IBOV 164,089.81 ▼ 0.43% COLCAP 2,452.46 — — IPC MEX 69,301.41 ▼ 0.08% MERVAL 2,848,945 — — USD/BRL5.89▼ 0.23% USD/MXN19.59▲ 0.91% USD/CLP1,033▲ 1.62% USD/COP3,605▲ 2.30% USD/PEN3.47▲ 0.51% USD/ARS1,592▲ 0.76% USD/UYU40.72▲ 3.78% USD/PYG6,399▲ 3.19% USD/BOB11.72▲ 2.95% USD/DOP59.74▲ 0.32% USD/CRC440.90▲ 1.83% USD/GTQ7.64▲ 3.32% USD/HNL26.89▼ 0.07% USD/NIO36.62▲ 0.34% USD/VES920.26▼ 0.13% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD157.09▲ 2.40% USD/TTD6.72▲ 2.28% EUR/BRL6.46▼ 0.01% BRENT 88.31 ▼ 3.38% WTI 81.61 ▼ 0.54% IRON ORE 161.91 — — COPPER 5.41 ▲ 0.85% GOLD 3,559 ▼ 0.08% SILVER 40.52 ▼ 0.59% SOY 1,222 ▼ 0.95% CORN 448.50 ▲ 3.34% WHEAT 583.75 ▲ 2.46% COFFEE 267.60 ▼ 2.46% SUGAR 17.81 ▲ 0.85% ORANGE JUICE 131.20 ▼ 2.31% COTTON 81.44 ▲ 2.93% COCOA 5,191 ▲ 0.10% BEEF 226.03 ▲ 0.66% CATTLE 332.95 ▼ 0.41% LITHIUM 53.69 ▼ 1.85% PETR4 40.55 ▼ 1.82% VALE3 55.19 ▼ 5.51% ITUB4 39.74 ▲ 0.03% BBDC4 13.62 ▼ 0.66% ABEV3 16.10 ▲ 1.00% BBAS3 14.18 ▼ 0.14% B3SA3 14.18 ▲ 0.14% WEGE3 50.20 ▲ 0.58% PRIO3 59.60 ▲ 2.37% SUZB3 56.14 ▲ 1.72% RENT3 28.51 ▼ 0.80% AZZA3 14.18 ▼ 2.74% CSAN3 3.23 ▲ 2.87% RAIZ4 14.11 ▲ 1.51% PCAR3 3.27 ▼ 9.17% GMAT3 4.10 ▼ 0.24% PSSA3 41.93 ▼ 2.28% CVCB3 0.69 ▼ 4.17% POSI3 3.14 ▼ 7.10% SLCE3 16.81 ▼ 0.77% NATU3 4.26 ▼ 6.37% BRKM5 2.50 ▼ 14.09% RANI3 7.83 ▲ 0.26% IBOV 164,089.81 ▼ 0.43% COLCAP 2,452.46 — — IPC MEX 69,301.41 ▼ 0.08% MERVAL 2,848,945 — — USD/BRL 5.89 ▼ 0.23% USD/MXN 19.60 ▲ 0.97% USD/CLP 1,033 ▲ 1.62% USD/COP 3,605 ▲ 2.30% USD/PEN 3.47 ▲ 0.51% USD/ARS 1,592 ▼ 0.03% USD/UYU 40.72 ▲ 3.56% USD/PYG 6,399 ▲ 3.19% USD/BOB 11.72 ▲ 2.95% USD/DOP 59.74 ▲ 0.32% USD/CRC 440.90 ▲ 1.83% USD/GTQ 7.64 ▲ 3.32% USD/HNL 26.89 ▼ 0.07% USD/NIO 36.62 ▲ 0.34% USD/VES 920.26 ▼ 0.13% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.09 ▲ 2.40% USD/TTD 6.72 ▲ 2.28% EUR/BRL 6.46 ▼ 0.03% BRENT 88.31 ▼ 3.38% WTI 81.61 ▼ 0.54% IRON ORE 161.91 — — COPPER 5.41 ▲ 0.85% GOLD 3,559 ▼ 0.08% SILVER 40.52 ▼ 0.59% SOY 1,222 ▼ 0.95% CORN 448.50 ▲ 3.34% WHEAT 583.75 ▲ 2.46% COFFEE 267.60 ▼ 2.46% SUGAR 17.81 ▲ 0.85% ORANGE JUICE 131.20 ▼ 2.31% COTTON 81.44 ▲ 2.93% COCOA 5,191 ▲ 0.10% BEEF 226.03 ▲ 0.66% CATTLE 332.95 ▼ 0.41% LITHIUM 53.69 ▼ 1.85% PETR4 40.55 ▼ 1.82% VALE3 55.19 ▼ 5.51% ITUB4 39.74 ▲ 0.03% BBDC4 13.62 ▼ 0.66% ABEV3 16.10 ▲ 1.00% BBAS3 14.18 ▼ 0.14% B3SA3 14.18 ▲ 0.14% WEGE3 50.20 ▲ 0.58% PRIO3 59.60 ▲ 2.37% SUZB3 56.14 ▲ 1.72% RENT3 28.51 ▼ 0.80% AZZA3 14.18 ▼ 2.74% CSAN3 3.23 ▲ 2.87% RAIZ4 14.11 ▲ 1.51% PCAR3 3.27 ▼ 9.17% GMAT3 4.10 ▼ 0.24% PSSA3 41.93 ▼ 2.28% CVCB3 0.69 ▼ 4.17% POSI3 3.14 ▼ 7.10% SLCE3 16.81 ▼ 0.77% NATU3 4.26 ▼ 6.37% BRKM5 2.50 ▼ 14.09% RANI3 7.83 ▲ 0.26%
since 2009
Wednesday, November 25, 2026

