IBOV 204,369.83 ▼ 1.22% IPSA 10,984.91 ▼ 0.32% IPC MEX 66,965.15 ▲ 0.33% MERVAL 2,852,826 ▼ 0.57% COLCAP 2,567.07 ▼ 0.13% BVL PERÚ 60,511.74 ▼ 0.96% USD/BRL5.04▲ 0.20% USD/MXN18.50▲ 0.69% USD/CLP986.15▲ 0.37% USD/COP3,196▲ 0.06% USD/PEN3.43▼ 0.01% USD/ARS1,514▲ 0.05% USD/UYU40.20▲ 3.11% USD/PYG5,684▲ 3.29% USD/BOB11.65▲ 1.40% USD/DOP61.11▲ 3.74% USD/CRC449.35▲ 1.80% USD/GTQ7.64▲ 3.11% USD/HNL26.86▲ 3.26% USD/NIO36.62▲ 2.71% USD/VES875.71▼ 0.13% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD 157.28 — 0.00% USD/TTD6.77▲ 2.76% EUR/BRL5.60▲ 0.70% BRENT 88.88 ▼ 0.03% WTI 83.11 ▼ 0.11% IRON ORE 161.91 — — COPPER 6.61 ▲ 0.03% GOLD 4,461 ▲ 1.78% SILVER 65.59 ▲ 1.26% SOY 1,184 ▲ 3.20% CORN 480.50 ▲ 10.02% WHEAT 655.00 ▲ 3.93% COFFEE 317.25 ▼ 5.51% SUGAR 16.43 ▼ 1.79% ORANGE JUICE 138.55 ▼ 0.47% COTTON 85.03 ▲ 2.33% COCOA 5,719 ▲ 3.18% BEEF 223.60 ▼ 3.93% CATTLE 339.10 ▼ 3.16% LITHIUM 75.20 ▲ 1.47% PETR4 41.64 ▼ 0.05% VALE3 72.97 ▲ 0.83% ITUB4 38.60 ▼ 1.03% BBDC4 16.85 ▲ 0.36% ABEV3 14.89 ▼ 0.80% BBAS3 19.37 ▲ 0.47% B3SA3 14.26 ▼ 0.21% WEGE3 47.59 ▲ 0.49% PRIO3 59.14 ▼ 0.19% SUZB3 41.33 ▲ 2.35% RENT3 34.68 ▼ 0.09% AZZA3 15.89 ▼ 2.63% CSAN3 3.22 ▼ 1.83% RAIZ4 0.25 — 0.00% PCAR3 2.75 ▼ 0.36% GMAT3 3.65 ▼ 1.08% PSSA3 48.13 ▼ 0.54% CVCB3 1.33 ▼ 2.92% POSI3 3.36 ▲ 2.44% SLCE3 13.34 ▲ 0.30% NATU3 8.14 ▼ 0.73% IBOV 204,369.83 ▼ 1.22% IPSA 10,984.91 ▼ 0.32% IPC MEX 66,965.15 ▲ 0.33% MERVAL 2,852,826 ▼ 0.57% COLCAP 2,567.07 ▼ 0.13% BVL PERÚ 60,511.74 ▼ 0.96% USD/BRL 5.16 ▲ 0.01% USD/MXN 17.06 ▼ 0.24% USD/CLP 913.98 ▲ 0.04% USD/COP 3,140 ▲ 0.03% USD/PEN 3.36 ▼ 0.66% USD/ARS 1,493 ▲ 0.10% USD/UYU 40.27 ▲ 1.24% USD/PYG 5,939 ▲ 1.68% USD/BOB 11.64 ▼ 0.76% USD/DOP 58.34 ▲ 1.25% USD/CRC 445.92 ▲ 0.89% USD/GTQ 7.62 ▲ 2.21% USD/HNL 26.79 ▲ 1.57% USD/NIO 36.62 ▲ 0.69% USD/VES 762.44 ▼ 0.13% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.28 — 0.00% USD/TTD 6.70 ▲ 0.61% EUR/BRL 5.95 ▲ 1.01% BRENT 88.88 ▼ 0.03% WTI 83.11 ▼ 0.11% IRON ORE 161.91 — — COPPER 6.61 ▲ 0.03% GOLD 4,461 ▲ 1.78% SILVER 65.59 ▲ 1.26% SOY 1,184 ▲ 3.20% CORN 480.50 ▲ 10.02% WHEAT 655.00 ▲ 3.93% COFFEE 317.25 ▼ 5.51% SUGAR 16.43 ▼ 1.79% ORANGE JUICE 138.55 ▼ 0.47% COTTON 85.03 ▲ 2.33% COCOA 5,719 ▲ 3.18% BEEF 223.60 ▼ 3.93% CATTLE 339.10 ▼ 3.16% LITHIUM 75.20 ▲ 1.47% PETR4 41.64 ▼ 0.05% VALE3 72.97 ▲ 0.83% ITUB4 38.60 ▼ 1.03% BBDC4 16.85 ▲ 0.36% ABEV3 14.89 ▼ 0.80% BBAS3 19.37 ▲ 0.47% B3SA3 14.26 ▼ 0.21% WEGE3 47.59 ▲ 0.49% PRIO3 59.14 ▼ 0.19% SUZB3 41.33 ▲ 2.35% RENT3 34.68 ▼ 0.09% AZZA3 15.89 ▼ 2.63% CSAN3 3.22 ▼ 1.83% RAIZ4 0.25 — 0.00% PCAR3 2.75 ▼ 0.36% GMAT3 3.65 ▼ 1.08% PSSA3 48.13 ▼ 0.54% CVCB3 1.33 ▼ 2.92% POSI3 3.36 ▲ 2.44% SLCE3 13.34 ▲ 0.30% NATU3 8.14 ▼ 0.73%
since 2009
Wednesday, October 14, 2026

