IBOV 176,573.35 ▼ 0.13% COLCAP 2,452.46 — — IPC MEX 71,657.88 ▲ 1.85% MERVAL 2,848,945 — — USD/BRL 5.56 — — USD/MXN19.63▼ 0.41% USD/CLP 1,030 — 0.00% USD/COP3,473▼ 2.15% USD/PEN3.47▼ 0.09% USD/ARS1,605▲ 0.23% USD/UYU 40.69 — — USD/PYG 6,405 — — USD/BOB 11.80 — — USD/DOP 60.44 — — USD/CRC 440.56 — — USD/GTQ 7.65 — — USD/HNL 26.89 — — USD/NIO 36.62 — — USD/VES924.04▼ 0.13% USD/PAB 1.00 — — USD/BZD 2.00 — — USD/JMD 156.69 — — USD/TTD 6.71 — — EUR/BRL 6.08 — — BRENT 90.84 ▼ 3.98% WTI 83.08 ▼ 0.72% IRON ORE 161.91 — — COPPER 5.60 ▲ 5.03% GOLD 3,669 ▲ 3.75% SILVER 43.70 ▲ 9.11% SOY 1,266 ▲ 1.79% CORN 463.00 ▲ 5.29% WHEAT 591.00 ▲ 4.51% COFFEE 275.55 ▼ 0.04% SUGAR 18.77 ▲ 2.34% ORANGE JUICE 123.35 ▼ 1.52% COTTON 84.69 ▲ 6.33% COCOA 5,499 ▲ 3.72% BEEF 228.13 ▲ 2.15% CATTLE 331.20 ▲ 1.12% LITHIUM 55.27 ▲ 4.56% PETR4 42.14 ▼ 2.43% VALE3 57.19 ▼ 2.62% ITUB4 42.73 ▲ 0.40% BBDC4 16.07 ▲ 1.52% ABEV3 16.26 ▼ 1.03% BBAS3 16.90 ▲ 2.18% B3SA3 17.23 ▲ 6.62% WEGE3 49.87 ▼ 2.90% PRIO3 61.93 ▼ 0.83% SUZB3 51.98 ▼ 5.27% RENT3 34.65 ▲ 2.61% AZZA3 16.47 ▼ 2.77% CSAN3 3.85 ▲ 0.26% RAIZ4 17.03 ▼ 4.59% PCAR3 3.61 ▼ 0.28% GMAT3 4.54 ▲ 5.58% PSSA3 43.65 ▲ 1.37% CVCB3 0.79 ▲ 2.60% POSI3 3.53 ▲ 1.73% SLCE3 16.74 ▼ 2.79% NATU3 4.86 ▼ 6.54% BRKM5 2.03 ▼ 6.45% RANI3 8.18 ▲ 0.49% IBOV 176,573.35 ▼ 0.13% COLCAP 2,452.46 — — IPC MEX 71,657.88 ▲ 1.85% MERVAL 2,848,945 — — USD/BRL 5.56 — — USD/MXN 19.63 ▼ 0.41% USD/CLP 1,030 — 0.00% USD/COP 3,473 ▼ 2.15% USD/PEN 3.47 ▼ 0.09% USD/ARS 1,605 ▲ 0.23% USD/UYU 40.69 — — USD/PYG 6,405 — — USD/BOB 11.80 — — USD/DOP 60.44 — — USD/CRC 440.56 — — USD/GTQ 7.65 — — USD/HNL 26.89 — — USD/NIO 36.62 — — USD/VES 924.04 ▼ 0.13% USD/PAB 1.00 — — USD/BZD 2.00 — — USD/JMD 156.69 — — USD/TTD 6.71 — — EUR/BRL 6.08 — — BRENT 90.84 ▼ 3.98% WTI 83.08 ▼ 0.72% IRON ORE 161.91 — — COPPER 5.60 ▲ 5.03% GOLD 3,669 ▲ 3.75% SILVER 43.70 ▲ 9.11% SOY 1,266 ▲ 1.79% CORN 463.00 ▲ 5.29% WHEAT 591.00 ▲ 4.51% COFFEE 275.55 ▼ 0.04% SUGAR 18.77 ▲ 2.34% ORANGE JUICE 123.35 ▼ 1.52% COTTON 84.69 ▲ 6.33% COCOA 5,499 ▲ 3.72% BEEF 228.13 ▲ 2.15% CATTLE 331.20 ▲ 1.12% LITHIUM 55.27 ▲ 4.56% PETR4 42.14 ▼ 2.43% VALE3 57.19 ▼ 2.62% ITUB4 42.73 ▲ 0.40% BBDC4 16.07 ▲ 1.52% ABEV3 16.26 ▼ 1.03% BBAS3 16.90 ▲ 2.18% B3SA3 17.23 ▲ 6.62% WEGE3 49.87 ▼ 2.90% PRIO3 61.93 ▼ 0.83% SUZB3 51.98 ▼ 5.27% RENT3 34.65 ▲ 2.61% AZZA3 16.47 ▼ 2.77% CSAN3 3.85 ▲ 0.26% RAIZ4 17.03 ▼ 4.59% PCAR3 3.61 ▼ 0.28% GMAT3 4.54 ▲ 5.58% PSSA3 43.65 ▲ 1.37% CVCB3 0.79 ▲ 2.60% POSI3 3.53 ▲ 1.73% SLCE3 16.74 ▼ 2.79% NATU3 4.86 ▼ 6.54% BRKM5 2.03 ▼ 6.45% RANI3 8.18 ▲ 0.49%
since 2009
Saturday, November 28, 2026

