio 51%, Lula 49% · Kalshi and Polymarket odds

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.