Ghana Africa

Ghana Maternity Hospital Stalls 14 Months

By · October 14, 2026 · 5 min read
Accident and Emergency building of Komfo Anokye Teaching Hospital in Kumasi with parked cars and people outside at dusk
Photo: Samaru Samaru / Wikimedia Commons (CC BY-SA 3.0)

GHANA · HEALTH

Key Facts

  • —What is happening As of Wednesday, 14 October, work on the 509-bed Mother and Baby Unit at Komfo Anokye Teaching Hospital in Kumasi has been suspended for about 14 months because the contractor has not been paid.
  • —Why it matters A maternity hospital first started in November 2019 sits just over half built, while procured materials deteriorate, some expire and their warranties are put at risk by the long stoppage.
  • —The numbers Physical construction stands at about 56% and procurement at about 75%, after the original 850-bed plan was replaced by a 509-bed rebuild; the total cost is not yet confirmed.
  • —Who is who Emmanuel Fobi Asabere is the consultant project manager, while Dr Mark Kurt Nawaane chairs Parliament’s Select Committee on Health, the panel that oversees the health sector and visited the site.
  • —What to watch Whether the contractor’s payment certificates are settled from government internal funds, as Nawaane promised, and when full-scale construction resumes; no date has been set for either.
  • —What it means for you For US investors in Ghana, unpaid contractor bills signal tight public cash flow, and Ghanaian Americans with family in Kumasi should not expect the new maternity beds soon.

A half-built maternity hospital in Ghana’s second city has stood idle for more than a year. Its project manager says the reason is simple: the contractor has not been paid.

Work on the KATH Mother and Baby Unit, a 509-bed maternity hospital in Kumasi, Ghana, has been suspended for about 14 months. The consultant project manager, Emmanuel Fobi Asabere, says the stoppage is caused by non-payment to the contractor.

Procured building materials are deteriorating, and some have become defective or expired, putting their warranties at risk. For foreign investors and donors, the idle site shows how unpaid bills can freeze even a priority health project in Ghana.

What the Project Manager Told Lawmakers

Asabere spoke during a visit to the Kumasi site by Parliament’s Select Committee on Health, the cross-party panel overseeing health. MyJoyOnline and Citi Newsroom, two leading Ghanaian news sites, both carried his account on Wednesday, 14 October.

“The suspension is as a result of non-payment to the contractor,” Asabere said. He added that the full stop followed an earlier period of reduced activity, also caused by payment delays.

The contractor, which neither outlet names, has kept the site maintained during the suspension. It is waiting to be paid for work already done before returning to full-scale construction.

Asabere warned that some procured materials have become defective or expired while sitting unused. He said the long inactivity also puts the warranty protections on those materials at risk.

Why KATH Matters

Komfo Anokye Teaching Hospital is a major public teaching hospital in Kumasi, capital of the Ashanti Region and Ghana’s second-largest city. Like Ghana’s other teaching hospitals, it falls under the Ministry of Health, which funds and oversees them.

