SOUTH AFRICA · MINING
As of Tuesday 3 November 2026, South Africa has set no penalty for the Samancor tailings dam collapse of 13 August. The mine’s dam remains shut to new deposits, and a state mine-safety inquiry, expected to take three months, is still open.
Key Facts
- What is happening A tailings dam at Samancor’s Dikwena chrome mine near Brits failed on 13 August; the state inquiry continues.
- Why it matters Regulators cite seepage and drainage work left undone; penalties are weighed only after the inquiry.
- The numbers No casualties; 30 days to file a clean-up plan; 14 days of daily water tests; six months of groundwater checks.
- Who is who Samancor Chrome owns the mine; the mineral department polices mines, and the water department polices dams.
- What to watch The mine-safety inquiry, planned for three months, has no published end date; groundwater tests run monthly.
- What it means for you No lost chrome output is published, so no price effect is confirmed for US stainless-steel buyers.
What Happened at the Dikwena Tailings Dam
The northern wall of Compartment 1B of the Inyoni tailings storage facility failed at about 5:30 p.m. on Thursday 13 August 2026. The facility belongs to the Dikwena chrome mine of Samancor Chrome, a South African chromium producer, near Brits in North West province.
Tailings are the crushed rock and water left after ore is processed, stored behind a dam wall. Slimes are the finest, muddiest part of that waste.
The Department of Water and Sanitation (DWS), which regulates dam safety, said almost all the tailings stored in the compartment escaped. It said no casualties were reported.
The slurry damaged mine infrastructure, a railway line and power lines of Eskom, the state power utility, and polluted a river tributary. A railway embankment and berms at the neighbouring Eland Mine stopped it reaching the R566 provincial road.
What Regulators Say Caused the Failure
The mine-safety regulator, the Department of Mineral and Petroleum Resources (DMPR), told Parliament on 23 October that persistent seepage caused the failure. Seepage is water slowly leaking through a dam wall.
It also cited weak monitoring and early-warning measures for a wall failure. A structural-integrity report had urged urgent engineering work, including a continuous drainage system, and it was not carried out.
A departmental memo of 8 September says seepage appeared in a technical report from 2023 and an engineer’s report of July 2026. It says Samancor did not report it, although seepage is a reportable dangerous occurrence under mine-safety regulations.
The memo also says the dam was not registered with the water department, as a notice of 29 November 2024 required. Its approval lines for the director-general and minister were blank, and the 23 October reply does not repeat that finding.
What Samancor Has Been Ordered to Do
The DMPR issued a Section 54 instruction under the Mine Health and Safety Act, a power to halt work that endangers safety. It ordered workers moved to safety and all deposits into Dikwena’s tailings dams stopped.
A Section 31L notice under the National Environmental Management Act orders Samancor to assess the environmental impact of its tailings facilities. It must also set out the measures needed.
Samancor must file a plan within 30 days of the notice to remove and dispose of the spilled tailings. It must also appoint an independent expert team for a forensic and environmental investigation.
Deposits may restart only after required measures are in place and the Principal Inspector of Mines accepts a presentation. The department is still assessing the risk in the remaining compartments, its 23 October reply says.
The memo says penalties or prosecution will be considered only after the inquiry under Section 60 of the Act concludes. An inspector of mines leads it, and it takes three months if no problems arise.
Water Tests, Clean-Up and Costs
Water samples were taken upstream and downstream of the affected watercourse, and an independent accredited laboratory was appointed. Daily surface-water sampling was scheduled for 14 consecutive days from 22 August 2026.
Groundwater monitoring is planned monthly for six months. The replies do not say when those six months begin.
Neither written reply, of 14 September or 23 October, publishes any test result. The results will decide whether more containment or rehabilitation is needed.
DWS sent engineers from its dam-safety regulation unit and officials of the Limpopo-Olifants Catchment Management Agency to the site. Its 17 August statement says it told the mine verbally to stop depositing tailings in all its dams during the investigation.
