IBOV 176,573.35 ▼ 0.13% COLCAP 2,452.46 — — IPC MEX 71,657.88 ▲ 1.85% MERVAL 2,848,945 — — USD/BRL 5.56 — — USD/MXN19.64▼ 0.04% USD/CLP1,030▼ 0.09% USD/COP3,473▼ 0.07% USD/PEN3.47▼ 0.06% USD/ARS 1,605 — 0.00% USD/UYU 40.69 — — USD/PYG 6,405 — — USD/BOB 11.80 — — USD/DOP 60.44 — — USD/CRC 440.56 — — USD/GTQ 7.65 — — USD/HNL 26.89 — — USD/NIO 36.62 — 0.00% USD/VES924.04▼ 0.36% USD/PAB 1.00 — — USD/BZD 2.00 — — USD/JMD 156.69 — — USD/TTD 6.71 — — EUR/BRL 6.08 — — BRENT 90.84 ▼ 3.98% WTI 83.08 ▼ 0.72% IRON ORE 161.91 — — COPPER 5.60 ▲ 5.03% GOLD 3,669 ▲ 3.75% SILVER 43.70 ▲ 9.11% SOY 1,266 ▲ 1.79% CORN 463.00 ▲ 5.29% WHEAT 591.00 ▲ 4.51% COFFEE 265.65 ▼ 3.63% SUGAR 18.81 ▲ 2.56% ORANGE JUICE 123.50 ▼ 1.40% COTTON 84.69 ▲ 6.33% COCOA 5,191 ▼ 2.09% BEEF 228.13 ▲ 2.15% CATTLE 331.20 ▲ 1.12% LITHIUM 55.27 ▲ 4.56% PETR4 42.14 — 0.00% VALE3 57.19 — 0.00% ITUB4 42.73 — 0.00% BBDC4 16.07 — 0.00% ABEV3 16.26 — 0.00% BBAS3 16.90 — 0.00% B3SA3 17.23 — 0.00% WEGE3 49.87 — 0.00% PRIO3 61.93 — 0.00% SUZB3 51.98 — 0.00% RENT3 34.65 ▲ 2.61% AZZA3 16.47 — 0.00% CSAN3 3.85 — 0.00% RAIZ4 17.03 ▼ 4.59% PCAR3 3.61 ▼ 0.28% GMAT3 4.54 ▲ 5.58% PSSA3 43.65 ▲ 1.37% CVCB3 0.79 ▲ 2.60% POSI3 3.53 ▲ 1.73% SLCE3 16.74 ▼ 2.79% NATU3 4.86 ▼ 6.54% BRKM5 2.03 — 0.00% RANI3 8.18 ▲ 0.49% IBOV 176,573.35 ▼ 0.13% COLCAP 2,452.46 — — IPC MEX 71,657.88 ▲ 1.85% MERVAL 2,848,945 — — USD/BRL 5.56 — — USD/MXN 19.64 ▼ 0.04% USD/CLP 1,030 ▼ 0.09% USD/COP 3,473 ▼ 0.07% USD/PEN 3.47 ▼ 0.06% USD/ARS 1,605 — 0.00% USD/UYU 40.69 — — USD/PYG 6,405 — — USD/BOB 11.80 — — USD/DOP 60.44 — — USD/CRC 440.56 — — USD/GTQ 7.65 — — USD/HNL 26.89 — — USD/NIO 36.62 — 0.00% USD/VES 924.04 ▼ 0.36% USD/PAB 1.00 — — USD/BZD 2.00 — — USD/JMD 156.69 — — USD/TTD 6.71 — — EUR/BRL 6.08 — — BRENT 90.84 ▼ 3.98% WTI 83.08 ▼ 0.72% IRON ORE 161.91 — — COPPER 5.60 ▲ 5.03% GOLD 3,669 ▲ 3.75% SILVER 43.70 ▲ 9.11% SOY 1,266 ▲ 1.79% CORN 463.00 ▲ 5.29% WHEAT 591.00 ▲ 4.51% COFFEE 265.65 ▼ 3.63% SUGAR 18.81 ▲ 2.56% ORANGE JUICE 123.50 ▼ 1.40% COTTON 84.69 ▲ 6.33% COCOA 5,191 ▼ 2.09% BEEF 228.13 ▲ 2.15% CATTLE 331.20 ▲ 1.12% LITHIUM 55.27 ▲ 4.56% PETR4 42.14 — 0.00% VALE3 57.19 — 0.00% ITUB4 42.73 — 0.00% BBDC4 16.07 — 0.00% ABEV3 16.26 — 0.00% BBAS3 16.90 — 0.00% B3SA3 17.23 — 0.00% WEGE3 49.87 — 0.00% PRIO3 61.93 — 0.00% SUZB3 51.98 — 0.00% RENT3 34.65 ▲ 2.61% AZZA3 16.47 — 0.00% CSAN3 3.85 — 0.00% RAIZ4 17.03 ▼ 4.59% PCAR3 3.61 ▼ 0.28% GMAT3 4.54 ▲ 5.58% PSSA3 43.65 ▲ 1.37% CVCB3 0.79 ▲ 2.60% POSI3 3.53 ▲ 1.73% SLCE3 16.74 ▼ 2.79% NATU3 4.86 ▼ 6.54% BRKM5 2.03 — 0.00% RANI3 8.18 ▲ 0.49%
since 2009
Sunday, November 29, 2026