The new Mother and Baby Unit is meant to add dedicated beds for mothers and newborns at the hospital. For scale, 509 beds is comparable to a large regional hospital in a mid-sized US city.

Multi-storey buildings of Komfo Anokye Teaching Hospital behind a lawn and trimmed hedges under a blue sky
Buildings of Komfo Anokye Teaching Hospital in Kumasi, pictured in 2007. Photo: OER Africa / Wikimedia Commons (CC BY 2.0)

How the KATH Project Was Redesigned

The project began in November 2019 as an effort to complete an existing hospital structure planned for about 850 beds. Assessments after the takeover found serious structural defects in that older building.

Three other firms and the Ghana Institution of Engineers, the national professional body for engineers, reviewed the structure. They concluded that repairing it was not economically advisable.

The project was therefore redesigned as a new 509-bed hospital, which required demolishing the old structure first. That decision reset much of the work and explains part of the long timeline since 2019.

How Far the Work Has Gone

Physical construction stands at about 56%, or just over half, the project manager said. Procurement of materials and equipment is about 75% complete.

Design work is finished, and demolition of the previous structure is fully complete. Asabere said the repeated suspensions have added to the project’s cost, without putting a figure on the increase.

Committee Chair Urges Contractors to Stay

Citi Newsroom also quoted Dr Mark Kurt Nawaane, chairman of the Select Committee on Health, after the visit. “Contractors, don’t give up,” he said, adding that the government will honour outstanding payments.

Nawaane asked contractors to raise their payment certificates for completed work, promising that “something will be done about it.” He said the money would come from “our internal source,” but he gave no amount or date.

What It Means for US Readers

No US company is named as the contractor, and no US funding link appears in the coverage. The case still matters to US holders of Ghanaian bonds, because unpaid contractor bills can signal tight government cash flow.

Ghanaian Americans with relatives in the Ashanti Region should not expect the new maternity capacity soon. Nawaane’s promise of internal funding, if kept, will test whether the government can clear arrears without new borrowing.

What Is Not Known

The contractor’s name, the amount it is owed and the project’s funder are not given in the coverage. The total cost is also unclear, because the two outlets give figures that do not match.

No response from the Ministry of Health or KATH management appears in the coverage. No date has been set for payment or for work to restart.

What Comes Next

The next step is for the contractor to submit payment certificates, as Nawaane urged, and for the government to settle them. Only then can full-scale work resume on the remaining 44% of physical construction.

The committee’s visit does not mean money has been released. It also does not settle who will pay for materials that expired during the suspension.

Frequently Asked Questions

What is the KATH Mother and Baby Unit?

It is a planned 509-bed maternity hospital at Komfo Anokye Teaching Hospital in Kumasi, Ghana. Work began in November 2019 and the building was later redesigned from scratch.

Why has construction stopped?

The consultant project manager says the contractor has not been paid for work already done. The site has been suspended for about 14 months.

How much of the hospital is finished?

Physical construction is about 56% complete and procurement about 75%. Design work and demolition of the old structure are finished.

What did Parliament’s health committee chair say?

Dr Mark Kurt Nawaane urged contractors not to abandon the project and said the government will pay. He gave no amount or date for the payments.

Does the delay affect visitors to Kumasi?

The delay concerns a new building, not the hospital’s existing wards. Visitors and residents should not count on the new maternity capacity opening soon.

Sources: MyJoyOnline: Unpaid contractor delays KATH Mother and Baby Unit; Citi Newsroom: KATH Mother and Baby Unit contractor awaits payment; Citi Newsroom: Nawaane to contractors (all accessed 14 October 2026).

RT
Ask Rio Times
17 years of Latin America reporting, on demand.
Open the full Ask Rio Times →

Africa Intelligence

One email, every weekday morning. African markets, politics and business — filed from our newsroom in Rio.

Yesterday’s subject line: “Kenya court lets US$1.6B US health deal proceed”

Free. We send a confirmation link first — nothing arrives until you click it. Unsubscribe with one click in any edition. If you stop opening us for 30 days we stop sending by ourselves, as we assume the interest is no longer there. See our privacy policy. We never share your email.

This article was produced by The Rio Times’ automated newsroom system. How we use AI · Report an error · Editorial responsibility: Matthias Camenzind, Editor-in-Chief

Part of our ongoing coverage

Africa: The New Scramble — the great-power contest over the continent.

More from Western Africa

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.