Ghana Africa

Ghana Maternity Hospital Stalls 14 Months

A half-built maternity hospital in Ghana's second city has stood idle for more than a year. Its project manager says the reason is simple: the contractor has not been paid.

By · · 6 min read
Accident and Emergency building of Komfo Anokye Teaching Hospital in Kumasi, Ghana
Photo: Samaru Samaru / Wikimedia Commons (CC BY-SA 3.0)

GHANA · HEALTH

Key Facts

  • What is happening As of Wednesday, 14 October, work on the 509-bed Mother and Baby Unit at Komfo Anokye Teaching Hospital in Kumasi has been suspended for about 14 months because the contractor has not been paid.
  • Why it matters A maternity hospital first started in November 2019 sits just over half built, while procured materials deteriorate, some expire and their warranties are put at risk by the long stoppage.
  • The numbers Physical construction stands at about 56% and procurement at about 75%, after the original 850-bed plan was replaced by a 509-bed rebuild; the total cost is not yet confirmed.
  • Who is who Emmanuel Fobi Asabere is the consultant project manager, while Dr Mark Kurt Nawaane chairs Parliament’s Select Committee on Health, the panel that oversees the health sector and visited the site.
  • What to watch Whether the contractor’s payment certificates are settled from government internal funds, as Nawaane promised, and when full-scale construction resumes; no date has been set for either.
  • What it means for you For US investors in Ghana, unpaid contractor bills signal tight public cash flow, and Ghanaian Americans with family in Kumasi should not expect the new maternity beds soon.

A half-built maternity hospital in Ghana’s second city has stood idle for more than a year. Its project manager says the reason is simple: the contractor has not been paid.

Free daily brief — no card needed
Get every Africa story in one morning email
We build you a personalized brief around the topics you follow — free for 7 days. Love it? Your first month after that is US$1.

Work on the KATH Mother and Baby Unit, a 509-bed maternity hospital in Kumasi, Ghana, has been suspended for about 14 months. The consultant project manager, Emmanuel Fobi Asabere, says the stoppage is caused by non-payment to the contractor.

Procured building materials are deteriorating, and some have become defective or expired, putting their warranties at risk. For foreign investors and donors, the idle site shows how unpaid bills can freeze even a priority health project in Ghana.

What the Project Manager Told Lawmakers

Asabere spoke during a visit to the Kumasi site by Parliament’s Select Committee on Health, the cross-party panel overseeing health. MyJoyOnline and Citi Newsroom, two leading Ghanaian news sites, both carried his account on Wednesday, 14 October.

“The suspension is as a result of non-payment to the contractor,” Asabere said. He added that the full stop followed an earlier period of reduced activity, also caused by payment delays.

The contractor, which neither outlet names, has kept the site maintained during the suspension. It is waiting to be paid for work already done before returning to full-scale construction.

Asabere warned that some procured materials have become defective or expired while sitting unused. He said the long inactivity also puts the warranty protections on those materials at risk.

