IBOV 176,799.84 ▲ 6.07% COLCAP 2,452.46 — — IPC MEX 70,563.45 ▼ 1.13% MERVAL 2,848,945 — — USD/BRL5.65▼ 2.92% USD/MXN19.63▲ 0.18% USD/CLP1,036▼ 0.33% USD/COP3,547▼ 2.03% USD/PEN3.47▼ 0.21% USD/ARS1,601▼ 0.12% USD/UYU40.70▲ 3.71% USD/PYG6,399▲ 2.73% USD/BOB11.78▲ 3.30% USD/DOP59.52▲ 1.67% USD/CRC441.10▲ 2.54% USD/GTQ7.65▲ 3.39% USD/HNL26.89▲ 3.34% USD/NIO36.62▲ 2.83% USD/VES922.04▼ 0.13% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD157.39▲ 2.56% USD/TTD6.73▲ 2.52% EUR/BRL6.20▼ 4.07% BRENT 92.27 ▼ 2.47% WTI 85.69 ▲ 2.40% IRON ORE 161.91 — — COPPER 5.62 ▲ 5.42% GOLD 3,643 ▲ 3.03% SILVER 43.31 ▲ 8.12% SOY 1,243 ▲ 0.75% CORN 439.50 ▲ 1.27% WHEAT 564.00 ▼ 1.01% COFFEE 265.65 ▼ 1.08% SUGAR 18.42 ▲ 4.30% ORANGE JUICE 125.40 ▼ 4.57% COTTON 81.97 ▲ 3.60% COCOA 5,191 ▼ 1.70% BEEF 223.58 ▼ 1.03% CATTLE 327.43 ▼ 1.64% LITHIUM 52.86 ▼ 1.55% PETR4 43.19 ▲ 4.42% VALE3 58.73 ▲ 3.22% ITUB4 42.56 ▲ 6.37% BBDC4 15.83 ▲ 11.56% ABEV3 16.43 ▲ 3.92% BBAS3 16.54 ▲ 12.59% B3SA3 16.16 ▲ 10.84% WEGE3 51.36 ▲ 3.44% PRIO3 62.45 ▲ 3.22% SUZB3 54.87 ▼ 0.96% RENT3 33.77 ▲ 15.18% AZZA3 16.94 ▲ 10.50% CSAN3 3.84 ▲ 12.28% RAIZ4 16.54 ▲ 17.22% PCAR3 3.62 ▲ 2.84% GMAT3 4.30 ▲ 3.12% PSSA3 43.06 ▲ 2.82% CVCB3 0.77 ▲ 5.48% POSI3 3.47 ▲ 6.77% SLCE3 17.22 ▲ 2.62% NATU3 5.20 ▲ 10.40% BRKM5 2.17 ▼ 3.13% RANI3 8.14 ▲ 2.13% IBOV 176,799.84 ▲ 6.07% COLCAP 2,452.46 — — IPC MEX 70,563.45 ▼ 1.13% MERVAL 2,848,945 — — USD/BRL 5.65 ▼ 2.92% USD/MXN 19.63 ▲ 0.16% USD/CLP 1,036 ▼ 0.33% USD/COP 3,547 ▼ 2.03% USD/PEN 3.46 ▼ 0.27% USD/ARS 1,601 ▼ 0.12% USD/UYU 40.70 ▲ 3.71% USD/PYG 6,399 ▲ 2.73% USD/BOB 11.78 ▲ 3.30% USD/DOP 59.52 ▲ 1.67% USD/CRC 441.10 ▲ 2.54% USD/GTQ 7.65 ▲ 3.39% USD/HNL 26.89 ▲ 3.34% USD/NIO 36.62 ▲ 2.83% USD/VES 922.04 ▼ 0.13% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.39 ▲ 2.56% USD/TTD 6.73 ▲ 2.52% EUR/BRL 6.20 ▼ 4.07% BRENT 92.27 ▼ 2.47% WTI 85.69 ▲ 2.40% IRON ORE 161.91 — — COPPER 5.62 ▲ 5.42% GOLD 3,643 ▲ 3.03% SILVER 43.31 ▲ 8.12% SOY 1,243 ▲ 0.75% CORN 439.50 ▲ 1.27% WHEAT 564.00 ▼ 1.01% COFFEE 265.65 ▼ 1.08% SUGAR 18.42 ▲ 4.30% ORANGE JUICE 125.40 ▼ 4.57% COTTON 81.97 ▲ 3.60% COCOA 5,191 ▼ 1.70% BEEF 223.58 ▼ 1.03% CATTLE 327.43 ▼ 1.64% LITHIUM 52.86 ▼ 1.55% PETR4 43.19 ▲ 4.42% VALE3 58.73 ▲ 3.22% ITUB4 42.56 ▲ 6.37% BBDC4 15.83 ▲ 11.56% ABEV3 16.43 ▲ 3.92% BBAS3 16.54 ▲ 12.59% B3SA3 16.16 ▲ 10.84% WEGE3 51.36 ▲ 3.44% PRIO3 62.45 ▲ 3.22% SUZB3 54.87 ▼ 0.96% RENT3 33.77 ▲ 15.18% AZZA3 16.94 ▲ 10.50% CSAN3 3.84 ▲ 12.28% RAIZ4 16.54 ▲ 17.22% PCAR3 3.62 ▲ 2.84% GMAT3 4.30 ▲ 3.12% PSSA3 43.06 ▲ 2.82% CVCB3 0.77 ▲ 5.48% POSI3 3.47 ▲ 6.77% SLCE3 17.22 ▲ 2.62% NATU3 5.20 ▲ 10.40% BRKM5 2.17 ▼ 3.13% RANI3 8.14 ▲ 2.13%
since 2009
Friday, November 27, 2026

Mexico Business

Sonora River Cleanup Begins 12 Years On

Mexico’s federal government has started removing contaminated soil, yet river communities say the drinking-water side of the plan falls short.