Business Latin America

Uruguay Data Centre Deal Hits US$5.7 Billion

President Yamandú Orsi signed a US$5.7 billion deal with Spain's Solaria for a solar-powered data centre park, the largest investment in Uruguay's history.

By · · 7 min read
Aerial view of San José de Mayo and surrounding farmland in San José department, Uruguay
Aerial view of San José de Mayo and its farmland; San José department will host the second phase of the data centre park. (Photo: Andrzej Otrębski, CC BY-SA 4.0, via Wikimedia Commons)

BUSINESS · URUGUAY

Uruguay data centre plans took a giant step on Wednesday 14 October, when President Yamandú Orsi signed a US$5.7 billion deal with Spain’s Solaria. The company will build a 500-megawatt park of data centres, powered by its own solar farms, in the departments of Canelones, San José and Florida.

The government calls it the largest investment in the country’s history, placing Uruguay in the regional race for the computing power behind artificial intelligence. For US readers, it adds a large clean-energy computing hub in South America, near Google’s data centre in Canelones.

Key Facts

  • The country Uruguay is a small South American democracy between Argentina and Brazil whose electricity comes almost entirely from renewable sources.
  • Why it matters The government calls it the largest investment in Uruguay’s history, aimed at the global race for data centre capacity.
  • Why now President Yamandú Orsi signed the agreement with Spain’s Solaria on Wednesday 14 October in Montevideo.
  • What happened Solaria will build a 500-megawatt data centre park with 350 megawatts of its own solar power, worth US$5.7 billion in total.
  • The numbers US$5.5 billion for data centres, US$200 million for solar, 3,100 construction jobs by 2029 and 1,500 permanent jobs.
  • What it means for you US cloud and AI firms gain a large, solar-powered site in South America, near Google’s data centre in Canelones.
  • Still open Who will rent the capacity, how the centres will be cooled, and the terms of an agreement that remains confidential.
  • Power Index Uruguay ranks 7th of 14 in The Rio Times Latin America Power Index, with 45.2 points (November 2026 edition).
Free daily brief — no card needed
Get every Business story in one morning email
We build you a personalized brief around the topics you follow — free for 7 days. Love it? Your first month after that is US$1.

What Orsi Announced in the Uruguay Data Centre Deal

Orsi, a centre-left president from the Broad Front coalition who took office in March 2025, made the announcement at the Torre Ejecutiva, the presidential offices. He said the project will run under Uruguay’s free-trade zone regime, which exempts companies from most national taxes.

The presidency said US$5.5 billion will go into the data centres and US$200 million into 350 megawatts of solar generation. That solar capacity is meant to supply the park with its own renewable power, according to the official release.

The project has two phases, the presidency said. The first covers 200 megawatts of data centres and all the solar plants, and the second adds another 300 megawatts of data centres.

Construction should need 3,100 workers in the first stage to 2029, including 2,400 on the data centres and 700 on the solar parks. Once fully running, the park is expected to employ 1,500 people permanently.

Industry Minister Fernanda Cardona said the solar plants will go up in Florida, while the first data centre phase will be in Canelones and the second in San José. She told reporters the first phase should be operating in 2029, or in 2030 at the latest.

Cardona said the new park will be five times larger than Google’s data centre in Canelones, El Observador reported. She added that the US$5.7 billion covers buildings and works only, not the equipment that will go inside.

The minister said the investment exceeds the public and private spending that shifted Uruguay’s power grid to renewables between 2010 and 2015. Orsi called the deal a signal that Uruguay is a country where the rules are clear and respected.