Why KATH Matters

Komfo Anokye Teaching Hospital is a major public teaching hospital in Kumasi, capital of the Ashanti Region and Ghana’s second-largest city. Like Ghana’s other teaching hospitals, it falls under the Ministry of Health, which funds and oversees them.

The new Mother and Baby Unit is meant to add dedicated beds for mothers and newborns at the hospital. For scale, 509 beds is comparable to a large regional hospital in a mid-sized US city.

Multi-storey buildings of Komfo Anokye Teaching Hospital behind a lawn and trimmed hedges under a blue sky
Buildings of Komfo Anokye Teaching Hospital in Kumasi, pictured in 2007. Photo: OER Africa / Wikimedia Commons (CC BY 2.0)

How the KATH Project Was Redesigned

The project began in November 2019 as an effort to complete an existing hospital structure planned for about 850 beds. Assessments after the takeover found serious structural defects in that older building.

Three other firms and the Ghana Institution of Engineers, the national professional body for engineers, reviewed the structure. They concluded that repairing it was not economically advisable.

The project was therefore redesigned as a new 509-bed hospital, which required demolishing the old structure first. That decision reset much of the work and explains part of the long timeline since 2019.

How Far the Work Has Gone

Physical construction stands at about 56%, or just over half, the project manager said. Procurement of materials and equipment is about 75% complete.

Design work is finished, and demolition of the previous structure is fully complete. Asabere said the repeated suspensions have added to the project’s cost, without putting a figure on the increase.

Committee Chair Urges Contractors to Stay

Citi Newsroom also quoted Dr Mark Kurt Nawaane, chairman of the Select Committee on Health, after the visit. “Contractors, don’t give up,” he said, adding that the government will honour outstanding payments.

Nawaane asked contractors to raise their payment certificates for completed work, promising that “something will be done about it.” He said the money would come from “our internal source,” but he gave no amount or date.

What It Means for US Readers

No US company is named as the contractor, and no US funding link appears in the coverage. The case still matters to US holders of Ghanaian bonds, because unpaid contractor bills can signal tight government cash flow.

Ghanaian Americans with relatives in the Ashanti Region should not expect the new maternity capacity soon. Nawaane’s promise of internal funding, if kept, will test whether the government can clear arrears without new borrowing.

What Is Not Known

The contractor’s name, the amount it is owed and the project’s funder are not given in the coverage. The total cost is also unclear, because the two outlets give figures that do not match.

No response from the Ministry of Health or KATH management appears in the coverage. No date has been set for payment or for work to restart.

What Comes Next

The next step is for the contractor to submit payment certificates, as Nawaane urged, and for the government to settle them. Only then can full-scale work resume on the remaining 44% of physical construction.

The committee’s visit does not mean money has been released. It also does not settle who will pay for materials that expired during the suspension.

Frequently Asked Questions

What is the KATH Mother and Baby Unit?

It is a planned 509-bed maternity hospital at Komfo Anokye Teaching Hospital in Kumasi, Ghana. Work began in November 2019 and the building was later redesigned from scratch.

Why has construction stopped?

The consultant project manager says the contractor has not been paid for work already done. The site has been suspended for about 14 months.

How much of the hospital is finished?

Physical construction is about 56% complete and procurement about 75%. Design work and demolition of the old structure are finished.

What did Parliament’s health committee chair say?

Dr Mark Kurt Nawaane urged contractors not to abandon the project and said the government will pay. He gave no amount or date for the payments.

Does the delay affect visitors to Kumasi?

The delay concerns a new building, not the hospital’s existing wards. Visitors and residents should not count on the new maternity capacity opening soon.

RT
Ask Rio Times
17 years of Latin America reporting, on demand.
Open the full Ask Rio Times →

The Big Picture

Africa: The New Scramble — why the world’s powers are competing for the continent

This article was produced by The Rio Times’ automated AI newsroom. Editorial responsibility: Matthias Camenzind, Publisher and Editor-in-Chief. The Rio Times also runs Ask Rio Times, which answers from 100,000+ of our own articles, the daily Latin America Power Map, and prediction-market odds on elections and markets.. How we use AI · Report an error

Brazil runoff date: Sunday, October 25, poll closing times and when results start · Brazil runoff polls: Flávio 51%, Lula 49% · Kalshi and Polymarket odds

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.