By · · 4 min read
Open-pit copper mine and processing ponds at Cananea, Sonora
The mining area at Cananea, Sonora, photographed on 20 August 2013 (Gildardo Quijada, CC BY-SA 3.0, via Wikimedia Commons).

MEXICO · COMPANIES

Twelve years after a copper mine spilled acidic waste into the Sonora River in northern Mexico, a government-led soil cleanup is under way. Local river committees say the plan provides too few drinking-water plants.

The spill came from a mine of Grupo México, the Mexican mining and rail group, on 6 August 2014. The soil cleanup began on Thursday 15 October 2026.

Free daily brief — no card needed
Get every Mexico story in one morning email
We build you a personalized brief around the topics you follow — free for 7 days. Love it? Your first month after that is US$1.

Key Facts

  • The spill 40,000 cubic metres of acidic copper waste escaped a Grupo México mine in 2014.
  • The cleanup Soil removal began on 15 October 2026; main works are due to end in early January.
  • The dispute Local committees say the drinking-water side of the plan falls short.
  • Power Index Mexico ranks 2nd of 14 in The Rio Times Latin America Power Index, with 70.8 points (November 2026 edition).
  • As of 27 November 2026, 02:30 GMT

Mexico’s federal government has started removing contaminated soil, yet river communities say the drinking-water side of the plan falls short.

RT
Ask Rio Times
Latin American markets, currencies and companies.
Open the full Ask Rio Times →

On Wednesday 6 August 2014, a leach-solution system at the Buenavista del Cobre copper mine in Cananea, a mining town in Sonora, failed. About 40,000 cubic metres of acidified copper sulphate flowed down the Tinajas stream into the Bacanuchi and Sonora rivers, according to official estimates.

Official estimates count more than 22,000 people affected along the rivers. In February 2026 Semarnat, Mexico’s environment ministry, began sampling metals along 402 kilometres of the river to assess the historic contamination.

The LatAm Brief

One email, every weekday morning. What moved in Latin American markets, politics and expat life.

Yesterday’s subject line: “Washington aims at Brazil’s jets. Mexico waits”

Grupo México set up the Río Sonora Trust with federal authorities to pay for the cleanup and for victims. The trust was to hold MX$2 billion (about US$102 million at today’s rate), and a 2017 agreement ended it.

In January 2020 the Supreme Court’s Second Chamber sided with the communities against that closure in amparo review 640/2019, a constitutional-rights appeal. The case reopened the question of who must finish the cleanup.

In December 2025 the interior ministry, Gobernación, announced a MX$2,222.6 million (about US$113 million) Justice Plan for Cananea and the Sonora River. Grupo México pays 70.14%, the federal government 21.7% and the Sonora government 8%, and the package also ended a strike at the Cananea mine that had lasted 18 years.

Footbridge at Ures, Sonora
A footbridge at Ures, Sonora, where the cleanup began (photo: Comisión Mexicana de Filmaciones, CC BY-SA 2.0, via Wikimedia Commons).

Soil work began on 15 October in Ures, a town on the river, with the contractors Veolia, a French environmental-services company, and two others, Semsa and Taesa. They aim to treat about 100,000 tonnes of contaminated earth, with 800 samples taken along 288 kilometres, with MX$654 million (about US$33 million) announced in August for the second stage of the remediation.

The main works are planned to last 87 days from 15 October, which points to early January 2027. Soil tests will decide whether more work is needed after that.

The Sonora River Basin Committees, a grassroots group of river communities, say the drinking-water plants promised after the spill have not been delivered. They also say they have not seen the text of the company’s agreement with the government.

The cleanup is a test of whether the 2025 agreement delivers on the ground. Semarnat has not said what happens if tests show more contaminated soil after the main works end.

For US readers, Grupo México also controls Southern Copper, a copper producer listed in New York. The cleanup bill and any new legal action therefore matter to investors in both.

Frequently Asked Questions

What Happened at the Sonora River in 2014?

A system holding acidic copper solution at a Grupo México mine failed and sent waste down the river. Thousands of residents were affected.

Who Pays for the Current Plan?

Under the December 2025 Justice Plan, the company pays most of the cost. The federal and Sonora governments cover the rest.

Sources: Semarnat data on the Sonora River spill, 2014 to 2026; Supreme Court of Mexico, Segunda Sala, amparo en revisión 640/2019, January 2020; Secretaría de Gobernación, Plan Integral de Justicia for Cananea and the Sonora River, December 2025; Semarnat, announcement of the remediation programme, 15 October 2026; Sonora River Basin Committees, statements of 2026; Southern Copper Corporation, annual report (Form 10-K) for 2025; RT market-data close for USD/MXN (19.63 pesos per US dollar), 27 November 2026.

This article was produced by The Rio Times’ automated AI newsroom. Editorial responsibility: Matthias Camenzind, Publisher and Editor-in-Chief. The Rio Times also runs Ask Rio Times, which answers from 100,000+ of our own articles, the daily Latin America Power Map, and prediction-market odds on elections and markets.. How we use AI · Report an error

The Rio Times · Power Map
See who really holds power in Latin America
Click to open the Power Map →

Brazil runoff date: Sunday, October 25, poll closing times and when results start · Brazil runoff polls: Flávio 51%, Lula 49% · Kalshi and Polymarket odds

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.