Glass lobby looking onto the grounds of Parque de las Ciencias, a business park in Canelones, Uruguay
Parque de las Ciencias, a free-trade zone business park in Canelones, photographed in 2011; Canelones will host the first phase of the Solaria data centres. (Photo: Andrés Franchi Ugart…, CC BY-SA 3.0, via Wikimedia Commons)
RT
Ask Rio Times
Latin American markets, currencies and companies.
Open the full Ask Rio Times →

How the Solaria Deal Came Together

Solaria Energía y Medio Ambiente, founded in 2002, is a Spanish solar power producer listed in Madrid since 2007 and part of the IBEX 35 index since 2020. It has run solar plants in Young and Mercedes, in western Uruguay, for almost a decade, selling power to the state utility UTE.

According to El Observador, the government first heard of Solaria’s interest in late February 2026, during a trip to Madrid by Presidency Secretary Alejandro Sánchez. Orsi then asked for the talks to stay confidential to avoid leaks, the newspaper reported, citing official sources.

Cardona travelled to Spain in June, and Solaria chief executive Arturo Díaz-Tejeiro visited Uruguay a month later for meetings with ministers, UTE and the state telecom firm Antel. In September a team of UTE managers went to Solaria’s headquarters in Spain to close the deal, the paper said.

The minister said the talks were closed in less than five months. The government says the project will not need extra public works, unlike earlier megaprojects such as the Finnish company UPM’s pulp mill, El Observador reported.

Not everyone was consulted, however. Darío Castiglioni, who represents the centre-right National Party, the largest opposition party, on UTE’s board, said he had not been told about the project and criticised a lack of transparency.

What It Means for You

For US technology companies, the park adds a large block of solar-powered computing capacity in a country that sells itself on stable rules. Orsi also pointed to fibre-optic coverage of 94% and submarine cables that connect Uruguay with the rest of the world.

The deal shows how the hunt for clean power for artificial intelligence is reaching smaller South American countries. Sánchez has said Uruguay competes for such projects with Paraguay, Chile and Brazil, according to El Observador.

Inside Uruguay, Orsi said the gains will go to workers, technicians, engineers and service companies, with growth reaching the interior. Cardona said the state utility UTE also wins, and officials told El Observador that UTE will supply power to the park only in emergencies.

The risks are timing and cost, since Cardona said both state teams and private firms must stick methodically to the schedule. Solaria’s own review found power in Uruguay can cost more than elsewhere in the region, the paper reported, but stability tipped the balance.

For background, read Uruguay Explained: The Country, Its Stability, Its Economy and What to Watch and Uruguay Economy 2026, Who Runs It and How. Antel’s smaller project is covered in Uruguay Bets on Green Power to Win an AI Data Centre, and our Montevideo city page covers life in the capital.

What Is Not Known

The agreement between Orsi and Díaz-Tejeiro is confidential, so its full terms, including any tax or power commitments, have not been published. The government has not said which companies will rent space in the data centres.

Officials have not said how the centres will be cooled or how much water they will use. Cardona said the energy infrastructure for the second phase will be defined later, and that phase will start under the next government.

Cardona also said the second phase could roughly double the investment figure, but no official number has been released. Until the contract is public, the US$5.7 billion total and the job estimates rest on the government’s own figures.

Frequently Asked Questions

What did Uruguay announce on 14 October?

President Yamandú Orsi signed a deal with Spain’s Solaria for a 500-megawatt data centre park with its own solar power. The government puts the investment at US$5.7 billion, the largest in Uruguay’s history.

Where will the Uruguay data centre park be built?

The first phase of data centres will be in Canelones and the second in San José, while the solar plants will be in Florida. The project will run under Uruguay’s free-trade zone regime, the government said.

How many jobs will the project create?

The government expects 3,100 construction jobs in the first stage to 2029, with 2,400 on data centres and 700 on solar parks. Once fully running, the park should employ 1,500 people permanently.

Who is Solaria?

Solaria Energía y Medio Ambiente is a Spanish solar power producer founded in 2002 and listed on the Madrid stock exchange since 2007. It already runs solar plants in Young and Mercedes that sell power to Uruguay’s state utility UTE.

Why does the deal matter to US readers?

It creates a large, clean-powered computing hub in South America, near Google’s data centre in Canelones. The tenants have not been named, but parks of this kind usually serve cloud and AI companies.

Sources

This article was produced by The Rio Times’ automated AI newsroom. Editorial responsibility: Matthias Camenzind, Publisher and Editor-in-Chief. The Rio Times also runs Ask Rio Times, which answers from 100,000+ of our own articles, the daily Latin America Power Map, and prediction-market odds on elections and markets.. How we use AI · Report an error

The Rio Times · Power Map
See who really holds power in Latin America
Click to open the Power Map →

Brazil runoff date: Sunday, October 25, poll closing times and when results start · Brazil runoff polls: Flávio 51%, Lula 49% · Kalshi and Polymarket odds

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.