South Africa Africa

Durban Port Backlog to Last Into January

Transnet says Durban's container jam will not clear before the new year. A full fix of the terminal could take about three more years.

By · · 4 min read
Container ship at a terminal in the Port of Durban, South Africa
File photo. Pier 2 of the container terminal at the Port of Durban, South Africa. Photo: Pechristener, CC BY-SA 3.0, Wikimedia Commons.

Port Crisis

Transnet, South Africa’s state-owned ports and rail group, says the container jam at Durban Gateway Terminal (DGT) will last into January 2027. Solly Letsoalo, Transnet’s group chief operating officer, said in an interview on Monday 23 November 2026 that the current plan “won’t take us out of the backlog in December.”

He added that full recovery of the terminal could take about three more years once the backlog clears. That matters to anyone who ships goods through Durban, from medicine importers to fruit exporters and retailers stocking for Christmas.

Free daily brief — no card needed
Get every Africa story in one morning email
We build you a personalized brief around the topics you follow — free for 7 days. Love it? Your first month after that is US$1.

Key Facts

  • Who. Transnet, South Africa’s state ports and rail group, and ICTSI, a Philippines-based terminal operator.
  • What. Congestion at Durban Gateway Terminal lasts into January; full recovery could take about three years.
  • Where. Durban Gateway Terminal, a container terminal at the Port of Durban.
  • When. Letsoalo spoke on Monday 23 November 2026; Transnet announced its measures on 18 November.
  • As of. 25 November 2026, 09:30 GMT.

Transnet says Durban’s container jam will not clear before the new year. A full fix of the terminal could take about three more years.

International Container Terminal Services (ICTSI), a Philippines-based port operator, has run DGT since January 2026 under a 25-year concession in which ICTSI holds 49% and Transnet 51%. Letsoalo said an operating-system failure at DGT in August coincided with the peak of the citrus export season, and “that backlog has never been recovered.”

Transnet said in a statement issued on Wednesday 18 November 2026 that it had dedicated Berth 102, a berth at the Port of Durban, to ships carrying their own cranes. It also supported diverting vessels to the Ngqura Container Terminal, a second port terminal near Gqeberha.