Officials have given no volume for the spill and no clean-up cost. The memo says costs and environmental damage will be set after the forensic investigation.

How It Compares With Jagersfontein and Brumadinho
A tailings dam at the Jagersfontein diamond mine in the Free State province collapsed on 11 September 2022. A parliamentary question of 14 September cited that disaster and asked whether North West tailings dams would be audited.
The department did not confirm any audit of other North West dams. It said it will decide on further assessments, and set each facility’s risk profile, once the investigations are complete.
In Brazil, a Vale tailings dam at Brumadinho collapsed on 25 January 2019 and killed about 270 people. Dikwena has no reported casualties, but both cases turn on whether regulators knew a dam was at risk.
The same statement says Pemmy Majodina, the water minister, renewed her call for owners of qualifying dams to register them. The National Water Act sets the criteria.
What It Means for You
Chromium goes into stainless steel, but the official replies give no figure for lost chrome output. No price effect is confirmed, so US buyers should watch company statements rather than assume a supply shock.
For companies with South African mining exposure, the unregistered-dam finding points to tougher scrutiny of tailings registers. The department has also issued a guideline for a mandatory code of practice on mine residue deposits.
Related Rio Times coverage includes stolen South African chrome in stainless steel and South Africa’s natural resources. More is on the Southern Africa hub and in Africa: The New Scramble.
What to Watch Next
- The Section 60 inquiry result: the memo says three months, but no start or end date is published.
- Any decision by the Principal Inspector of Mines to let Dikwena restart deposits; no date is set.
- Monthly groundwater results; none have been published.
- Further written replies from the minerals minister in Parliament, which so far came on 14 September and 23 October.
What Is Not Known
No spill volume, clean-up cost, penalty or water-test result has been published. The cause stays preliminary until the Section 60 inquiry reports.
Press reports quote Samancor Chrome’s chief executive accepting responsibility and naming a contractor on part of the operation. That is unconfirmed at an official source, as is whether the minister adopts the memo’s unregistered-dam finding.
The scope of the suspension is unclear, because the replies name both Dikwena Chrome and Samancor. The department gave no date for its instruction, and no deadline is set for the investigations.
Frequently Asked Questions
What happened at the Samancor tailings dam near Brits?
The northern wall of Compartment 1B at Dikwena chrome mine failed at about 5:30 p.m. on 13 August 2026. Almost all the stored tailings escaped, and no casualties were reported.
What caused the Samancor tailings dam collapse?
The mineral department cites persistent seepage near the wall, weak monitoring and engineering work that was not done. The Section 60 inquiry has not yet reported.
Has Samancor been fined or charged?
No penalty or charge has been announced as of 3 November 2026. The department says penalties or prosecution will be considered after its inquiry ends.
Can Dikwena mine put tailings back into its dams?
Not yet. Deposits stay suspended until required measures are in place and the Principal Inspector of Mines accepts a presentation.
Sources: Minister of Mineral and Petroleum Resources, written reply NW5107 to the National Assembly, 23 October 2026; Written reply NW4679, 14 September 2026 (water testing and rehabilitation plan); reply NW4744 of the same date covers the Section 31L notice; Ministry of Mineral and Petroleum Resources memorandum on NCOP question 1032, 8 September 2026; Statement of the Department of Water and Sanitation, published by the South African government, 17 August 2026; all accessed 3 November 2026.
This article was produced by The Rio Times’ automated AI newsroom. Editorial responsibility: Matthias Camenzind, Publisher and Editor-in-Chief. The Rio Times also runs Ask Rio Times, which answers from 100,000+ of our own articles, the daily Latin America Power Map, and prediction-market odds on elections and markets.. How we use AI · Report an error
Critical Minerals in Africa
- Africa’s Critical Minerals 2026: Who Holds What and Why
- DR Congo Explained 2026, Its War, Cobalt and Politics
- Zambia Explained: The Country, Its Copper Economy, Its Politics and What to Watch
- The Lobito Corridor: A New Railway for African Copper