IBOV 166,376.43 ▼ 0.69% COLCAP 2,452.46 — — IPC MEX 68,629.46 ▼ 0.12% MERVAL 2,848,945 — — USD/BRL5.91▼ 0.70% USD/MXN19.14▲ 0.30% USD/CLP 1,022 — 0.00% USD/COP3,483▲ 3.77% USD/PEN3.45▲ 0.19% USD/ARS1,580▲ 0.93% USD/UYU40.61▲ 3.16% USD/PYG6,212▲ 2.34% USD/BOB11.64▲ 2.55% USD/DOP59.52▼ 0.80% USD/CRC441.73▲ 2.68% USD/GTQ7.64▲ 3.22% USD/HNL26.89▲ 3.31% USD/NIO36.62▼ 0.69% USD/VES913.46▼ 0.45% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD157.59▲ 2.60% USD/TTD6.70▲ 2.00% EUR/BRL6.52▲ 1.12% BRENT 89.95 ▼ 2.21% WTI 83.41 ▲ 0.24% IRON ORE 161.91 — — COPPER 5.49 ▼ 2.49% GOLD 3,515 ▼ 4.62% SILVER 41.07 ▼ 7.33% SOY 1,221 ▲ 1.10% CORN 448.75 ▲ 2.22% WHEAT 592.00 ▲ 2.38% COFFEE 273.35 ▼ 3.08% SUGAR 17.07 ▼ 0.52% ORANGE JUICE 129.25 ▼ 2.49% COTTON 79.30 ▲ 4.41% COCOA 5,150 ▲ 1.72% BEEF 227.70 ▲ 2.18% CATTLE 335.43 ▼ 0.78% LITHIUM 51.98 ▼ 4.33% PETR4 42.67 ▼ 1.16% VALE3 58.48 ▼ 0.88% ITUB4 40.07 ▼ 0.30% BBDC4 13.83 ▼ 1.78% ABEV3 16.08 ▲ 0.06% BBAS3 14.30 ▲ 1.27% B3SA3 14.28 ▼ 0.14% WEGE3 51.13 ▼ 0.49% PRIO3 60.20 ▼ 2.70% SUZB3 55.32 ▼ 0.50% RENT3 28.86 ▼ 2.00% AZZA3 14.63 ▼ 7.29% CSAN3 3.08 ▼ 1.60% RAIZ4 15.00 ▼ 10.71% PCAR3 3.23 ▲ 8.03% GMAT3 4.18 ▲ 3.21% PSSA3 43.96 ▼ 1.57% CVCB3 0.72 ▼ 7.69% POSI3 3.37 ▲ 6.31% SLCE3 17.53 ▼ 1.96% NATU3 4.48 ▼ 6.28% BRKM5 2.60 ▼ 1.14% RANI3 8.01 ▼ 0.74% IBOV 166,376.43 ▼ 0.69% COLCAP 2,452.46 — — IPC MEX 68,629.46 ▼ 0.12% MERVAL 2,848,945 — — USD/BRL 5.91 ▼ 0.70% USD/MXN 19.14 ▲ 0.30% USD/CLP 1,022 — 0.00% USD/COP 3,483 ▲ 3.77% USD/PEN 3.45 ▲ 0.19% USD/ARS 1,580 ▲ 0.93% USD/UYU 40.61 ▲ 3.16% USD/PYG 6,212 ▲ 2.34% USD/BOB 11.64 ▲ 2.55% USD/DOP 59.52 ▼ 0.80% USD/CRC 441.73 ▲ 2.68% USD/GTQ 7.64 ▲ 3.22% USD/HNL 26.89 ▲ 3.31% USD/NIO 36.62 ▼ 0.69% USD/VES 913.46 ▼ 0.45% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.59 ▲ 2.60% USD/TTD 6.70 ▲ 2.00% EUR/BRL 6.52 ▲ 1.12% BRENT 89.95 ▼ 2.21% WTI 83.41 ▲ 0.24% IRON ORE 161.91 — — COPPER 5.49 ▼ 2.49% GOLD 3,515 ▼ 4.62% SILVER 41.07 ▼ 7.33% SOY 1,221 ▲ 1.10% CORN 448.75 ▲ 2.22% WHEAT 592.00 ▲ 2.38% COFFEE 273.35 ▼ 3.08% SUGAR 17.07 ▼ 0.52% ORANGE JUICE 129.25 ▼ 2.49% COTTON 79.30 ▲ 4.41% COCOA 5,150 ▲ 1.72% BEEF 227.70 ▲ 2.18% CATTLE 335.43 ▼ 0.78% LITHIUM 51.98 ▼ 4.33% PETR4 42.67 ▼ 1.16% VALE3 58.48 ▼ 0.88% ITUB4 40.07 ▼ 0.30% BBDC4 13.83 ▼ 1.78% ABEV3 16.08 ▲ 0.06% BBAS3 14.30 ▲ 1.27% B3SA3 14.28 ▼ 0.14% WEGE3 51.13 ▼ 0.49% PRIO3 60.20 ▼ 2.70% SUZB3 55.32 ▼ 0.50% RENT3 28.86 ▼ 2.00% AZZA3 14.63 ▼ 7.29% CSAN3 3.08 ▼ 1.60% RAIZ4 15.00 ▼ 10.71% PCAR3 3.23 ▲ 8.03% GMAT3 4.18 ▲ 3.21% PSSA3 43.96 ▼ 1.57% CVCB3 0.72 ▼ 7.69% POSI3 3.37 ▲ 6.31% SLCE3 17.53 ▼ 1.96% NATU3 4.48 ▼ 6.28% BRKM5 2.60 ▼ 1.14% RANI3 8.01 ▼ 0.74%
since 2009
Saturday, November 21, 2026

