INFRASTRUCTURE · COLOMBIA
Key Facts
- —The country Colombia is a close US partner on security and trade. Bogotá, its capital and largest city, is still waiting for its first metro line.
- —Why it matters Line 1 is built by Metro Línea 1, a consortium made up mostly of Chinese companies. The national government pays 70% of the cost (Presidential Office for Bogotá, 4 October 2026).
- —Why now On 4 October Mayor Carlos Fernando Galán said stations, communications systems and public space are lagging. He and the national government asked the builder for more workers.
- —What happened The Empresa Metro de Bogotá put Line 1 at 82.33% complete on 31 August 2026, against 86.79% in its early schedule (manager Leonidas Narváez, Caracol Radio, 4 October).
- —The numbers 23.9 km and 16 stations; 18 km of viaduct built and 19 of 30 trains in Bogotá (city government, September 2026).
- —What it means for you Visitors will rely on TransMilenio buses and taxis for some time yet. Trial runs are planned from 14 September 2027, paid service from March 2028.
- —Still open Whether the consortium adds staff, and whether the station gap closes before the viaduct is finished, expected in January or February 2027.
The Bogotá metro, the biggest transport project in Colombia and one built mainly by Chinese companies, is running about 4.5 points behind its early schedule. Bogotá’s mayor and the national government have both now told the builder to put more workers on site.
For US readers, the line is one of the most visible Chinese-built works in a close US security partner. The warning came on Sunday 4 October, with the line still due to open in 2028.
What the Mayor and the National Government Asked For
Mayor Carlos Fernando Galán, a centrist who has run Bogotá since January 2024, raised the alarm in a Caracol Radio interview reported on Sunday. He said the works remain within what he called a tolerable margin of delay, but only just.
“Some things are further ahead than they should be, others are behind,” he said. If those delays are not corrected, he warned, the project could enter a problematic situation.
Galán named the stations, the communications systems and the public space around the line as the weak points. He said he had asked the concessionaire Metro Línea 1, by letter and in other messages, to add staff.
Clara Lucía Sandoval, a former Bogotá city councillor who heads the Presidential Office for Bogotá, made the same request on X the same day. She called on the builder to hire the personnel needed to cut the risk of delay.
Sandoval added that the nation contributes 70% of the funding for Line 1. The calendar, she said, must be met.
Sandoval was appointed in August by President Abelardo de la Espriella, a conservative lawyer who took office on 7 August 2026. Both messages point the same way, which is unusual: Bogotá often clashed with his predecessor, the leftist Gustavo Petro, over the metro’s design and funding.
Where the Gap Sits
The official figure is the one the city published in September. Line 1 stood at 82.33% complete on 31 August 2026, according to the Empresa Metro de Bogotá, the city-owned company in charge of the project.
Leonidas Narváez, the metro company’s manager, told Caracol Radio that the early schedule had foreseen 86.79% by the same date. That leaves a gap of about four and a half points.

Narváez said the main problem is the station buildings. He listed masonry, finishes and internal networks as the tasks that need more capacity and more workers.
The heavy structures are further along. The viaduct passed 18 kilometres on 12 September, three quarters of the 23.9 kilometre route.
More than nine kilometres of double track has been laid on top of it. Nineteen of the 30 trains are already in Bogotá. Galán expects the viaduct to be finished around January or February 2027.
A Tight Final Stretch
Galán described the coming months as a critical stage, the finishing work. The challenge, he said, is that viaduct, stations, trains and rail systems must now be completed and joined at once.
The current timetable has trial running, known locally as marcha blanca, starting on 14 September 2027. Paid passenger service would follow six months later, in March 2028.
Narváez said the present deviations can still be recovered if the consortium changes its pace. Neither the city nor the metro company has announced any change to the opening date.
On Monday Narváez told El Espectador the viaduct should be finished in January. He put the train depot and workshop yard at 94% complete, ahead of plan.
The city’s own audit office, the Contraloría de Bogotá, has monitored the project since 2021. It opened a new audit with site inspections during 2026.
The line also has a successor in the queue. Bogotá is also tendering Line 2, as covered in Bogotá Metro Line 2 Bids Are Due Monday After a Failed First Tender.
Why a Chinese Builder Matters Here
Metro Línea 1 is made up mostly of Chinese companies, and the 30 trains were built in China. Colombia deepened its Beijing ties in 2025, as set out in Colombia’s 2025 China Turn: What Joining the Belt and Road Really Changes.
Galán was measured, saying dialogue with the builders is constant even when they argue back. His message, he said, is that the work must be finished.
For Washington, a delivery on time would show Chinese contractors can complete a large project in a partner country. A slip would feed the opposite argument, in a region where that debate is live.
What It Means for You
For travellers, nothing changes yet. Visitors to Bogotá will rely on TransMilenio buses, taxis and ride apps until paid metro service starts, planned for March 2028.
For US investors and policymakers, Line 1 is a test case for Chinese contractors in a close US partner. Its record on a flagship project, 70% paid for by the national government, will feed the debate over Chinese building in Latin America.
For companies bidding on Line 2, the dispute is a signal that Bogotá and the national government are now willing to put public pressure on a builder.
What Is Not Known
The consortium had not answered the mayor or the presidential office publicly by Monday afternoon. It is not known how many extra workers, if any, it will bring in.
The metro company has not yet published progress figures for September. Those numbers will show whether the gap with the schedule has narrowed or widened.
It is also unclear whether any delay to the stations would move the September 2027 trial date. So far, both the city and the metro company say March 2028 stands.
When will the Bogotá metro open?
The city and the Empresa Metro de Bogotá plan trial runs from 14 September 2027 and paid passenger service from March 2028. Neither date has been changed after the mayor’s warning on 4 October 2026.
Who is building Bogotá Metro Line 1?
The concessionaire is Metro Línea 1, a consortium made up mostly of Chinese companies. The national government pays 70% of the project and the city the rest, according to the Presidential Office for Bogotá.
How far behind is the project?
On 31 August 2026 the line was 82.33% complete, against 86.79% in the early schedule, according to the metro company’s manager. The mayor says that is still within a tolerable margin.
Sources: Caracol Radio, interview with Mayor Carlos Fernando Galán and statements by Leonidas Narváez and Clara Lucía Sandoval, 4 October 2026; Portafolio, 5 October 2026; Semana, 5 October 2026; El Espectador, interview with Leonidas Narváez, 5 October 2026; Alcaldía de Bogotá, progress report at 31 August 2026; Empresa Metro de Bogotá, Line 1 stations; Publimetro, Sandoval appointment, 25 August 2026.