The same statement said the sixth and last refurbished ship-to-shore crane, the giant crane that lifts boxes off ships, would be commissioned on Friday 20 November 2026 and handed to operations the next day. It also said Transnet Freight Rail, the group’s rail arm, had made trains available to carry import containers to Gauteng, the province around Johannesburg, and that pharmaceuticals and auto parts would be prioritised before vessels berth.

Letsoalo put the size of the problem at roughly 10 or 11 vessels a day that cannot berth when they arrive. He said clearing the extra retail backlog would take about two months, and that no auto-industry containers were waiting as of Monday.

On medicine, Transnet said 18 of the 41 containers identified by the health department as urgent had been cleared and delivered, with seven more due in the coming days. Letsoalo said no ship carrying urgently required pharmaceutical products was stuck or waiting, and that the ships still due had left India and Rotterdam.

Transport Minister Barbara Creecy said on Wednesday 18 November 2026: “I’m not going to stop until this gets resolved.” Transnet’s 18 November statement names pharmaceuticals and auto parts as the cargo it is prioritising.

Why Full Recovery Takes Years

The three-year estimate rests on equipment. Letsoalo said ICTSI is bringing in new ship-to-shore cranes and must resurface the terminal yard so that rubber-tyred gantry cranes, which run on wheels, can be used.

He said the first phase, using new equipment, would be finished in about a year and a half. Until then the terminal uses new and second-hand machines of the current, less efficient design.

Calm water in Durban harbour with waterfront apartment towers and port cranes in the distance
The harbour and waterfront of Durban, South Africa. (File photo, undated, RishHans, CC0, Wikimedia Commons)

Importers and Growers Pay the Price

Industry voices are less patient. The Southern African Association of Freight Forwarders (SAAFF), which represents the freight-forwarding industry, reported on 16 November 2026 that waterside volumes were down 19%, with 13 to 14 vessels waiting at anchorage.

Boitshoko Ntshabele, chief executive of the Citrus Growers’ Association of Southern Africa, called the 2026 season unprofitable. Growers packed 201 million 15kg cartons for export this season, 1.5% fewer than in 2025.

Letsoalo said no relief is expected before January. He expects the backlog to fall then because the festive-season peak will have passed.

Frequently Asked Questions

When will Durban port be back to normal?

Letsoalo says the backlog should start to fall in January. Full recovery of the terminal could take about three more years once the backlog clears.

Why is the recovery so slow?

The operator must bring in new cranes and resurface the terminal yard for different machines. Until then it works with older, less efficient equipment.

Are medicines still stuck?

Transnet says it is clearing the health department’s urgent list first. It says 18 of the 41 urgent containers had been cleared and seven more were due in the coming days.

Sources

Transnet group chief operating officer Solly Letsoalo, 23 November 2026; Transnet and Durban Gateway Terminal statement on decongestion measures, 18 November 2026; Department of Transport, Minister Barbara Creecy, 18 November 2026; Southern African Association of Freight Forwarders, cargo movement update, 16 November 2026; Citrus Growers’ Association of Southern Africa, November 2026

Connected Coverage

South Africa news · Durban Port Clears 18 of 41 Medicine Loads

The Big Picture

Africa: The New Scramble — why the world’s powers are competing for the continent

This article was produced by The Rio Times’ automated AI newsroom. Editorial responsibility: Matthias Camenzind, Publisher and Editor-in-Chief. The Rio Times also runs Ask Rio Times, which answers from 100,000+ of our own articles, the daily Latin America Power Map, and prediction-market odds on elections and markets.. How we use AI · Report an error

Living in or visiting Durban? See this month's events and our Durban city guide with rents, safety and upcoming concerts.

RT
Ask Rio Times
Latin American markets, currencies and companies.
Open the full Ask Rio Times →

Africa Intelligence

One email, every weekday morning. African markets, politics and business — filed from our newsroom in Rio.

Yesterday’s subject line: “US to send Kenya health aid over Democratic holds”

Brazil runoff date: Sunday, October 25, poll closing times and when results start · Brazil runoff polls: Flávio 51%, Lula 49% · Kalshi and Polymarket odds

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.