Tanzania Africa

Tanzania Gold Mine Nyanzaga Is 88% Complete

Construction is nearly finished and the cost forecast has risen, so the first gold pour in January 2027 is the next checkpoint.

By · · 4 min read
Worker in a hard hat operating a drilling machine underground at a gold mine in Tanzania
File photo. A worker operates a drilling machine underground at the Shanta Gold mine, Tanzania, 2017. Photo: Deo photographer, CC BY-SA 4.0, Wikimedia Commons.

Mining: Tanzania

Perseus Mining, an Australian gold producer, says its Nyanzaga gold mine in Tanzania is 88.4% complete and still on course to pour its first gold, the moment molten metal is first cast into bars, in January 2027. The company reported the progress on 27 October 2026, three weeks before the Tanzania Mining and Investment Conference, a government-organised mining forum, opened in Dar es Salaam.

Key Facts

Free daily brief — no card needed
Get every Africa story in one morning email
We build you a personalized brief around the topics you follow — free for 7 days. Love it? Your first month after that is US$1.
  • Who. Perseus Mining, an Australian gold producer listed on the Australian Securities Exchange.
  • What. Nyanzaga is 88.4% complete; forecast cost is US$553 million to US$563 million against US$523 million budgeted.
  • When. Perseus reported on 27 October 2026; first gold pour is planned for January 2027.
  • As of. 21 November 2026, 19:30 GMT

Construction is nearly finished and the cost forecast has risen, so the first gold pour in January 2027 is the next checkpoint.

Nyanzaga sits in the Sukumaland Greenstone Belt, a gold-bearing rock formation in Tanzania, and Perseus acquired the project in 2024. The company’s project page says Perseus owns 80% of it.

The project page puts the mine’s life at 16 years, including 14 years of production above 200,000 ounces of gold a year. Its ore reserve, the part of the deposit that can be mined profitably, stood at 4.0 million ounces in February 2026, according to the page.

Perseus said in its September 2026 quarterly report that Nyanzaga “remains on budget and on schedule to produce gold in January 2027”. Overall project progress reached 88.4% at the end of September, according to the quarterly report.

The company’s project page put it at 48% on 31 March 2026.

Open-pit gold mine in Tanzania, file photo
File photo. The Geita open-pit gold mine in north-western Tanzania, not Nyanzaga. Photo: Gordon Greenall, CC BY-SA 2.0, Wikimedia Commons.
RT
Ask Rio Times
17 years of Latin America reporting, on demand.
Open the full Ask Rio Times →

Perseus has spent US$407.6 million of the US$483 million approved construction budget, or 84%, and US$443.9 million in total once advance payments are counted. The construction budget is holding, but the total is rising: the investment decision, the final go-ahead in April 2025, set US$523 million, and Perseus now forecasts US$553 million to US$563 million.

Africa Intelligence

One email, every weekday morning. African markets, politics and business — filed from our newsroom in Rio.

Yesterday’s subject line: “South Africa's first woman deputy president dies at 71”

The company announced on 26 August 2026 that the increase comes from pre-production mining costs, revised because it is mining faster than first planned. Pre-stripping, the removal of waste rock to uncover ore, reached 4.6 million bank cubic metres (rock volume measured before blasting) by the end of September, against a target of 7.0 to 7.7 million before the first gold pour.

First ore has now been mined and stockpiled, with 14,822 tonnes at 0.72 grams of gold per tonne moved in the quarter. Perseus says its commissioning team, which brings the plant into service, has mobilised, and ore is expected to go through the primary crusher, the first machine that breaks the rock, to the stockpile in the coming period.

Inside the plant, ring gears and motors, which turn the mills, are installed on both grinding mills, and the leaching tanks, where chemicals dissolve gold from crushed ore, are complete. Line stringing is under way on the 220-kilovolt (high-voltage) grid connection, and all 28 generators of the back-up power station are installed.

The tailings storage facility, which holds the leftover slurry after the gold is extracted, is ahead of schedule, with all three embankments complete. Perseus says construction of the front end of the process plant is nearing completion.

Perseus guides to about 55,000 ounces from Nyanzaga in its financial year ending 30 June 2027, with commercial production planned for April to June 2027. Operating costs are capitalised until then, meaning they are added to the project’s cost instead of being booked as expenses.

Nyanzaga joins a group that produced 92,551 ounces in the first quarter of its financial year, at an all-in site cost, the full cost of mining and processing, of US$2,035 an ounce. Group guidance for the year is 420,000 to 480,000 ounces from its three operating mines plus Nyanzaga.

Perseus held US$900 million in cash and bullion, meaning gold held in bars, on 30 September 2026. Its cost guidance for the three operating mines assumes gold at US$4,000 an ounce.

The seventh Tanzania Mining and Investment Conference runs 19 to 21 November at the Julius Nyerere International Convention Centre in Dar es Salaam. Tanzania’s Ministry of Minerals, the mining ministry, organises it with the Tanzania Chamber of Mines, the industry body.

The timetable is Perseus’s own statement. It has not been independently audited.

The next dated step is the first gold pour that Perseus plans for January 2027. Updated Nyanzaga guidance is due in the January to March 2027 quarter.

Frequently Asked Questions

When will Nyanzaga pour its first gold?

Perseus says the mine is on schedule to produce gold in January 2027. Commercial production is planned for April to June 2027.

Is the Nyanzaga project over budget?

Perseus now forecasts a final cost above the budget it set at the investment decision. It attributes the rise to mining waste rock faster than planned.

Who is behind the Nyanzaga mine?

Perseus Mining develops it and says it owns 80%. Perseus acquired the project in 2024.

Related reading: Nigerian firm eyes US$50m Tanzania gold deal · Tanzania’s state miner plans three new mines · Barrick anchors Tanzania’s mining pitch · Tanzania steps up checks on mining licences

Sources: Perseus Mining September 2026 quarterly report (27 October 2026); Perseus Mining Nyanzaga project page; Tanzania Mining and Investment Conference programme page (organiser: Ministry of Minerals).

The Big Picture

Africa: The New Scramble — why the world’s powers are competing for the continent

This article was produced by The Rio Times’ automated AI newsroom. Editorial responsibility: Matthias Camenzind, Publisher and Editor-in-Chief. The Rio Times also runs Ask Rio Times, which answers from 100,000+ of our own articles, the daily Latin America Power Map, and prediction-market odds on elections and markets.. How we use AI · Report an error

Brazil runoff date: Sunday, October 25, poll closing times and when results start · Brazil runoff polls: Flávio 51%, Lula 49% · Kalshi and Polymarket odds

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.